Govt Moves to Revive Delayed MEX II Project
The long-delayed Maju Expressway extension project (MEX II), aimed at connecting Putrajaya to the Kuala Lumpur International Airport (KLIA), is back in the spotlight as the Malaysian government intensifies efforts to resolve critical issues stalling it.
According to Bernama, Works Minister Datuk Seri Alexander Nanta Linggi confirmed that his ministry will collaborate closely with relevant stakeholders to address the project’s persistent delays.
He went on to add, “MEX II, as everyone is aware, is facing challenges in reaching completion. However, the good news is that all relevant parties, including the Finance Ministry, the Works Ministry, and the Public Works Department, are working together to help resolve the issue.”
Construction on the 18 KM expressway began in 2016 and was originally scheduled for completion in 2019. The project has since been plagued by financial challenges, incomplete work, and more recently, legal scrutiny.
According to The Edge, the project was financed by RM1.3 billion in debt raised in 2016 by Maju Group, owned by tycoon Tan Sri Abu Sahid Mohamed. Now, nearly a decade later, only RM30 million remains - with RM29 million already pledged to banks - and the highway remains unfinished.
The MEX II project has been under receivership since May 2022, leaving bondholders in limbo and the government facing tough decisions.
Further complicating matters, the Malaysian Anti-Corruption Commission (MACC) is currently investigating the concessionaire for allegedly submitting false claims amounting to RM416 million.
The parent expressway, the 26-KM Maju Expressway (MEX), which connects Kuala Lumpur to Putrajaya, has fulfilled its role as a critical transport artery since opening nearly 18 years ago. But its incomplete sibling, MEX II, remains a "thorn" for Maju Group and a lingering infrastructure puzzle for the government.
With government intervention stakeholders hope the long-stalled MEX II project can finally shift gears toward completion - provided that financial, legal, and operational hurdles can be overcome in time.
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VPU5129
SELANGOR
BSJ3255
JOHOR
JYH7665
PULAU PINANG
PRU5836
PERAK
APB6014
PAHANG
CFD6737
KEDAH
KGC5174
NEGERI SEMBILAN
NEH3095
KOTA KINABALU
SJM9999*
KUCHING
QAB3079M
Last updated 08 Oct, 2025
Fuel Price
Petrol
RON 95
RM 2.60
+0.55
RON 97
RM 3.21
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.93
EURO 5 B7
RM 3.13
Last updated 30 Sep, 2025
Related News
R&M, Govt in Final Talks to Revive Stalled MEX II Highway
The government and sukuk holders are finalising a rescue plan for the stalled MEX II Highway.
13-08-2025
MACC: RM32 Million Seized From ‘Tan Sri’ Over Expressway Scandal
MACC seizes RM32 Million in luxury assets from a highway concessionaire amid a probe into the misuse of sukuk funds.
30-05-2025
R&M, Govt in Final Talks to Revive Stalled MEX II Highway
The government and sukuk holders are finalising a rescue plan for the stalled MEX II Highway.
13-08-2025
Govt Looking To Revive MEX II Highway With New Completion Plan
The government is working with bondholders to restart the long-delayed MEX II Highway.
01-08-2025
MACC: RM32 Million Seized From ‘Tan Sri’ Over Expressway Scandal
MACC seizes RM32 Million in luxury assets from a highway concessionaire amid a probe into the misuse of sukuk funds.
30-05-2025
East-West Rail Link Across Titiwangsa Could Take 10-20 Years - Nanta
The east-west rail project crossing the Titiwangsa Range could take 10 to 20 years to complete.
16-09-2025
Nanta: MYJalan Will Become National Road Database
MYJalan app set to evolve from complaint channel to key tool in managing Malaysia’s road network.
29-08-2025
NPE Extension Deal Inked, RM1.4b+ Project Starts Q4 2025
NPE extension project costing over RM1.4b promises to cut travel time by up to 25 minutes and integrate with KL’s Traffic Master Plan 2040.
28-08-2025
Latest News
Govt Still Weighing Options For KL–Singapore HSR Project - Loke
Malaysia is still reviewing options for the KL–Singapore HSR, with a final model yet to be determined.
08-10-2025
Budi95: KPDN Now Empowered to Check MyKad
KPDN officers are now authorised to check MyKad to ensure the smooth rollout of the BUDI95 subsidy.
08-10-2025
No Ban On SUVs For E-Hailing Registration - Loke
Loke clarified that SUVs remain eligible for e-hailing services, dismissing recent reports of registration restrictions as inaccurate.
07-10-2025
AHTV Succeeds Shah Alam As Proton’s Next-Generation Manufacturing Hub
AHTV poised to position Proton as regional export hub and boost local supplier networks through high-value jobs.
07-10-2025
Omoda | Jaecoo Malaysia Celebrates 20,000th Unit Delivery Milestone
Just over a year since its market debut, Omoda | Jaecoo Malaysia has delivered its 20,000th vehicle here in Malaysia.
07-10-2025
Over 7,000 Commercial Vehicle Safety Audits Completed - Loke
Loke told Parliament that JPJ has audited more than 7,000 commercial vehicle operators, with a new digital system set by 2027.
07-10-2025
Ops Grip: MACC Exposes Fake Labels, Erased Barcodes and Smuggled Tyres
MACC’s Op Grip exposes multi-million Ringgit racket involving fake labels, smuggled tyres and money laundering.
07-10-2025
Jalan Reko Upgrade Aims To Curb Floods, Ease Traffic By 2028
The RM68 million road upgrade in Kajang aims to resolve long-standing flash flood and congestion issues.
07-10-2025
Show More
trending_flat