LRT3: 33 Problems Identified, Solutions Ready, Tests Ongoing
-full_normal.jpg)
Although solutions have been developed for all 33 technical issues flagged on the LRT3 Shah Alam Line, the systems have yet to complete full testing to confirm they perform reliably under operating conditions.
According to Sinar Harian, Shah Alam Line COO Mohd Ariffin Idris said the project team is now focused on extended and continuous testing, aimed at validating whether the fixes introduced truly resolve the problems encountered earlier.

He explained that while corrective measures are already in place, they must be proven through rigorous trials before the line can be considered operationally ready. Testing, he said, is still ongoing and remains a critical phase of the project.
A major area of attention is the system software, which is being upgraded to the latest baseline to ensure it can cope with both existing faults and any new issues that may emerge during testing.
Mohd Ariffin added that failure-free run (FFR) testing is currently being carried out on all trains assigned to the Shah Alam Line. A total of 22 trains must undergo the process, with each test monitored by the Land Public Transport Agency (APAD) as part of standard regulatory requirements.

Even trains that have already clocked the required mileage are not exempt, as they still need to be reassessed to ensure every technical and safety criterion is fully satisfied.
According to him, the line cannot open to passengers until all trains pass FFR testing and the entire system, including infrastructure and signalling, is confirmed to be fully complete and stable.
Testing is conducted around the clock, including overnight sessions, with specialists from original equipment manufacturers involved to address specific technical challenges. These include signalling systems supplied from Germany and rolling stock sourced from China.
He noted that uncovering new issues during dry runs is not unusual, and any problems identified will be rectified before further testing continues to ensure long-term stability.

As for the start of public operations, Mohd Ariffin said an official projection is expected to be announced by senior management around January next year, once testing reaches a more conclusive stage.
Earlier reports by Prasarana Malaysia Bhd revealed that the 33 technical issues, largely linked to software errors and system disruptions, were identified during two and a half months of testing and were a key reason behind delays to the line’s launch.
Among the problems detected were trains failing to stop precisely at platforms, issues with door operations, incorrect speed settings, failures in automatic train movement, and unintended train movement when the system should have remained static.
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VQY9148
SELANGOR
BSQ3215
JOHOR
JYX2059
PULAU PINANG
PSC4698
PERAK
APH6301
PAHANG
CFG5817
KEDAH
KGG1844
NEGERI SEMBILAN
NEK4752
KOTA KINABALU
SJR9999*
KUCHING
QAB8244N
Last updated 26 May, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
Prasarana to Reveal LRT3 Launch Date This April—Here’s Everything We Know So Far
The wait for the LRT3 Shah Alam Line is entering its final stretch. After months of "will they, won't they" speculation, Prasarana has officially pointed to April 2026 as the month of truth.
05-03-2026
LRT3 Set for June 2026 Launch, Contractor Faces RM2.73 Million Daily Penalty for Delays
The Shah Alam LRT3 line is targeted to begin operations by June 2026, with contractors liable for RM2.73 million per day in delay penalties.
24-02-2026
LRT3 Shah Alam Line Expected To Open In June
After years of delays, the LRT3 Shah Alam Line could finally begin operations in June, pending final safety tests.
05-02-2026
Shah Alam LRT Launch Delayed To Avoid Another 2021 Kelana Jaya Crash
Prasarana delays the Shah Alam LRT opening, prioritising passenger safety and thorough testing after past LRT mishaps.
15-12-2025
LRT3 Won’t Launch This Year As Glitches Persist, No New Date Set
The LRT3 faces another delay after 33 software glitches were discovered during fault-free tests and no new opening date has been fixed yet.
12-12-2025
LRT3 Enters Final Testing Phase, Govt Targets Dec 31 Opening
LRT3 line is now in its final round of safety and reliability tests, with its launch date hinging on Dec results.
18-11-2025
Shah Alam LRT Delayed Again, December Now In Sight
The Shah Alam LRT may miss its September deadline, with Prasarana now aiming for a December launch pending crucial safety tests.
26-08-2025
LRT3 Shah Alam Line Opening Could Be Delayed to Oct 31 – Report
The LRT3 Shah Alam line opening could be delayed until Oct 31 instead of the planned launch date of Sept 30.
04-08-2025
Latest News
Anthony Loke Forces Vulnerable JPJ Systems Back Online Despite Active Fraud Exposure
Transport Minister Anthony Loke instructs JPJ to postpone its online vehicle transfer system upgrade to the long weekend, keeping the system active despite major fraud warnings.
25-05-2026
The End of Crazy Price Drops: A Market Analyst Says EV Pricing Is Finally Becoming "Rational" In Malaysia
A CIMB Securities automotive analyst reveals why MITI’s new July 1 CBU EV policy will end aggressive price wars and push imported EV showroom prices past RM300k.
25-05-2026
10 BIG Reasons To Visit KLIMS 2026 Even If You’re Not A Car Enthusiast
Discover 10 massive reasons to visit KLIMS 2026 at MITEC from June 12–21, featuring free weekday entry, live RIUH concerts, a Pokémon truck, simulators, and smart transit options.
21-05-2026
Game Over, Tonto! JPJ Teams Up With MACC To Hunt Down Secret Lorry Informant Syndicates
JPJ partners with the MACC to dismantle a secret "tonto" sticker syndicate helping heavy commercial lorries evade law enforcement checkpoints.
21-05-2026
254,000 Cars Sold So Far In 2026! A Look At Which Malaysian States Are Freezing In Traffic
Over 254,000 new cars have hit Malaysian roads in the first 4 months of 2026. Discover how MAA’s April sales surged 17% as vehicle production ramped up post-Raya.
20-05-2026
We're Lagging Behind! MAA Reminds MITI That Malaysia Is Already Losing The EV Race To Our SEA Neighbours
MAA President Mohd Shamsor warns MITI that Malaysia's sub-4% EV sales lag far behind Thailand and Vietnam, urging a phased approach to new CBU rules.
20-05-2026
Dataran DBKL 'Flooded' By 1,000+ Runners For KLIMS Run 2026!
Over 1,000 runners took over Dataran DBKL for the first-ever KLIMS Run 2026, snagging free tickets to the upcoming June mobility show and a MacBook Neo.
20-05-2026
Marketing Gone Wrong! 15 People Land In Lockup After Rented Hilux Flare Stunt Fails To Impress Cops
KL police have arrested 15 people over a dangerous late-night flare stunt in Bukit Bintang, which was a marketing promo for a Dengkil clothing store's 6th anniversary.
19-05-2026
Show More
trending_flat