Auto News

"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

Anis

Share via



According to Transport Minister Anthony Loke, the East Coast Rail Link (ECRL) is currently 42.06% complete. Loke stated today, while visiting the Genting ECRL Tunnel construction site, that the rail line's construction progress is on track to be completed by December 2026. However, Loke also stated that the ECRL project is currently facing a difficult challenge with the completion of the Genting ECRL tunnel, a twin tunnel spanning 16.39km in length that connects Bukit Tinggi, Pahang with Gombak, Selangor.


According to Loke, the tunnel will be built using a tunnel boring machine (TBM) rather than the drilling and explosives used in other ECRL tunnels. “I am confident with the management and workforce for the ECRL project to complete the project using two TBMs which were made in China. "When the construction crosses the Titiwangsa Range, these highly technological machines will be able to face engineering challenges and geological conditions," Loke said.



Construction on the first Genting tunnel has already begun, and approval to use the TBM for the second tunnel was obtained in November. “Boring works for the first Genting ECRL Tunnel have already reached a depth of 2.602km while the second reached 2.497km.




"For your information, the Genting ECRL Tunnel construction site spans 11.6ha in width and employs over 300 people."


"We hope that by January 2027, the ECRL will be fully operational, saving three hours of travel time from Kota Baru to Gombak," Loke added.

Gallery

Tagged:

ECRL
East Coast Rail Link (ECRL)
ECRL project
ECRL contruction progress
Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

Related News

Auto News
ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.

24-06-2025
Auto News
ECRL Is More Than 60% Complete - Malaysia Rail

ECRL Is More Than 60% Complete - Malaysia Rail

ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.

25-03-2024
Auto News
ECRL Project Progress Surpasses 56% - Loke

ECRL Project Progress Surpasses 56% - Loke

ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.

11-12-2023
Auto News
ECRL Kelantan Expected To Be Completed Six Months Earlier

ECRL Kelantan Expected To Be Completed Six Months Earlier

The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.

26-06-2023
Auto News
ECRL Project In Terengganu Reaches 55% Progress

ECRL Project In Terengganu Reaches 55% Progress

The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.

05-04-2023
Auto News
ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

ECRL project's Kuantan Tunnel will be completed by the end of April.

08-03-2023
Auto News
ECRL Land-Clearing; Enforcement Due To SOP Breach - Selangor MB’s Aide

ECRL Land-Clearing; Enforcement Due To SOP Breach - Selangor MB’s Aide

Selangor Forestry Department found that the alleged land clearing activities in the Selangor State Park are part of the ECRL project.

06-02-2023
Auto News
Kelantan And Terengganu ECRL Project Affected By Floods

Kelantan And Terengganu ECRL Project Affected By Floods

The floods last week impacted around 70% of the construction work at sections 1 and 2 of the East Coast Rail Line (ECRL), which spans 82 kilometres from Tunjong here to Setiu in Terengganu.

28-12-2022

Latest News

Auto News
JPJ: 2.3 Million Malaysians Have Expired Driving Licences

JPJ: 2.3 Million Malaysians Have Expired Driving Licences

JPJ claims there are over 2.3 million Malaysians with driving licences that are expired beyond three-year renewal window.

Auto News
Petrol Cards And Civil Servant Perks On Offer By Jetour Malaysia This Month

Petrol Cards And Civil Servant Perks On Offer By Jetour Malaysia This Month

Up to RM1 million worth of free petrol cards plus special perks for civil servants on offer from Jetour Malaysia this month.

20-09-2025
Auto News
TQ Wuling Bingo EV CKD Production Set to Begin in Dec 2025

TQ Wuling Bingo EV CKD Production Set to Begin in Dec 2025

The new SGMW-Tan Chong joint venture EV plant will start its local assembly efforts this Dec with the TQ Wuling Bingo.

19-09-2025
Auto News
MyKad Checks Urged Ahead of Fuel Price Drop

MyKad Checks Urged Ahead of Fuel Price Drop

Home minister urges Malaysians to fix faulty MyKad chips early to enjoy the upcoming targeted fuel subsidy.

19-09-2025
Auto News
GAC Emkoo Awarded 5-star ASEAN NCAP Rating

GAC Emkoo Awarded 5-star ASEAN NCAP Rating

Upcoming GAC Emkoo C-SUV earns coveted 5-star rating form ASEAN NCAP crash-testing regime.

19-09-2025
Auto News
KLCC Roads Closed Saturday For Sarong Music Run

KLCC Roads Closed Saturday For Sarong Music Run

Expect road closures and traffic delays around KLCC tomorrow for the Malaysia Sarong Music Run 2025.

19-09-2025
Auto News
Sand, Log Trucks Dominate Kelantan Roads - JPJ

Sand, Log Trucks Dominate Kelantan Roads - JPJ

Sand and log trucks make up most heavy vehicle traffic in Kelantan, with fewer overloaded cases.

19-09-2025
Auto News
Customs Seizes 32 Imported Cars Worth RM8.45 Million

Customs Seizes 32 Imported Cars Worth RM8.45 Million

Ops Purple uncovered vehicles stored beyond the legal limit, with unpaid duties and taxes totalling RM5.38 million.

19-09-2025