"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

Anis

Share via



According to Transport Minister Anthony Loke, the East Coast Rail Link (ECRL) is currently 42.06% complete. Loke stated today, while visiting the Genting ECRL Tunnel construction site, that the rail line's construction progress is on track to be completed by December 2026. However, Loke also stated that the ECRL project is currently facing a difficult challenge with the completion of the Genting ECRL tunnel, a twin tunnel spanning 16.39km in length that connects Bukit Tinggi, Pahang with Gombak, Selangor.


According to Loke, the tunnel will be built using a tunnel boring machine (TBM) rather than the drilling and explosives used in other ECRL tunnels. “I am confident with the management and workforce for the ECRL project to complete the project using two TBMs which were made in China. "When the construction crosses the Titiwangsa Range, these highly technological machines will be able to face engineering challenges and geological conditions," Loke said.



Construction on the first Genting tunnel has already begun, and approval to use the TBM for the second tunnel was obtained in November. “Boring works for the first Genting ECRL Tunnel have already reached a depth of 2.602km while the second reached 2.497km.




"For your information, the Genting ECRL Tunnel construction site spans 11.6ha in width and employs over 300 people."


"We hope that by January 2027, the ECRL will be fully operational, saving three hours of travel time from Kota Baru to Gombak," Loke added.

Gallery

Tagged:

ECRL
East Coast Rail Link (ECRL)
ECRL project
ECRL contruction progress
Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

Related News

Auto News
ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses

ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses

The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.

14-10-2025
Auto News
ECRL Project Hits 87% Completion by August 2025 – MoT

ECRL Project Hits 87% Completion by August 2025 – MoT

The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.

23-09-2025
Auto News
ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.

24-06-2025
Auto News
ECRL Is More Than 60% Complete - Malaysia Rail

ECRL Is More Than 60% Complete - Malaysia Rail

ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.

25-03-2024
Auto News
ECRL Project Progress Surpasses 56% - Loke

ECRL Project Progress Surpasses 56% - Loke

ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.

11-12-2023
Auto News
ECRL Kelantan Expected To Be Completed Six Months Earlier

ECRL Kelantan Expected To Be Completed Six Months Earlier

The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.

26-06-2023
Auto News
ECRL Project In Terengganu Reaches 55% Progress

ECRL Project In Terengganu Reaches 55% Progress

The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.

05-04-2023
Auto News
ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

ECRL project's Kuantan Tunnel will be completed by the end of April.

08-03-2023

Latest News

Auto News
Genting Highlands Set To Introduce Vehicle Fee to Boost Safety

Genting Highlands Set To Introduce Vehicle Fee to Boost Safety

Motorists heading to Genting Highlands will soon pay a fee to fund maintenance and safety on the 24 km private road.

Auto News
ACCCIM Calls For Gradual Enforcement Of Lorry Bridge Load Limits

ACCCIM Calls For Gradual Enforcement Of Lorry Bridge Load Limits

ACCCIM urges a phased rollout of lorry bridge load limit rules to avoid disrupting logistics and the supply chain.

13-11-2025
Auto News
Malaysia’s First BYD Tech Discovery Day Kicks Off in KL – Nov 14-16, Plaza Arkadia

Malaysia’s First BYD Tech Discovery Day Kicks Off in KL – Nov 14-16, Plaza Arkadia

Malaysia’s first BYD Tech Discovery Day is set to take place later this week on Nov 14-16 at Plaza Arkadia, KL.

13-11-2025
Auto News
MOF: RM36.3B Collected from Vehicle Taxes Over Three Years

MOF: RM36.3B Collected from Vehicle Taxes Over Three Years

Import and excise duties alone contributed more than RM26 billion, underscoring the auto sector’s economic weight.

Auto News
Johor Regent Flags Traffic Concerns Ahead Of RTS Link Launch

Johor Regent Flags Traffic Concerns Ahead Of RTS Link Launch

Tunku Mahkota Ismail flags potential congestion around Bukit Chagar as the JB–SG RTS Link nears completion.

13-11-2025
Auto News
Diesel Subsidy Reform Cuts Over 300 Million Litres In Sales

Diesel Subsidy Reform Cuts Over 300 Million Litres In Sales

Diesel subsidy rationalisation cuts sales by over 300 million litres a month, helping curb smuggling.

13-11-2025
Auto News
Updated Fuel Prices From 13 To 19 November

Updated Fuel Prices From 13 To 19 November

The Ministry of Finance (MoF) has announced the retail prices of all fuels in Malaysia, for the coming week of 13 to 19 November, 2025, the rates are as such.

12-11-2025
Auto News
RM1.7b NPE2 Extension To Ease KL Congestion By 2029 - Nanta

RM1.7b NPE2 Extension To Ease KL Congestion By 2029 - Nanta

The NPE2 will connect Pantai Dalam to Jalan Istana, cutting travel time by up to 25 minutes and improving traffic flow across KL.

12-11-2025