New Marang Bridge 55% Done, Set to Finish By Jan 2027

Anis

Share via

2281184.jpg
Construction of the new Marang Bridge, aimed at improving travel between Kuala Terengganu and Kuantan is progressing steadily and is expected to be completed by January 2027.

According to Works Minister Datuk Seri Alexander Nanta Linggi, the project had reached 54.7% completion as of June 30.

“This is it, no more extensions,” he said during a recent site visit. “All land acquisition issues have been resolved, and work is moving forward as planned.”

The RM338 million project, led by the Public Works Department (JKR), includes a 2.5km realignment along Federal Route 3, a 680-metre flyover to divert traffic around Marang town, a 220-metre bridge across Sungai Marang, and upgrades to 1.5km of existing roads.

Built in the 1950s,  the current bridge has long been a traffic bottleneck, particularly during rush hours. It will be replaced by a modern four-lane structure designed to handle higher traffic volume and reduce congestion for east coast motorists.

But the benefits go beyond smoother traffic. With increased clearance, the new bridge will also support the local fishing community by allowing larger Zone C vessels to pass upstream, a move expected to improve accessibility and strengthen the region’s maritime and fisheries economy.

New-Marang-bridge-1-850x583.jpg
“This isn’t just about easing traffic. It’s about creating better access for fishermen, supporting local industries, and boosting Marang’s potential as a logistics hub,” Nanta affirmed. He added that the project had been prioritised under the 12th Malaysia Plan to meet rising transportation demands in the area.

Tagged:

Public Works Minister Datuk Seri Alexander Nanta Linggi
Marang Bridge
12th Malaysia Plan
Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

Related News

Auto News

Govt Yet to Decide on Toll-Free Travel for Next Year’s Festive Season

Govt has yet to decide on bringing back toll-free travel for next year’s festive season, says the Works Minister.

25-07-2025
Auto News

East-West Highway Safe, More Upgrades Coming - Works Minister

The Works Ministry told Bernama the JRTB is safe for users, but more upgrades are on the way under the 13th Malaysia Plan.

22-07-2025
Auto News

KKR Only Gets Half of RM4B Needed for Road Repairs – Ahmad Maslan

The Public Works Ministry only received half of the RM 4 billion required to repair the damaged roads in Malaysia.

30-06-2025
Auto News

RM4b Needed, Critical Road Repairs Come First

Road repairs will be done in stages due to budget limits, with priority on the most severe sections.

19-06-2025
Auto News

Bukit Kayu Hitam ICQS-Sadao CIQ Project On Track For Completion This Year

Bukit Kayu Hitam ICQS-Sadao CIQ project is 47% finished and expected to be completed by Sept.

06-05-2025
Auto News

Works Minister: Tapah Smoother Now, WISE to Offer Alternative to Menora

With the Tapah traffic project now complete, the Works Ministry eyes the upcoming WISE highway - a new alternative to the Menora Tunnel route. o

Auto News

Works Ministry Considering Motorcycle Lanes On Future Highways

The Works Ministry is considering adding motorcycle lanes to new highways to improve safety.

16-04-2025
Auto News

Works Minister Demands Urgent Report On Kluang Pothole Crash

Works Minister demanded a swift report on the poor maintenance of Jalan Sengkang-Felda Inas-Bandar Tenggara road.

28-03-2025

Latest News

Auto News

PMX: Proton’s International Success a Model for Malaysia

PM Datuk Seri Anwar Ibrahim says Proton’s success abroad in Egypt proves the brand is ready to expand into more markets.

Auto News

New Proton Saga ‘Teased’ During EV Factory Launch – ADAS Confirmed

Upcoming next-gen Proton Saga ‘teased’ during new EV factory launch, basic ADAS confirmed, along with other bits.

04-09-2025
Auto News

Proton Launches New EV Plant in Tanjung Malim – e.MAS 7 CKD Begins

Proton has launched its first EV plant in Tanjung Malim, with the local assembly of the e.MAS 7 EV already started.

04-09-2025
Auto News

Penang Defends Mega Projects As Key To Tackling Traffic Woes

Penang’s transport councillor says flyovers, underpasses and the LRT are essential to ease congestion.

04-09-2025
Auto News

KPDN Tightens RON95 Subsidy Control with MyKad Verification via eCOSS

Malaysians will soon need to verify their MyKad through the eCOSS system to purchase subsidised RON95 petrol.

Auto News

Selangor Eyes DRT Comeback By Year-End

State govt fine-tuning plans to relaunch Selangor Mobility’s on-demand transit service after pilot phase ended last year.

04-09-2025
Auto News

KLIA Aerotrain Breaks Down Hours After Back-in-Schedule Announcement

Fresh off nearly two weeks of “fine-tuning” maintenance to boost reliability, KLIA’s aerotrain stalled at 1.36PM, service only resumed at 5.38PM.

Auto News

Pos Malaysia Expands EV Fleet with 136 New Electric Vans

Pos Malaysia has expanded its EV fleet by adding 136 new all-electric Maxus eDeliver 3 electric vans.

04-09-2025