ECRL Finishes Excavation Of 30 Tunnels Ahead Of Schedule
The East Coast Rail Link (ECRL) project made three tunnel breakthroughs in a single day in the Bentong district, and as of now, it has finished excavating 30 tunnels along its rail alignment.
The owner of the ECRL project, Malaysia Rail Link Sdn Bhd (MRL), stated in a statement on Tuesday that the "drill and blast" method of tunnelling was used to excavate three ECRL tunnels Bentong, Kampung Lentang, and Kampung Lentang 2 earlier than expected.
With 30 tunnel breakthroughs, MRL Chief Executive Officer Datuk Seri Darwis Abdul Razak announced that the ECRL project has reached a new milestone.
As of February 2024, the ECRL project had made an overall progress of 62.40 percent, according to Darwis. This progress was supported by quick infrastructure work, such as tunnel excavation, beam launching, track laying, and station construction.
He continued by saying that about 23,000 workers at roughly 1,900 work sites spread across the states of Selangor, Pahang, Terengganu, and Kelantan support the project.
The railway track's maximum gradient of 0.9% should be met by the construction of ECRL tunnels in the Bentong district, which should also greatly reduce open forest cutting and lessen the area's impact on wildlife.
Along its rail alignment, the ECRL project entails the construction of 41 tunnels totaling about 69 km in length. There are twenty tunnels in Section C (Mentakab-Port Klang), and twenty more in Section A (Kota Bharu-Dungun) and Section B (Dungun-Mentakab).
Of the 41 tunnels along the ECRL alignment, nine tunnels in Section C and all 21 tunnels in Sections A and B have finished excavation as of August 2023. The remaining tunnels are still under construction.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VPG4347
SELANGOR
BSF5076
JOHOR
JYA5080
PULAU PINANG
PRR4984
PERAK
ANW6804
PAHANG
CFC1457
KEDAH
KGA9451
NEGERI SEMBILAN
NEG2394
KOTA KINABALU
SJL3102
KUCHING
QAB5152L
Last updated 18 Jun, 2025
Fuel Price
Petrol
RON 95
RM 2.05
RON 97
RM 3.07
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.74
EURO 5 B7
RM 2.94
Last updated 12 Jun, 2025
Related News
ECRL: KotaSAS Station System Installation Completed
KotaSAS Station becomes first along ECRL route to complete installation of critical systems.
30-05-2025
MiTRANS: ECRL-Sungai Golok Link Key to Regional Rail
MiTRANS: Extending the ECRL to Sungai Golok would complete a key missing link in the ASEAN rail network.
22-05-2025
Thai Ambassador Proposes ECRL Extension To Sungai Golok
Thai Ambassador Lada Phumas suggested extending the ECRL to Sungai Golok for better rail links.
16-05-2025
ECRL Hits 82% Completion, Promises 1,800 Jobs - 80% For Locals
ECRL, Malaysia’s largest rail project is nearing completion, with passenger service set to begin by Jan 2027.
06-05-2025
ECRL to Boost East Coast Growth, Strengthen Malaysia-China Ties
The ECRL project is set to unlock new growth for Malaysia’s east coast and strengthen links with China.
29-04-2025
ECRL Railway Construction Along Kota Bharu-Selangor Over 80% Complete
ECRL project along Kota Bharu-Selangor alignment is over 81% complete and remains on track for completion in Dec 2026.
18-04-2025
ECRL Concludes 38 Tunnel Excavations Ahead Of Schedule
MRL announces the completion of excavation work for 38 tunnels along the ECRL rail line.
09-04-2025
ECRL 80% Complete, Shifting To Above-Ground Work
The ECRL project, which is nearing 80% completion, is transitioning from the underground construction phase to above-ground work.
27-03-2025
Latest News
Amir Hamzah: RON95 Subsidy Coming Reform Before 2026 Carbon Tax
RON95 petrol subsidies to be rationalised ahead of 2026 carbon tax rollout, comes as part of Malaysia’s energy transition.
17-06-2025
Malaysian Single-Mom Truckers Make Local Headlines
In a male-dominated industry, 39-year-old Irzunika Idris and 40-year-old Marlia Ramli became truck drivers to support their kids.
17-06-2025
Rapid KL On-Demand Adds 5 New Zones — Cyberjaya & Putrajaya Included
The Rapid KL On-Demand service has been expanded to five new zones, including Cyberjaya and Putrajaya.
17-06-2025
PRO-NET Opens Three New Proton e.MAS & smart Dealerships
PRO-NET has expanded both its Proton e.MAS and smart dealer network by opening three new outlets in Malaysia.
17-06-2025
FT Dept, JPJ Told To Deal With Abandoned Vehicles
FT Dept and JPJ ordered to review and improve laws on abandoned vehicle disposal in KL and Putrajaya.
17-06-2025
Gerik Crash: PSV Licence Suspended, RM1.7M Aid Raised
JPJ suspends Gerik crash bus driver’s PSV licence as investigations rule out technical failure.
17-06-2025
PLUS Opens Three New Lanes At Rawang Selatan Toll Plaza
PLUS has announced the addition of three new lanes at the Rawang Selatan toll plaza (Exit 115).
16-06-2025
RON95 Petrol Subsidy Rationalisation Will Proceed – PMX
The government will proceed with the RON95 fuel subsidy rationalisation, says Prime Minister Anwar Ibrahim.
16-06-2025
Show More
trending_flat