Govt Moves to Revive Delayed MEX II Project
The long-delayed Maju Expressway extension project (MEX II), aimed at connecting Putrajaya to the Kuala Lumpur International Airport (KLIA), is back in the spotlight as the Malaysian government intensifies efforts to resolve critical issues stalling it.
According to Bernama, Works Minister Datuk Seri Alexander Nanta Linggi confirmed that his ministry will collaborate closely with relevant stakeholders to address the project’s persistent delays.
He went on to add, “MEX II, as everyone is aware, is facing challenges in reaching completion. However, the good news is that all relevant parties, including the Finance Ministry, the Works Ministry, and the Public Works Department, are working together to help resolve the issue.”
Construction on the 18 KM expressway began in 2016 and was originally scheduled for completion in 2019. The project has since been plagued by financial challenges, incomplete work, and more recently, legal scrutiny.
According to The Edge, the project was financed by RM1.3 billion in debt raised in 2016 by Maju Group, owned by tycoon Tan Sri Abu Sahid Mohamed. Now, nearly a decade later, only RM30 million remains - with RM29 million already pledged to banks - and the highway remains unfinished.
The MEX II project has been under receivership since May 2022, leaving bondholders in limbo and the government facing tough decisions.
Further complicating matters, the Malaysian Anti-Corruption Commission (MACC) is currently investigating the concessionaire for allegedly submitting false claims amounting to RM416 million.
The parent expressway, the 26-KM Maju Expressway (MEX), which connects Kuala Lumpur to Putrajaya, has fulfilled its role as a critical transport artery since opening nearly 18 years ago. But its incomplete sibling, MEX II, remains a "thorn" for Maju Group and a lingering infrastructure puzzle for the government.
With government intervention stakeholders hope the long-stalled MEX II project can finally shift gears toward completion - provided that financial, legal, and operational hurdles can be overcome in time.
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VPN7617
SELANGOR
BSH1407
JOHOR
JYF1913
PULAU PINANG
PRT3486
PERAK
APA2951
PAHANG
CFD2141
KEDAH
KGB7996
NEGERI SEMBILAN
NEG7284
KOTA KINABALU
SJM1550
KUCHING
QAB9276L
Last updated 16 Aug, 2025
Fuel Price
Petrol
RON 95
RM 2.05
RON 97
RM 3.13
-0.04
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.90
-0.04
EURO 5 B7
RM 3.10
-0.04
Last updated 14 Aug, 2025
Related News
R&M, Govt in Final Talks to Revive Stalled MEX II Highway
The government and sukuk holders are finalising a rescue plan for the stalled MEX II Highway.
13-08-2025
MACC: RM32 Million Seized From ‘Tan Sri’ Over Expressway Scandal
MACC seizes RM32 Million in luxury assets from a highway concessionaire amid a probe into the misuse of sukuk funds.
30-05-2025
R&M, Govt in Final Talks to Revive Stalled MEX II Highway
The government and sukuk holders are finalising a rescue plan for the stalled MEX II Highway.
13-08-2025
Govt Looking To Revive MEX II Highway With New Completion Plan
The government is working with bondholders to restart the long-delayed MEX II Highway.
01-08-2025
MACC: RM32 Million Seized From ‘Tan Sri’ Over Expressway Scandal
MACC seizes RM32 Million in luxury assets from a highway concessionaire amid a probe into the misuse of sukuk funds.
30-05-2025
JKR Set To Use Solar Lights In Over 1,000 Accident Hotspots
JKR steps up safety measures with nationwide solar lighting at over 1,000 accident hotspots.
11-08-2025
RM20 Million Allocated to Upgrade Federal Highway Motorcycle Lanes – KKR
A total of RM20 million will be allocated to upgrade the motorcycle lanes on the Federal Highway, the Works Ministry says.
08-08-2025
RM25 Million Allocated to Light Up Dark Federal Roads – KKR
The Works Ministry has allocated RM25 million to light up dark federal roads to prevent future accidents.
07-08-2025
Latest News
KLIA Aerotrain To Undergo Overnight Works Starting Aug 18
KLIA's Aerotrain service will be replaced by buses nightly from midnight to 5 am, starting August 18, for two weeks due to scheduled maintenance.
16-08-2025
Omoda | Jaecoo Hits New Heights with 570,000 Sales
Omoda | Jaecoo cements its status as one of the fastest-growing automotive brands, with Malaysia poised to be its RHD hub.
16-08-2025
2025 PJ Half Marathon Road Closures Start Tomorrow – Aug 16
PJ Half Marathon will see multiple road closures from Saturday evening.
15-08-2025
Perak Cop Dies After Motorcycle Clips Lorry, Driver Missing
A 23-year-old policeman died in Bagan Serai after his motorcycle clipped a lorry. Police are now searching for the driver.
15-08-2025
KTMB’s MyRailLife Pass Clocked Over 628,000 Free Rides
KTMB’s MyRailLife Pass has clocked over 628,000 free rides for students and persons with disabilities this year.
15-08-2025
Malaysia Imports RM3.53 Billion In Tyres To Meet Demand
Malaysia imported RM3.53 billion worth of tyres last year to meet demand of 22 million units.
15-08-2025
JPJ Seizes Four Singapore-Registered Cars for Illegal e-Hailing
The Road Transport Department seized four Singapore-registered vehicles for illegal ride-hailing services.
15-08-2025
Selangor May Fine Men RM500 For Parking In Women-Only Bays
Selangor may impose RM500 fines and towing for men misusing women-only parking bays.
14-08-2025
Show More
trending_flat