LOKE : LRT3 86% Complete, To Begin Service 1 March 2025 - 67,000 Daily Capacity

Kumeran Sagathevan

Share via

LRT3-(1).jpg

Yesterday, Transport Minister YB Anthony Loke delivered an update on the Light Rail Transit 3 (LRT3) project's development. Loke reported that construction is progressing quickly, with completion at 86%, including the installation of the signalling system.

Currently, 22 sets of three-coach trains are being tested thoroughly. LRT3 operations are expected to begin on March 1, 2025, which is approximately 18 to 19 months from now. Loke expressed confidence in the project's successful implementation, emphasising the significance of collaboration among all stakeholders to fulfil the target deadline.

LRT3-(8).jpgLRT3-(7).jpg

The LRT3 is intended to assist nearly two million Klang Valley people, notably those living between Petaling Jaya and Klang.  As a densely populated and developed region, tens of thousands of passengers are expected to utilise the LRT3.

With a capacity to accommodate 18,630 passengers per hour per direction, the project will include two interchange stations.  Bandar Utama will connect the MRT Kajang Line to LRT3, while Glenmarie will connect the Kelana Jaya Line to LRT3. A flyover will connect these two stations, improving the system's overall connection.

LRT3-(3).jpg

Loke emphasised that the 22 train sets are all brand new, luxurious, and outfitted with environmentally friendly "green technology." They are currently in the last stages of testing to ensure their readiness for the approaching opening.

During a site visit to the depot and LRT3 operation control center, Loke personally conducted a test drive on the trial route using one of the trains. He emphasised that the LRT3 is an important addition to public transportation in the Klang Valley, with the goal of encouraging more people to use public transportation in the area.

LRT3-(4).jpg

Once completed, the LRT3 line would be approximately 37 kilometres long, with 2 km running underground. Over 2000 parking spots would be offered in 6 stations to assist travellers who choose to Park & Ride. The route would also service 67,000 people every day, with a 6-minute average wait time. 



Source: MalayMail


Gallery

Tagged:

Minister of Transport YB Anthony Loke
Light Rail Transit 3 (LRT3)
Mass Rapid Transit 3 (MRT3)
Share This Article

Written By

Kumeran Sagathevan

More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!

Share via

Related News

Auto News

Loke: KLIA Taxi Touting Betrays Nation’s Image

KLIA taxi touts overcharging tourists by up to RM400 are tarnishing Malaysia’s reputation.

Auto News

Use Of Three-Wheelers For Agriculture Subject To Regulations - MOT

MOT says three-wheeled motorcycles may be used for farming, but only with full compliance to safety and licensing rules.

25-08-2025
Auto News

Govt Plans to Add 50 New Train Sets for KTM ETS & Komuter Services

The government is planning to add 50 new train sets to meet growing demand for KTM ETS & Komuter services.

25-08-2025
Auto News

Langkawi LRT ‘Unrealistic’, Focus Stays on Penang LRT and ECRL - Loke

The government is pushing ahead with the Penang LRT and ECRL, but dismissed talk of a Langkawi LRT as unrealistic.

19-08-2025
Auto News

Malaysian Transport Safety Board Proposal Back on Table – MOT

The Ministry of Transport is drafting a policy to establish the Malaysian Transport Safety Board (MTSB).

13-08-2025
Auto News

Loke: Accessibility, Safety Upgrades Coming To LRT Stations

Prasarana studying plans to install barriers at older LRT stations for enhanced passenger safety.

Auto News

Aerotrain Disruption A Minor Glitch, ETS3 Project On Track - Loke

KLIA’s Aerotrain glitch was a minor software bug, not a breakdown, while ETS3 to Johor Bahru is on track, says Transport Minister.

07-08-2025
Auto News

ETS Segamat–Johor Bahru Extension is On Track, No Delays – MoT

Transport Minister Anthony Loke says the ETS extension project from Segamat to Johor Bahru is on track with no delays.

06-08-2025

Latest News

Auto News

JPJ: 2.3 Million Malaysians Have Expired Driving Licences

JPJ claims there are over 2.3 million Malaysians with driving licences that are expired beyond three-year renewal window.

Auto News

Petrol Cards And Civil Servant Perks On Offer By Jetour Malaysia This Month

Up to RM1 million worth of free petrol cards plus special perks for civil servants on offer from Jetour Malaysia this month.

20-09-2025
Auto News

TQ Wuling Bingo EV CKD Production Set to Begin in Dec 2025

The new SGMW-Tan Chong joint venture EV plant will start its local assembly efforts this Dec with the TQ Wuling Bingo.

19-09-2025
Auto News

MyKad Checks Urged Ahead of Fuel Price Drop

Home minister urges Malaysians to fix faulty MyKad chips early to enjoy the upcoming targeted fuel subsidy.

19-09-2025
Auto News

GAC Emkoo Awarded 5-star ASEAN NCAP Rating

Upcoming GAC Emkoo C-SUV earns coveted 5-star rating form ASEAN NCAP crash-testing regime.

19-09-2025
Auto News

KLCC Roads Closed Saturday For Sarong Music Run

Expect road closures and traffic delays around KLCC tomorrow for the Malaysia Sarong Music Run 2025.

19-09-2025
Auto News

Sand, Log Trucks Dominate Kelantan Roads - JPJ

Sand and log trucks make up most heavy vehicle traffic in Kelantan, with fewer overloaded cases.

19-09-2025
Auto News

Customs Seizes 32 Imported Cars Worth RM8.45 Million

Ops Purple uncovered vehicles stored beyond the legal limit, with unpaid duties and taxes totalling RM5.38 million.

19-09-2025