LRT3: 33 Problems Identified, Solutions Ready, Tests Ongoing
-full_normal.jpg)
Although solutions have been developed for all 33 technical issues flagged on the LRT3 Shah Alam Line, the systems have yet to complete full testing to confirm they perform reliably under operating conditions.
According to Sinar Harian, Shah Alam Line COO Mohd Ariffin Idris said the project team is now focused on extended and continuous testing, aimed at validating whether the fixes introduced truly resolve the problems encountered earlier.

He explained that while corrective measures are already in place, they must be proven through rigorous trials before the line can be considered operationally ready. Testing, he said, is still ongoing and remains a critical phase of the project.
A major area of attention is the system software, which is being upgraded to the latest baseline to ensure it can cope with both existing faults and any new issues that may emerge during testing.
Mohd Ariffin added that failure-free run (FFR) testing is currently being carried out on all trains assigned to the Shah Alam Line. A total of 22 trains must undergo the process, with each test monitored by the Land Public Transport Agency (APAD) as part of standard regulatory requirements.

Even trains that have already clocked the required mileage are not exempt, as they still need to be reassessed to ensure every technical and safety criterion is fully satisfied.
According to him, the line cannot open to passengers until all trains pass FFR testing and the entire system, including infrastructure and signalling, is confirmed to be fully complete and stable.
Testing is conducted around the clock, including overnight sessions, with specialists from original equipment manufacturers involved to address specific technical challenges. These include signalling systems supplied from Germany and rolling stock sourced from China.
He noted that uncovering new issues during dry runs is not unusual, and any problems identified will be rectified before further testing continues to ensure long-term stability.

As for the start of public operations, Mohd Ariffin said an official projection is expected to be announced by senior management around January next year, once testing reaches a more conclusive stage.
Earlier reports by Prasarana Malaysia Bhd revealed that the 33 technical issues, largely linked to software errors and system disruptions, were identified during two and a half months of testing and were a key reason behind delays to the line’s launch.
Among the problems detected were trains failing to stop precisely at platforms, issues with door operations, incorrect speed settings, failures in automatic train movement, and unintended train movement when the system should have remained static.
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VQM1970
SELANGOR
BSM5340
JOHOR
JYR5875
PULAU PINANG
PRY7324
PERAK
APF3221
PAHANG
CFF3478
KEDAH
KGE3875
NEGERI SEMBILAN
NEJ5389
KOTA KINABALU
SJQ3151
KUCHING
QAB2485N
Last updated 17 Feb, 2026
Fuel Price
Petrol
RON 95
RM 2.54
RON 97
RM 3.10
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.99
+0.03
EURO 5 B7
RM 3.19
+0.03
Last updated 12 Feb, 2026
Related News
LRT3 Shah Alam Line Expected To Open In June
After years of delays, the LRT3 Shah Alam Line could finally begin operations in June, pending final safety tests.
05-02-2026
Shah Alam LRT Launch Delayed To Avoid Another 2021 Kelana Jaya Crash
Prasarana delays the Shah Alam LRT opening, prioritising passenger safety and thorough testing after past LRT mishaps.
15-12-2025
LRT3 Won’t Launch This Year As Glitches Persist, No New Date Set
The LRT3 faces another delay after 33 software glitches were discovered during fault-free tests and no new opening date has been fixed yet.
12-12-2025
LRT3 Enters Final Testing Phase, Govt Targets Dec 31 Opening
LRT3 line is now in its final round of safety and reliability tests, with its launch date hinging on Dec results.
18-11-2025
Shah Alam LRT Delayed Again, December Now In Sight
The Shah Alam LRT may miss its September deadline, with Prasarana now aiming for a December launch pending crucial safety tests.
26-08-2025
LRT3 Shah Alam Line Opening Could Be Delayed to Oct 31 – Report
The LRT3 Shah Alam line opening could be delayed until Oct 31 instead of the planned launch date of Sept 30.
04-08-2025
LRT3 Enters Final Testing Phase, Govt Targets Dec 31 Opening
LRT3 line is now in its final round of safety and reliability tests, with its launch date hinging on Dec results.
18-11-2025
Shah Alam LRT Delayed Again, December Now In Sight
The Shah Alam LRT may miss its September deadline, with Prasarana now aiming for a December launch pending crucial safety tests.
26-08-2025
Latest News
2026 Car Tint Guide: Top Brands Malaysians Recommend
We’ve rounded up the 5 best car tints to keep your cabin comfy, protect your skin, and maintain privacy.
16-02-2026
Tesla Malaysia Completes First Vehicle Delivery in East Malaysia
Tesla Malaysia has completed its first official vehicle delivery in East Malaysia at its pop-up experience centre in Kuching.
16-02-2026
MAA: Jan 2026 New Vehicle Sales Down by 29% at 64,298 Units
Jan 2026 saw a total of 64,298 units of new vehicles being sold, marking a 29% decrease over the previous month.
16-02-2026
Jetour Malaysia Launches Owners Club, T2 Previewed at First Gathering
JETOUR Malaysia launches its owners club with a Genting convoy drive and exclusive preview of the upcoming T2 SUV.
16-02-2026
West Coast Expressway Expects 35% Traffic Surge for CNY
WCE anticipates 160,000 vehicles daily during the Chinese New Year festive rush, a 35% increase compared to last year.
14-02-2026
Chery Malaysia’s 2026 Plans Detailed – Four New Models, 30% CSH Sales, Gen 4 Outlet
Chery Malaysia’s 2026 vision will see the automaker launching four new models, and 30% of its sales coming from CSH models.
13-02-2026
Zeekr Malaysia Set To Release Three New Models In 2026
Zeekr Malaysia confirm plans to release three new models locally this year, could include 9X as ‘new flagship’ offering too.
13-02-2026
Traffic Nightmare Hits Klang Valley, Economy Feels the Burn
Commuters face unprecedented jams as KL and Selangor grind to a halt this festive season.
13-02-2026
Show More
trending_flat