Ampang/Sri Petaling LRT Line Repair Completion Delayed Till February 2024
-full_normal.jpg)
Rapid Rail Sdn Bhd (Rapid Rail), the operator of the Ampang/Sri Petaling LRT Line, announced that the comprehensive repair work (Phase 2) on the viaduct structure and tracks near the Bandaraya LRT Station is delayed and is expected to be completed, and normal operations resume on 29 February 2024.
The original plan for completing the repair work and restoring normal operations on this route was in mid-October 2023. However, the additional time is necessary because, in addition to the initial damage to viaduct 163, several other damages have been identified on nearby viaduct structures, namely viaducts 164 and 165, which require thorough repairs.
-full_normal.jpg)
After consulting with engineering experts, additional work is required on these viaduct structures to ensure they are safe, meet specifications, and can fulfil the criteria for normal safe operations.
These repair works also involve consultation, assessment, and approval from the Department of Irrigation and Drainage (JPS) of the Federal Territories, as support structures need to be installed along the Klang River adjacent to the affected LRT viaducts.
-full_normal.jpg)
Safety considerations are a top priority for all parties involved in carrying out these high-risk tasks and this additional work has extended the timeline for the restoration work by 3 months.
Rapid Rail is extending its apologies for the inconvenience experienced by commuters. The decision to extend the timeline for the restoration work is to ensure that all damages are identified and repaired to guarantee the safety of public transportation operations and users.
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VQQ1659
SELANGOR
BSN3367
JOHOR
JYT1498
PULAU PINANG
PSA4874
PERAK
APF9094
PAHANG
CFF7343
KEDAH
KGE7324
NEGERI SEMBILAN
NEJ7530
KOTA KINABALU
SJQ7590
KUCHING
QAB4013N
Last updated 14 Mar, 2026
Fuel Price
Petrol
RON 95
RM 2.59
+0.05
RON 97
RM 3.15
+0.05
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.04
+0.05
EURO 5 B7
RM 3.24
+0.05
Last updated 26 Feb, 2026
Related News
Sri Petaling LRT Line Will Resume Operations On 29 February
Repairs to specific stations along the Sri Petaling LRT line will be completed by the end of February 2024, says Rapid KL.
07-01-2024
Ampang/Sri Petaling LRT Line Repair Works To Take Up To 7 Months
Ampang/Sri Petaling LRT repair work would take up to seven months to complete.
22-02-2023
LRT Ampang, Sri Petaling Line Will Get Women’s Coach From Dec 31
RapidKL has announced the implementation of women-only coaches on the LRT Ampang/Sri Petaling line, which will begin on December 31, 2024.
24-12-2024
Direct Service From Ampang, Putra Heights LRT Stations To Masjid Jamek Resumes
LRT passengers from the Ampang and Putra Heights lines can continue their journey to Masjid Jamek effective today.
01-02-2024
Park N Ride Facilities At Ampang & Gombak LRT Station Now Uses ‘Pay & Go App’ Parking Payment
RapidKL announced Park & Ride facilities at Ampang and Gombak LRT Station will now utilise an automatic number plate recognition (ANPR) system.
04-04-2023
Bandaraya-Masjid Jamek LRT Line Closed For Two Weeks - Loke
Ampang LRT line will be closed between the Bandaraya and Masjid Jamek stations for about two weeks.
02-02-2023
Ampang/Sri Petaling LRT Line Repair Works To Take Up To 7 Months
Ampang/Sri Petaling LRT repair work would take up to seven months to complete.
22-02-2023
Rapid Rail To Install Temporary LRT Platform Barriers Starting Year-End
Rapid Rail will install temporary platform barriers along key LRT lines starting the end of this year.
17-10-2025
Latest News
9,000+ Drivers Chose Toyota Hybrids This Year: Proof That Toyota’s Multi-Pathway Strategy Works
Toyota Malaysia hits 9,556 sales in early 2026, proving the "Multi-Pathway" strategy works. From Vios Hybrid to Vellfire HEV, see why hybrids are winning the sales war.
12-03-2026
Chery Tiggo 7 is Now the Safest Chinese SUV on the Planet, This Is Why
The Chery Tiggo 7 makes history as the only Chinese SUV to sweep 5-star ratings from Euro NCAP, ANCAP, and ASEAN NCAP. With a record 94.68 points, see why this is 2026’s safest family SUV.
11-03-2026
Sepang Dates Confirmed: Catch Team Porsche Malaysia in Action on 21–23 August
While the 2026 Porsche Carrera Cup Asia (PCCA) season kicks off in Shanghai this weekend, Malaysian fans are already looking ahead to the highlight of the year: the homecoming.
10-03-2026
Iran-US War Day 10: It’s Not Just Fuel — Malaysia’s Automotive Industry Faces New Risks
While the BUDI95 subsidy program is already feeling the heat of oil prices flirting with US$120 a barrel, the true threat to our automotive sector lies beneath the surface.
09-03-2026
Prasarana to Reveal LRT3 Launch Date This April—Here’s Everything We Know So Far
The wait for the LRT3 Shah Alam Line is entering its final stretch. After months of "will they, won't they" speculation, Prasarana has officially pointed to April 2026 as the month of truth.
05-03-2026
EV King is Here: How Proton e.MAS 5 Dethroned Popular Petrol Cars in 60 Days
PRO-NET has announced that the Proton e.MAS 5 has officially surpassed the 5,000-unit delivery milestone in just two months.
05-03-2026
Wolfgang Egger’s Masterpiece: Denza Z9 GT Confirmed for Malaysia Launch in Q2 2026
BYD Malaysia has officially confirmed that the Denza Z9 GT is set to launch in the local market in early 2026 (expected Q2). As the flagship luxury "shooting brake" for the brand, the Z9 GT is designed to offer a tech-forward alternative to the Porsche Panamera and BMW 5 Series Touring.
03-03-2026
Kelana Jaya LRT trains “out of service” but line running normally - RapidRail
Rapid Rail clarified that temporary train withdrawals on the Kelana Jaya LRT line are part of standard safety procedures.
27-02-2026
Show More
trending_flat