ECRL 80% Complete, Shifting To Above-Ground Work

The East Coast Rail Line (ECRL) project has achieved nearly 80% completion as of February. The 665-kilometer rail network, which connects the states of Kelantan, Terengganu, Pahang, and Selangor, has largely progressed from underground construction to above-ground infrastructure, and the installation of systems is underway throughout the entire route.
The ECRL project is expected to be completed by 2027, and this critical phase will accelerate progress toward that goal. Kong Qi, managing director of China Communications Construction (ECRL) Sdn Bhd (CCC-ECRL), said that the project's success can be attributed to the ongoing commitment of local partners.
-full_normal.jpg)
“Their expertise, resilience, and adherence to high industry standards have been instrumental in driving progress," he says in a NST report.
The project, with a total allocation of RM74.96 billion, comprising RM50.27 billion designated for construction and RM24.69 billion for supplemental development expenditures, is projected to serve as a significant driver for economic advancement and sustainable development across key sectors.

The rail network will feature twenty stations distributed throughout the states of Kelantan, Terengganu, Pahang, and Selangor.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VQR1783
SELANGOR
BSN4702
JOHOR
JYT4674
PULAU PINANG
PSA6595
PERAK
APG1378
PAHANG
CFF8499
KEDAH
KGE8360
NEGERI SEMBILAN
NEJ8149
KOTA KINABALU
SJQ8651
KUCHING
QAB4278N
Last updated 24 Mar, 2026
Fuel Price
Petrol
RON 95
RM 2.59
+0.05
RON 97
RM 3.15
+0.05
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.04
+0.05
EURO 5 B7
RM 3.24
+0.05
Last updated 26 Feb, 2026
Related News
Kuantan Welcomes ECRL’s First Trains Ahead of 2027 Operations
The first ECRL electric passenger trains and freight locomotives have arrived in Kuantan as the project moves closer to operations in 2027.
11-02-2026
ECRL Fares To Be Announced Ahead of 2027 Launch
ECRL fares will be disclosed several months prior to the commencement of operations in January 2027, according to Transport Minister.
30-01-2026
ECRL Launch Hinges On System Integration, Jan 2027 Target Maintained
The ECRL remains on schedule, with system integration and testing now the key focus ahead of its planned Jan 2027 launch.
29-01-2026
ECRL First EMU Trains, E-Locos Head To Malaysia For Testing
Malaysia’s East Coast Rail Link gears up as its first EMUs and electric locomotives arrive for testing and future service.
17-12-2025
First ECRL Trains Depart China, Remaining Units Arriving Through 2026
First ECRL trains depart China, with remaining units scheduled to arrive through 2026.
28-11-2025
ECRL Nears Completion with 89% Progress, Operations Set for 2027
ECRL is on track to begin services from Kota Bharu to Gombak in Jan 2027, as construction progress hits 89%.
24-11-2025
ECRL Trains Fully Assembled, Ready for Malaysia
The first batch of trains for the East Coast Rail Link (ECRL) is now ready in Dalian, China.
21-11-2025
ECRL Hits 88% Milestone As Key C1B Stretch Completed
The ECRL project has hit 88% completion with the C1B Segment now successfully completed.
05-11-2025
Latest News
Strait of Hormuz to Malaysia: Why We’re Paying for a War 6,000km Away
Why is RON97 at RM4.55/L? We decode the Strait of Hormuz conflict, the May 2026 subsidy deadline, and why Malaysia imports oil despite being a producer.
19-03-2026
From 82 Minutes to 8: How the Mutiara Line is Giving Penangites Their Time Back
Is the 80-minute Penang Bridge crawl finally ending? The Mutiara Line LRT links Butterworth to Komtar in just 8 minutes. Get the latest 2026 project updates, station lists, and more.
17-03-2026
The 2026 Proton X90 Buyer’s Warning: 5 Critical Safety Features You Are No Longer Getting
ASEAN NCAP revokes Proton X90’s 5-star rating. The 2026 facelift is downgraded to 1-star after stripping critical ADAS features. Is your family safe? Get the full safety specs here.
16-03-2026
9,000+ Drivers Chose Toyota Hybrids This Year: Proof That Toyota’s Multi-Pathway Strategy Works
Toyota Malaysia hits 9,556 sales in early 2026, proving the "Multi-Pathway" strategy works. From Vios Hybrid to Vellfire HEV, see why hybrids are winning the sales war.
12-03-2026
Chery Tiggo 7 is Now the Safest Chinese SUV on the Planet, This Is Why
The Chery Tiggo 7 makes history as the only Chinese SUV to sweep 5-star ratings from Euro NCAP, ANCAP, and ASEAN NCAP. With a record 94.68 points, see why this is 2026’s safest family SUV.
11-03-2026
Sepang Dates Confirmed: Catch Team Porsche Malaysia in Action on 21–23 August
While the 2026 Porsche Carrera Cup Asia (PCCA) season kicks off in Shanghai this weekend, Malaysian fans are already looking ahead to the highlight of the year: the homecoming.
10-03-2026
Iran-US War Day 10: It’s Not Just Fuel — Malaysia’s Automotive Industry Faces New Risks
While the BUDI95 subsidy program is already feeling the heat of oil prices flirting with US$120 a barrel, the true threat to our automotive sector lies beneath the surface.
09-03-2026
Prasarana to Reveal LRT3 Launch Date This April—Here’s Everything We Know So Far
The wait for the LRT3 Shah Alam Line is entering its final stretch. After months of "will they, won't they" speculation, Prasarana has officially pointed to April 2026 as the month of truth.
05-03-2026
Show More
trending_flat