"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

Anis

Share via



According to Transport Minister Anthony Loke, the East Coast Rail Link (ECRL) is currently 42.06% complete. Loke stated today, while visiting the Genting ECRL Tunnel construction site, that the rail line's construction progress is on track to be completed by December 2026. However, Loke also stated that the ECRL project is currently facing a difficult challenge with the completion of the Genting ECRL tunnel, a twin tunnel spanning 16.39km in length that connects Bukit Tinggi, Pahang with Gombak, Selangor.


According to Loke, the tunnel will be built using a tunnel boring machine (TBM) rather than the drilling and explosives used in other ECRL tunnels. “I am confident with the management and workforce for the ECRL project to complete the project using two TBMs which were made in China. "When the construction crosses the Titiwangsa Range, these highly technological machines will be able to face engineering challenges and geological conditions," Loke said.



Construction on the first Genting tunnel has already begun, and approval to use the TBM for the second tunnel was obtained in November. “Boring works for the first Genting ECRL Tunnel have already reached a depth of 2.602km while the second reached 2.497km.




"For your information, the Genting ECRL Tunnel construction site spans 11.6ha in width and employs over 300 people."


"We hope that by January 2027, the ECRL will be fully operational, saving three hours of travel time from Kota Baru to Gombak," Loke added.

Gallery

Tagged:

ECRL
East Coast Rail Link (ECRL)
ECRL project
ECRL contruction progress
Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

Related News

Auto News
ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses

ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses

The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.

14-10-2025
Auto News
ECRL Project Hits 87% Completion by August 2025 – MoT

ECRL Project Hits 87% Completion by August 2025 – MoT

The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.

23-09-2025
Auto News
ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.

24-06-2025
Auto News
ECRL Is More Than 60% Complete - Malaysia Rail

ECRL Is More Than 60% Complete - Malaysia Rail

ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.

25-03-2024
Auto News
ECRL Project Progress Surpasses 56% - Loke

ECRL Project Progress Surpasses 56% - Loke

ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.

11-12-2023
Auto News
ECRL Kelantan Expected To Be Completed Six Months Earlier

ECRL Kelantan Expected To Be Completed Six Months Earlier

The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.

26-06-2023
Auto News
ECRL Project In Terengganu Reaches 55% Progress

ECRL Project In Terengganu Reaches 55% Progress

The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.

05-04-2023
Auto News
ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

ECRL project's Kuantan Tunnel will be completed by the end of April.

08-03-2023

Latest News

Auto News
BYD Sees 2025 YTD Sales Total Reach 11,097 Units – 70% YoY Up From 2024

BYD Sees 2025 YTD Sales Total Reach 11,097 Units – 70% YoY Up From 2024

BYD Cars Malaysia discloses its 2025 YTD toral sales have reached 11,097 units, marking a 70% YoY increase from 2024.

14-11-2025
Auto News
KLIA Aerotrain To Stop Nightly From Nov 15 For Reliability Upgrades

KLIA Aerotrain To Stop Nightly From Nov 15 For Reliability Upgrades

KLIA’s Aerotrain will be suspended nightly from 9PM to 7AM starting Nov 15 for reliability upgrades.

14-11-2025
Auto News
Kelana Jaya LRT Weekend Disruptions For Upgrades

Kelana Jaya LRT Weekend Disruptions For Upgrades

Rapid KL will upgrade the Kelana Jaya Line signalling system on Nov 15–16 and 29–30.

14-11-2025
Auto News
GWM Malaysia Accelerates Localisation Drive To Strengthen Supply Chain

GWM Malaysia Accelerates Localisation Drive To Strengthen Supply Chain

GWM Malaysia strengthens local partnerships and production to support the nation’s new-energy mobility ambitions.

Auto News
Upgraded Mitsubishi Eon Auto Mart 3S Centre Reopens in Melaka

Upgraded Mitsubishi Eon Auto Mart 3S Centre Reopens in Melaka

Mitsubishi Motors Malaysia, together with Eon Auto Mart, announces the relocation and upgrade of its outlet in Melaka.

14-11-2025
Auto News
PLUS Implements Night Contra-Flow On Elite Highway For Pipe Work

PLUS Implements Night Contra-Flow On Elite Highway For Pipe Work

Motorists on the Elite Highway should expect a contra-flow from Nov 17–20 for pipe work.

14-11-2025
Auto News
Flat Rate, Rule of 78, Reducing Balance: How Hire-Purchase Loans Really Work

Flat Rate, Rule of 78, Reducing Balance: How Hire-Purchase Loans Really Work

We break down a RM100,000 loan over seven years to show how reducing balance interest saves you money.

Auto News
Genting Highlands Set To Introduce Vehicle Fee to Boost Safety

Genting Highlands Set To Introduce Vehicle Fee to Boost Safety

Motorists heading to Genting Highlands will soon pay a fee to fund maintenance and safety on the 24 km private road.