Ampang/Sri Petaling LRT Line Repair Completion Delayed Till February 2024
-full_normal.jpg)
Rapid Rail Sdn Bhd (Rapid Rail), the operator of the Ampang/Sri Petaling LRT Line, announced that the comprehensive repair work (Phase 2) on the viaduct structure and tracks near the Bandaraya LRT Station is delayed and is expected to be completed, and normal operations resume on 29 February 2024.
The original plan for completing the repair work and restoring normal operations on this route was in mid-October 2023. However, the additional time is necessary because, in addition to the initial damage to viaduct 163, several other damages have been identified on nearby viaduct structures, namely viaducts 164 and 165, which require thorough repairs.
-full_normal.jpg)
After consulting with engineering experts, additional work is required on these viaduct structures to ensure they are safe, meet specifications, and can fulfil the criteria for normal safe operations.
These repair works also involve consultation, assessment, and approval from the Department of Irrigation and Drainage (JPS) of the Federal Territories, as support structures need to be installed along the Klang River adjacent to the affected LRT viaducts.
-full_normal.jpg)
Safety considerations are a top priority for all parties involved in carrying out these high-risk tasks and this additional work has extended the timeline for the restoration work by 3 months.
Rapid Rail is extending its apologies for the inconvenience experienced by commuters. The decision to extend the timeline for the restoration work is to ensure that all damages are identified and repaired to guarantee the safety of public transportation operations and users.
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VPY7918
SELANGOR
BSK1383
JOHOR
JYK9434
PULAU PINANG
PRV6170
PERAK
APC4637
PAHANG
CFE1418
KEDAH
KGC9560
NEGERI SEMBILAN
NEH5860
KOTA KINABALU
SJN6348
KUCHING
QAB5029M
Last updated 13 Nov, 2025
Fuel Price
Petrol
RON 95
RM 2.65
+0.05
RON 97
RM 3.25
+0.05
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.07
+0.05
EURO 5 B7
RM 3.27
+0.05
Last updated 13 Nov, 2025
Related News
Sri Petaling LRT Line Will Resume Operations On 29 February
Repairs to specific stations along the Sri Petaling LRT line will be completed by the end of February 2024, says Rapid KL.
07-01-2024
Ampang/Sri Petaling LRT Line Repair Works To Take Up To 7 Months
Ampang/Sri Petaling LRT repair work would take up to seven months to complete.
22-02-2023
LRT Ampang, Sri Petaling Line Will Get Women’s Coach From Dec 31
RapidKL has announced the implementation of women-only coaches on the LRT Ampang/Sri Petaling line, which will begin on December 31, 2024.
24-12-2024
Direct Service From Ampang, Putra Heights LRT Stations To Masjid Jamek Resumes
LRT passengers from the Ampang and Putra Heights lines can continue their journey to Masjid Jamek effective today.
01-02-2024
Park N Ride Facilities At Ampang & Gombak LRT Station Now Uses ‘Pay & Go App’ Parking Payment
RapidKL announced Park & Ride facilities at Ampang and Gombak LRT Station will now utilise an automatic number plate recognition (ANPR) system.
04-04-2023
Bandaraya-Masjid Jamek LRT Line Closed For Two Weeks - Loke
Ampang LRT line will be closed between the Bandaraya and Masjid Jamek stations for about two weeks.
02-02-2023
Ampang/Sri Petaling LRT Line Repair Works To Take Up To 7 Months
Ampang/Sri Petaling LRT repair work would take up to seven months to complete.
22-02-2023
Rapid Rail To Install Temporary LRT Platform Barriers Starting Year-End
Rapid Rail will install temporary platform barriers along key LRT lines starting the end of this year.
17-10-2025
Latest News
Updated Fuel Prices From 13 To 19 November
The Ministry of Finance (MoF) has announced the retail prices of all fuels in Malaysia, for the coming week of 13 to 19 November, 2025, the rates are as such.
12-11-2025
RM1.7b NPE2 Extension To Ease KL Congestion By 2029 - Nanta
The NPE2 will connect Pantai Dalam to Jalan Istana, cutting travel time by up to 25 minutes and improving traffic flow across KL.
12-11-2025
BYD Shark PHEV Pick-Up Truck Teased by BYD Cars Malaysia – Coming Soon?
BYD Cars Malaysia has dropped a teaser for the BYD Shark PHEV pick-up truck. Coming to Malaysia soon?
12-11-2025
Malaysia Scraps Rule of 78, Car Loan Savings Ahead - Analysts
Malaysia ends the Rule of 78, letting car loan borrowers save more with fairer interest.
12-11-2025
Govt Not Forcing Aeroline To TBS, Corus KLCC Stop Unsuitable
Express bus operators aren’t forced to use TBS or TBG but must run from safe, licensed terminals.
12-11-2025
Oct 2025 Vehicle Sales Up 30%, xEV Share at 8.7%
Malaysia’s car market surged in Oct 2025 with 81,413 new registrations, up 30% from Sept’s 62,598 units.
12-11-2025
LATAR Interchange Opens, Direct Access To Eco Grandeur
The Eco Grandeur Interchange and Toll Plaza has officially opened, offering direct access through Exit 2502 to Eco Grandeur.
11-11-2025
Penang Sentral Set to Become Mainland’s Integrated Transport Hub
The Butterworth KTM station, Mutiara Line LRT, and airport expansions will turn Penang Sentral into key transport and logistics hub.
11-11-2025
Show More
trending_flat