MRT Putrajaya Line Phase Two Operational March 2023, Total Line Spans 56.2KM

Kumeran Sagathevan

Share via


Mass Rapid Transit Corporation Sdn Bhd (MRT Corp) just released a press statement to inform the general public that the construction works for MRT Putrajaya Line Phase Two from Kampung Batu MRT Station to Putrajaya Sentral MRT Station has been completed and is currently in the operational readiness phase.


The 38.7 km-long section of the Phase Two alignment, which consists of 15 elevated stations and 9 underground stations, is expected to be operational in March 2023. The test runs for this route was completed on 18 December 2022.


Once opened, the entire Putrajaya Line will house 36 stations spanning over 56.2 km and served by 49 units of four car train sets capable of carrying up to 1,200 passengers. Passengers would also have the option of hopping on to other existing rail lines at 10 different interchange stations.


The interchange stations are Kwasa Damansara (with Kajang MRT Line), Sungai Buloh (with KTM), Sri Damansara Timur (with KTM), Kampung Batu (with KTM), Titiwangsa (with Ampang & Sri Petaling LRT Lines, KL Monorail), Ampang Park (with Kelana Jaya LRT Line), Tun Razak Exchange (with Kajang MRT Line), Chan Sow Lin (with Ampang & Sri Petaling LRT Lines), Sungai Besi (with Sri Petaling LRT Line) and Putrajaya Sentral (with ERL and KLIA Transit Lines).




For the ease of passenger, there will be 5,870 parking bays made available across the 15 stations along the alignment. Having said that, technically the entire Klang Valleys train line still suffers from lack of efficient first and last mile connectivity which would help eliminate the dependence driving to these stations.  



Tagged:

MRT Putrajaya Line Phase 2
MRT Putrajaya Line
MRT corp
Mass Rapid Transit Corporation Sdn Bhd (MRT Corp)
Share This Article

Written By

Kumeran Sagathevan

More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!

Share via

Related News

Auto News

"Too early to assess Putrajaya MRT route on peak-hour congestion" - Loke

It is still too early to assess the effectiveness of Putrajaya's MRT service in reducing traffic congestion, says Loke.

07-04-2023
Auto News

MRT Putrajaya Line Free Ride Ends Tomorrow March 31

MRT Putrajaya Line free ride ends tomorrow on March 31.

30-03-2023
Auto News

PM Announces Free MRT Putrajaya Line Fares Until End Of March

PM inaugurated the full launch of MRT Putrajaya Line plus announced free fares starting March 16 to 31, 2023.

16-03-2023
Auto News

MRT Putrajaya Line Phase Two Expected To Lessen Traffic Congestion Heading To KL

MRT Putrajaya Line Phase Two is expected to reduce traffic congestion to the city centre.

13-03-2023
Auto News

RapidKL Is Upgrading The LRT, MRT & Monorail Audio System

RapidKL is upgrading the LRT, MRT and Monorail audio system in phases prior to the MRT Putrajaya Line Phase 2 opening.

07-03-2023
Auto News

MRT Putrajaya Line Fully Operational Starting 16 Mar 2023, 3PM

MRT Putrajaya Link (PYL) from Kwasa Damansara right up to Putrajaya Sentral would be fully operational starting 3pm, 16 Mar 2023

Auto News

Phase 2 Of The Putrajaya MRT Line 95% Completed - Prasarana

Phase 2 of the Putrajaya MRT Line is more than 95% complete, with a final test scheduled for the end of this month.

24-02-2023
Auto News

MRT Putrajaya Line Phase Two To Have 4 Interchange & 2 Connecting Stations

There will be 4 new interchange stations and 2 new connection stations added along the MRT Putrajaya Line.

Latest News

Auto News

42 Clauses Are Changing: M'sia Is Facing Its Biggest Road Law Overhaul Since 2020, And Yes, It Affects Your Saman

Malaysia is introducing 42 new clauses to the Road Transport Act in its biggest traffic law overhaul since 2020. Here is how it affects your fines and roadblocks.

19-06-2026
Auto News

Good News For 5 Million Perodua Owners! Don't Go To Outside Workshops As Service Prices Just Dropped

Thinking of visiting an outside mechanic? Perodua is slashing overall service maintenance parts and labor costs by 10% nationwide starting 19 June.

18-06-2026
Auto News

It’s Happening! After Years Of Delays, The LRT3 Is Finally Ready To Start Operations

The long-awaited LRT3 Shah Alam Line is officially set to begin operations by the end of this month, as confirmed by Transport Minister Anthony Loke.

18-06-2026
Auto News

No More Just 'Screwing Parts Together', Malaysia Wants Local Talents To Design The Next Big ASEAN Car Tech

At KLIMS 2026, Deputy Transport Minister Datuk Hasbi Habibollah urged Malaysia's automotive industry to evolve from car assemblers into technology creators.

18-06-2026
Auto News

It Costs Up To RM300K To Protect One School Zone, And The Government Is Inviting Private Companies To Step Up

Why does a single Safe School Zone cost up to RM300K to build? Transport Minister Anthony Loke breaks down the new physical 30km/h traffic-calming blueprint and why private companies are being asked to step up.

17-06-2026
Auto News

Prime, Premium, Or Premium Plus? 4 Major Differences Between The 3 Proton e.Mas 7 Tiers

Prime, Premium, or Premium Plus? We break down the 4 massive differences in battery range, price, and luxury features across the new Proton eMas 7 EV tiers.

12-06-2026
Auto News

15 Drug Records But Still Driving?! Malaysians Are Furious Over The Viral Penang Highway Triton Rampage

Shocking details emerge on the viral Mitsubishi Triton highway crash in Penang. The drugged driver has 17 prior convictions, leaving 18 cars damaged.

10-06-2026
Auto News

Don't Buy A Car Full Price! Perodua Just Quietly Slashed Prices On 5 Models & The Discounts Vanish After June 30

Perodua just quietly slashed prices on 5 popular models for June 2026! Check out the exact cash rebates for the Myvi, Ativa, Aruz, Bezza, and Axia here.

09-06-2026