RTS & ETS Projects On Track For 2025-2026 Completion

The Johor-Singapore Rapid Transit System (RTS) project is running on schedule and is expected to be fully operational by December 2026, said Johor Regent Tunku Ismail Sultan Ibrahim.
In a statement reported by The Independent SG, Tunku Ismail shared that the state’s rail connectivity plans are moving forward smoothly, with construction milestones being met.
.jpg)
.jpg)
“Construction of the double-track Electric Train Service (ETS) line to Johor Bahru has now reached 99.48% completion
“With the service recently extended to Kluang at the end of last month, we are expecting the ETS to officially connect to Johor Bahru by December this year,” he said.
Road projects are also underway to ease traffic flow in southern Johor.
.jpg)
Upgrades to the North-South Expressway (PLUS) are being rolled out in phases with Phase 1, Package A began in June 2023 and is slated to wrap up by June 2025, while Package B, which kicked off this June, should finish by December 2025.
The first phase of the Senai-Desaru Expressway upgrading works, which started in November 2023, is also moving along and targeted for completion in April next year.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VQK3835
SELANGOR
BSM1569
JOHOR
JYQ6201
PULAU PINANG
PRY2567
PERAK
APE7109
PAHANG
CFE9937
KEDAH
KGE1434
NEGERI SEMBILAN
NEJ4084
KOTA KINABALU
SJQ172
KUCHING
QAB1466N
Last updated 30 Jan, 2026
Fuel Price
Petrol
RON 95
RM 2.54
+0.02
RON 97
RM 3.10
+0.02
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.88
+0.04
EURO 5 B7
RM 3.08
+0.04
Last updated 22 Jan, 2026
Related News
Bukit Chagar RTS Link Station Roof Completed, Final Facade Works Underway
Bukit Chagar station reaches a major milestone as the RTS Link roof is completed.
22-01-2026
Johor-Singapore RTS Completes First Test Run from Wadi Hana To Border
The RTS Link completes its first train test run from Wadi Hana Depot through Bukit Chagar to the Malaysia-Singapore border.
30-12-2025
Malaysia–Singapore Ink Additional Agreement for RTS Link
Malaysia–Singapore reaffirm RTS Link with an Additional Agreement to enable single-point immigration clearance.
05-12-2025
Johor’s Elevated ART Moving Forward, RFP Under Review - Loke
Johor’s Autonomous Rapid Transit project is progressing, with proposals being refined before final approval.
24-11-2025
Johor Questions Delay as Penang LRT Gets Federal Nod
Johor is urging Putrajaya to expedite approval for its long-awaited rail system to avoid RTS congestion.
21-11-2025
RTS Link: First Train Arrives In Johor, Testing Kicks Off At Wadi Hana Depot
Train Set 02 has arrived at Wadi Hana Depot, marking the start of critical testing and commissioning.
17-11-2025
Johor Regent Flags Traffic Concerns Ahead Of RTS Link Launch
Tunku Mahkota Ismail flags potential congestion around Bukit Chagar as the JB–SG RTS Link nears completion.
13-11-2025
RTS Link 65% Complete, First Train Arriving This Month
RTS Link connecting JB and SG is officially 65% complete, with the first train set expected to arrive this month.
03-11-2025
Latest News
Is GWM Seeking To Build Its Own Plant in Malaysia?
MITI raises prospects of a standalone GWM factory as newly launched Wey G9 begins production with 40% local content.
29-01-2026
BAS.MY Kota Bharu Sees Ridership Soar
Kelantan's BAS.MY Stage Bus Service records almost 84,000 passengers per month in the fourth quarter of 2025.
29-01-2026
Honda Malaysia Shifted 72,301 Units in 2025, No. 1 Non-National Car Brand for 12 Years
Honda Malaysia sold 72,301 units in 2025, retaining its position as the number 1 non-national passenger car brand for the 12th consecutive year.
29-01-2026
ETS To Run 24 Hours During Festive Peaks As Demand Surges
KTMB will operate 24/7 during festive periods to meet high passenger demand.
29-01-2026
ECRL Launch Hinges On System Integration, Jan 2027 Target Maintained
The ECRL remains on schedule, with system integration and testing now the key focus ahead of its planned Jan 2027 launch.
29-01-2026
Loke: Motorcycle Ban On Highway Not a Quick Fix
Motorcycle ban on highways is not a quick fix, as authorities weigh safety benefits against commuter needs.
29-01-2026
Proton Eyes 200,000 Units Sales For 2026, No 1 Status By 2029
Proton gears up to achieve 200,000 units sales for 2026, wants No 1 status by 2029 too.
29-01-2026
Updated Fuel Prices From 29 January To 4 February
The Ministry of Finance (MoF) has announced the retail prices of all fuels in Malaysia, for the coming week of 29 January to 4 February, 2026, the rates are as such.
28-01-2026
Show More
trending_flat