Ampang/Sri Petaling LRT Line Repair Completion Delayed Till February 2024
-full_normal.jpg)
Rapid Rail Sdn Bhd (Rapid Rail), the operator of the Ampang/Sri Petaling LRT Line, announced that the comprehensive repair work (Phase 2) on the viaduct structure and tracks near the Bandaraya LRT Station is delayed and is expected to be completed, and normal operations resume on 29 February 2024.
The original plan for completing the repair work and restoring normal operations on this route was in mid-October 2023. However, the additional time is necessary because, in addition to the initial damage to viaduct 163, several other damages have been identified on nearby viaduct structures, namely viaducts 164 and 165, which require thorough repairs.
-full_normal.jpg)
After consulting with engineering experts, additional work is required on these viaduct structures to ensure they are safe, meet specifications, and can fulfil the criteria for normal safe operations.
These repair works also involve consultation, assessment, and approval from the Department of Irrigation and Drainage (JPS) of the Federal Territories, as support structures need to be installed along the Klang River adjacent to the affected LRT viaducts.
-full_normal.jpg)
Safety considerations are a top priority for all parties involved in carrying out these high-risk tasks and this additional work has extended the timeline for the restoration work by 3 months.
Rapid Rail is extending its apologies for the inconvenience experienced by commuters. The decision to extend the timeline for the restoration work is to ensure that all damages are identified and repaired to guarantee the safety of public transportation operations and users.
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VRB7683
SELANGOR
BSQ6674
JOHOR
JYY2783
PULAU PINANG
PSC8479
PERAK
APJ745
PAHANG
CFG7302
KEDAH
KGG4258
NEGERI SEMBILAN
NEK6084
KOTA KINABALU
SJS3240
KUCHING
QAB9603N
Last updated 13 Jun, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
Sri Petaling LRT Line Will Resume Operations On 29 February
Repairs to specific stations along the Sri Petaling LRT line will be completed by the end of February 2024, says Rapid KL.
07-01-2024
Ampang/Sri Petaling LRT Line Repair Works To Take Up To 7 Months
Ampang/Sri Petaling LRT repair work would take up to seven months to complete.
22-02-2023
LRT Ampang, Sri Petaling Line Will Get Women’s Coach From Dec 31
RapidKL has announced the implementation of women-only coaches on the LRT Ampang/Sri Petaling line, which will begin on December 31, 2024.
24-12-2024
Direct Service From Ampang, Putra Heights LRT Stations To Masjid Jamek Resumes
LRT passengers from the Ampang and Putra Heights lines can continue their journey to Masjid Jamek effective today.
01-02-2024
Park N Ride Facilities At Ampang & Gombak LRT Station Now Uses ‘Pay & Go App’ Parking Payment
RapidKL announced Park & Ride facilities at Ampang and Gombak LRT Station will now utilise an automatic number plate recognition (ANPR) system.
04-04-2023
Bandaraya-Masjid Jamek LRT Line Closed For Two Weeks - Loke
Ampang LRT line will be closed between the Bandaraya and Masjid Jamek stations for about two weeks.
02-02-2023
Ampang/Sri Petaling LRT Line Repair Works To Take Up To 7 Months
Ampang/Sri Petaling LRT repair work would take up to seven months to complete.
22-02-2023
Rapid Rail To Install Temporary LRT Platform Barriers Starting Year-End
Rapid Rail will install temporary platform barriers along key LRT lines starting the end of this year.
17-10-2025
Latest News
Prime, Premium, Or Premium Plus? 4 Major Differences Between The 3 Proton e.Mas 7 Tiers
Prime, Premium, or Premium Plus? We break down the 4 massive differences in battery range, price, and luxury features across the new Proton eMas 7 EV tiers.
12-06-2026
15 Drug Records But Still Driving?! Malaysians Are Furious Over The Viral Penang Highway Triton Rampage
Shocking details emerge on the viral Mitsubishi Triton highway crash in Penang. The drugged driver has 17 prior convictions, leaving 18 cars damaged.
10-06-2026
Don't Buy A Car Full Price! Perodua Just Quietly Slashed Prices On 5 Models & The Discounts Vanish After June 30
Perodua just quietly slashed prices on 5 popular models for June 2026! Check out the exact cash rebates for the Myvi, Ativa, Aruz, Bezza, and Axia here.
09-06-2026
Upgraded e.MAS 7 & A Spicy X50?! 5 Things To Check Out At Proton’s KLIMS 2026 Booth This June 12–21
Proton is bringing an upgraded long-range e.MAS 7, a humanoid robot, and new FutureMotion hybrid tech to KLIMS 2026 at MITEC. Here is what to look out for.
09-06-2026
1,400 hp SUV? 3 Wildest Things To See At Zeekr’s KLIMS 2026 Booth This 12-21 June
Looking for ultimate luxury? Discover why you should hold your premium vehicle booking until KLIMS 2026 as Zeekr previews the insane 1,400hp Zeekr 9X PHEV, the 4-seat 009 Grand, and the handle-less 2026 Zeekr X facelift.
09-06-2026
Holding A Showroom Pen? Freeze Your SUV Deposit Until You See Mazda's Booth At KLIMS 2026
Thinking of buying a new SUV? Discover why you should freeze your deposit until KLIMS 2026 as Mazda previews the bigger 3rd-gen Mazda CX-5 and launches the straight-six CX-60 3.3G AWD.
09-06-2026
Heartbreaking Dashcam Footage Reveals Final Moments Before Tragic Collision That Wiped Out 3 Generations Of A Family
A brand-new Proton X50 turned into a nightmare just hours after delivery, as a tragic head-on collision claimed the lives of 6 family members, including a baby.
08-06-2026
RM200k Rebates?! Test Drive 9 Brands At The Sime Motors MotorExpo 2026 This Weekend
Hit up the free-entry Sime Motors MotorExpo 2026 at XOX Arena this weekend for massive RM200,000 rebates and test drives from 9 major brands.
05-06-2026
Show More
trending_flat