New Marang Bridge 55% Done, Set to Finish By Jan 2027

Construction of the new Marang Bridge, aimed at improving travel between Kuala Terengganu and Kuantan is progressing steadily and is expected to be completed by January 2027.
According to Works Minister Datuk Seri Alexander Nanta Linggi, the project had reached 54.7% completion as of June 30.
“This is it, no more extensions,” he said during a recent site visit. “All land acquisition issues have been resolved, and work is moving forward as planned.”
The RM338 million project, led by the Public Works Department (JKR), includes a 2.5km realignment along Federal Route 3, a 680-metre flyover to divert traffic around Marang town, a 220-metre bridge across Sungai Marang, and upgrades to 1.5km of existing roads.
Built in the 1950s, the current bridge has long been a traffic bottleneck, particularly during rush hours. It will be replaced by a modern four-lane structure designed to handle higher traffic volume and reduce congestion for east coast motorists.
But the benefits go beyond smoother traffic. With increased clearance, the new bridge will also support the local fishing community by allowing larger Zone C vessels to pass upstream, a move expected to improve accessibility and strengthen the region’s maritime and fisheries economy.

“This isn’t just about easing traffic. It’s about creating better access for fishermen, supporting local industries, and boosting Marang’s potential as a logistics hub,” Nanta affirmed.
He added that the project had been prioritised under the 12th Malaysia Plan to meet rising transportation demands in the area.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VPW5324
SELANGOR
BSJ6214
JOHOR
JYJ9068
PULAU PINANG
PRV1342
PERAK
APB9473
PAHANG
CFD8428
KEDAH
KGC7035
NEGERI SEMBILAN
NEH4362
KOTA KINABALU
SJN3067
KUCHING
QAB3974M
Last updated 25 Oct, 2025
Fuel Price
Petrol
RON 95
RM 2.60
RON 97
RM 3.14
-0.04
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.89
-0.04
EURO 5 B7
RM 3.09
-0.04
Last updated 23 Oct, 2025
Related News
SSLR2 Highway Launched: RM7.6b Project Will Link Sarawak and Sabah
The 335km Sarawak–Sabah Link Road Phase 2 will connect key towns across northern Sarawak into Sabah.
12-09-2025
Govt Yet to Decide on Toll-Free Travel for Next Year’s Festive Season
Govt has yet to decide on bringing back toll-free travel for next year’s festive season, says the Works Minister.
25-07-2025
East-West Highway Safe, More Upgrades Coming - Works Minister
The Works Ministry told Bernama the JRTB is safe for users, but more upgrades are on the way under the 13th Malaysia Plan.
22-07-2025
KKR Only Gets Half of RM4B Needed for Road Repairs – Ahmad Maslan
The Public Works Ministry only received half of the RM 4 billion required to repair the damaged roads in Malaysia.
30-06-2025
RM4b Needed, Critical Road Repairs Come First
Road repairs will be done in stages due to budget limits, with priority on the most severe sections.
19-06-2025
Bukit Kayu Hitam ICQS-Sadao CIQ Project On Track For Completion This Year
Bukit Kayu Hitam ICQS-Sadao CIQ project is 47% finished and expected to be completed by Sept.
06-05-2025
Works Minister: Tapah Smoother Now, WISE to Offer Alternative to Menora
With the Tapah traffic project now complete, the Works Ministry eyes the upcoming WISE highway - a new alternative to the Menora Tunnel route. o
02-05-2025
Works Ministry Considering Motorcycle Lanes On Future Highways
The Works Ministry is considering adding motorcycle lanes to new highways to improve safety.
16-04-2025
Latest News
Proton: Sabah X50 Customers Have Nothing To Worry
Proton reaffirms after-sales for X50 model customers in Sabah through Regional Parts Centre established in Kota Kinabalu.
24-10-2025
85 Deaths, 8,940 Crashes Recorded During Op Lancar Deepavali 2025
Road deaths fell 12% during Op Lancar Deepavali 2025, even as total crashes rose slightly to nearly 9,000 cases nationwide.
24-10-2025
Toll Collection Begins On EKVE Section 1 This Saturday
Motorists using the EKVE Section 1 will start paying tolls from Oct 25 as the free toll period comes to an end.
24-10-2025
JPJ Issued Over 4,000 Notices for Heavy Vehicle Speed Limiter Compliance
JPJ has issued over 4,000 notices to ensure heavy vehicles install speed limiter devices for safer roads.
23-10-2025
RM1.17Mil In Fines Collected From Singapore Drivers Without RFID VEP
JPJ has issued nearly 4,000 summonses to Singaporean motorists since July for failing to install RFID VEP tags.
23-10-2025
BHPetrol Refreshes CI, Shows New Look In Bandar Tun Razak Station
Fuel retailers BHPetrol announces CI refresh, ‘new look’ now applied to key Bandar Tun Razak station.
23-10-2025
MOF: Budi Madani Diesel Sees RM5 Billion in Annual Savings
Budi Madani Diesel subsidy rationalisation has freed up RM5 billion annually for social and development spending.
23-10-2025
Call For Return Of Child Car Seat Subsidy As Usage Remains Low
Bangi MP Syahredzan Johan has urged the government to bring back the child safety seat subsidy next year.
23-10-2025
Show More
trending_flat