The Govt Wants 30,000 EV Chargers By 2030, But We Barely Hit Half Of Our Last Target

⚡ The New Milestone: MITI has set an ambitious new target of 30,000 public EV chargers across Malaysia by 2030.
📉 The Past Miss: This follows a massive shortfall in our previous roadmap, where the country missed its 2025 target of 10,000 chargers, managing to deploy only about 5,600.
🔌 The Real Bottleneck: The primary delay isn't a lack of real estate or equipment—it’s a severe power grid constraint. Setting up high-powered DC fast chargers requires entirely new TNB electrical substations to prevent local grid overloads.
If you currently drive an electric vehicle (EV) in Malaysia, or you've been hovering your finger over the "buy" button on a new one, you already know the absolute pain of looking for a working public charger outside the Klang Valley. Range anxiety is very real, and the struggle to find a plug that isn’t broken or occupied is a daily topic in local car groups.
Well, the government heard us complaining. During a session in the Dewan Rakyat, Deputy Investment, Trade and Industry Minister Sim Tze Tzin dropped a massive new milestone: The government is now aiming to build 30,000 EV charging stations across Malaysia by the year 2030.
On paper, that sounds fantastic. But if you've been tracking Malaysia's green transition, a sudden wave of skepticism is completely justified. Why? Because our previous milestone was to hit 10,000 public chargers by 2025, and official data shows we only managed to roll out around 5,600.
So, how exactly are we going to build more than five times that amount in the next few years when we barely cleared half of our last target?
Turns out, there is a massive behind-the-scenes bottleneck that has nothing to do with finding empty parking spaces.
The Real Reason Your Favourite Mall Doesn't Have Fast Charging
Most everyday drivers assume that installing a high-powered EV charger is as simple as mounting a box to a concrete wall and plugging it into the building’s existing electrical room. MITI just pulled back the curtain on why that's a complete myth.

According to Deputy Minister Sim, expanding our network isn't a retail real-estate problem, it’s a power grid capacity crisis. High-voltage Direct Current (DC) fast chargers pull an immense amount of electricity. If you just hook them up to normal commercial lines, you risk overloading local setups.
To fix this, the government is working with Tenaga Nasional Berhad (TNB) to construct entire, dedicated power substations solely to feed these upcoming charging hubs.
💡 The Core Problem: Expanding Malaysia's EV infrastructure isn't a space allocation issue, it's a severe power grid capacity crisis. High-output DC fast chargers pull massive current, requiring full substation additions to avoid localized blackouts.
In short: No new TNB substations, no fast chargers. This massive engineering hurdle is the main reason why operators haven't been able to expand into smaller towns as quickly as they wanted to.
Read: EV 'Fuel' Hike: How To Use TNB’s Off-Peak Rates To Dodge The Upcoming August Surcharge
The Push Beyond Major Cities
This grid upgrade cannot happen fast enough. During the parliamentary session, Kubang Pasu MP Datuk Dr Ku Abdul Rahman Ku Ismail pressured the ministry to stop focusing all the charging love exclusively on major metropolitan hubs like Kuala Lumpur and Penang.

The opposition urged the government to expand infrastructure to secondary towns like Sungai Petani and Alor Setar so that cross-country EV travel actually becomes viable for regular families. Furthermore, there are calls to collaborate with the Public Works Department and the Housing and Local Government Ministry to legally mandate EV chargers into residential developments, like apartments and condominiums, so high-rise residents aren't locked out of EV ownership.
If there are no substations, no party can build charging facilities as the power supply is insufficient. For charging points to function effectively, we need substations to supply sufficient direct current power.
— Sim Tze Tzin, Deputy MITI Minister (Dewan Rakyat)MITI has noted the suggestions, stating that while these foundational upgrades will take time, they are currently formulating fresh, targeted incentives for private Charging Point Operators (CPOs) to make building in smaller towns financially viable.
The roadmap to 30,000 chargers is officially laid out, but the success of our EV transition is no longer up to car manufacturers, it's resting entirely on how fast TNB can dig up roads and upgrade the national power grid.
Read: Updated 2026: Top 10 CPOs In Malaysia
Written By
Sofea Najmi
A Bachelor of English Language and Literature graduate with an obsession for the finer details. Sofea uses her background in translation to decode the technicalities of automotive innovation. She is dedicated to delivering impactful, meticulously researched articles that provide a narrative far beyond the spec sheet. LinkedIn: https://bit.ly/3C018vv
JPJ Running Numbers
KUALA LUMPUR
VRF3447
SELANGOR
BSR4610
JOHOR
J4295J
PULAU PINANG
PSD6194
PERAK
APJ6733
PAHANG
CFH1022
KEDAH
KGG9158
NEGERI SEMBILAN
NEK8526
KOTA KINABALU
SJS9307
KUCHING
QAB1664P
Last updated 08 Jul, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Latest News
The Govt Wants 30,000 EV Chargers By 2030, But We Barely Hit Half Of Our Last Target
MITI targets 30,000 public EV chargers in Malaysia by 2030, but we barely cleared half of our last target. Here is the power grid crisis causing the bottleneck.
08-07-2026
Perodua Claims 1,700 QV-E Bookings, But Data Shows Only 182 Are Actually Registered
A leaked equity report reveals a massive 1,700 booking backlog secured before the June price cut, directly contrasting slow JPJ registration data. Here is the real story behind the numbers.
08-07-2026
Is This The Next Bezza? Theottle’s ‘Situ’ Render Takes The Perodua C2 Concept To The Next Level
Is the new Perodua ‘Situ’ the electric Bezza we’ve been waiting for? We break down Theottle's stunning render and how it evolves Perodua’s C2 concept into a future reality.
02-07-2026
Porsche Malaysia Quietly Replaces The RM575k Taycan With A Shocking RM775k Price Tag — Here’s Their Official Response
Porsche Malaysia secretly dropped a massive RM200k to RM410k price hike across the EV Taycan line overnight. Is it post-tax-holiday reality or tech inflation?
01-07-2026
Bermaz Just Scrapped Its Deepal Deal, And It Signals The End Of Cheap Imported EVs In Malaysia
Bermaz Auto has scrapped its Deepal deal. With new July 1st MITI rules now in effect, is the era of affordable imported EVs in Malaysia officially over?
01-07-2026
Tesla Malaysia Stays Cheap Despite MITI’s New July Ruling, But There’s A Catch
Tesla Malaysia prices remain steady despite new MITI import rules, but there's a catch. Find out why Tesla is exempt and what the removal of the one-time FSD purchase means for buyers.
01-07-2026
From Tanjong Malim To Bandar Seri Begawan: Proton e.MAS Expands Into Brunei
Proton e.MAS officially expands into Brunei through Grand Motors! See how our national carmaker is taking Malaysian-developed EV tech to the regional stage.
30-06-2026
The Great EV Clearance: Why You Need To Act Fast If You Want A ‘Budget’ EV In Malaysia
Starting July 1, 2026, new MITI rules on imported EVs could push prices over RM300k.
29-06-2026
Show More
trending_flat