Govt Looking To Revive MEX II Highway With New Completion Plan

Anis

Share via

LEBUHRAYAMEXII_4328-(1).jpeg

The MEX II Highway, once planned as a major traffic solution for Klang Valley, has remained unfinished since 2019. Now, the government is working with bondholders to revive the project and get construction moving again.

Talks are currently underway between federal agencies and the Receivers and Managers appointed by the project's sukuk holders, who took over after the original concession company defaulted in early 2022. 

The focus now is on finding a financially and technically viable path to completion.

Works Minister Datuk Seri Alexander Nanta Linggi said the discussions are centred on four key areas; updated construction costs, cash flow projections, long-term toll revenue, and traffic analysis. 

These factors, according to him, will help determine whether the highway can still deliver value to motorists and investors alike. BH3MEXIM_BHfield_image_socialmedia.var_1746244591.jpg
Once a revised plan is finalised, it will be presented to the Cabinet for further consideration.

“We are reviewing all aspects, including technical and financial feasibility. The aim is to ensure the project remains viable and serves the public interest,” Nanta said in a written reply in Parliament.

The issue was raised by Puchong Member of Parliament Yeo Bee Yin, who questioned how much more funding might be required and what steps are being taken to avoid similar project failures in the future.

Nanta clarified that the MEX II project was a fully private initiative, funded and managed under a contractual model where the private concessionaire builds, operates, and eventually transfers the highway. 

“All progress payments and claims were managed between the concessionaire, contractors, engineers, and the sukuk holders without government involvement in approvals or disbursements,” the minister explained. MEX-ii-plan.jpg
Originally set to be completed in December 2019, the 18-kilometre extension was designed to ease congestion on the existing MEX Expressway. 

However, prolonged cash flow issues halted the work. The project has since come under renewed public scrutiny following an investigation into RM360 million worth of alleged false claims, now being probed by the Malaysian Anti-Corruption Commission (MACC).



Tagged:

Maju Expressway extension project (MEX II)
Build-Operate-Transfer (BOT) arrangement.
STALLED MEX II HIGHWAY PROJECT
Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

Related News

Auto News

MACC: RM32 Million Seized From ‘Tan Sri’ Over Expressway Scandal

MACC seizes RM32 Million in luxury assets from a highway concessionaire amid a probe into the misuse of sukuk funds.

Auto News

Govt Moves to Revive Delayed MEX II Project

From missed deadlines to MACC probes, troubled MEX II project finally see a turning point as govt swoops in to revive it.

Latest News

Auto News

Govt Still Weighing Options For KL–Singapore HSR Project - Loke

Malaysia is still reviewing options for the KL–Singapore HSR, with a final model yet to be determined.

08-10-2025
Auto News

Budi95: KPDN Now Empowered to Check MyKad

KPDN officers are now authorised to check MyKad to ensure the smooth rollout of the BUDI95 subsidy.

Auto News

No Ban On SUVs For E-Hailing Registration - Loke

Loke clarified that SUVs remain eligible for e-hailing services, dismissing recent reports of registration restrictions as inaccurate.

07-10-2025
Auto News

AHTV Succeeds Shah Alam As Proton’s Next-Generation Manufacturing Hub

AHTV poised to position Proton as regional export hub and boost local supplier networks through high-value jobs.

Auto News

Omoda | Jaecoo Malaysia Celebrates 20,000th Unit Delivery Milestone

Just over a year since its market debut, Omoda | Jaecoo Malaysia has delivered its 20,000th vehicle here in Malaysia.

07-10-2025
Auto News

Over 7,000 Commercial Vehicle Safety Audits Completed - Loke

Loke told Parliament that JPJ has audited more than 7,000 commercial vehicle operators, with a new digital system set by 2027.

07-10-2025
Auto News

Ops Grip: MACC Exposes Fake Labels, Erased Barcodes and Smuggled Tyres

MACC’s Op Grip exposes multi-million Ringgit racket involving fake labels, smuggled tyres and money laundering.

Auto News

Jalan Reko Upgrade Aims To Curb Floods, Ease Traffic By 2028

The RM68 million road upgrade in Kajang aims to resolve long-standing flash flood and congestion issues.

07-10-2025