"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

According to Transport Minister Anthony Loke, the East Coast Rail Link (ECRL) is currently 42.06% complete.
Loke stated today, while visiting the Genting ECRL Tunnel construction site, that the rail line's construction progress is on track to be completed by December 2026.
However, Loke also stated that the ECRL project is currently facing a difficult challenge with the completion of the Genting ECRL tunnel, a twin tunnel spanning 16.39km in length that connects Bukit Tinggi, Pahang with Gombak, Selangor.
According to Loke, the tunnel will be built using a tunnel boring machine (TBM) rather than the drilling and explosives used in other ECRL tunnels.
“I am confident with the management and workforce for the ECRL project to complete the project using two TBMs which were made in China.
"When the construction crosses the Titiwangsa Range, these highly technological machines will be able to face engineering challenges and geological conditions," Loke said.

Construction on the first Genting tunnel has already begun, and approval to use the TBM for the second tunnel was obtained in November. “Boring works for the first Genting ECRL Tunnel have already reached a depth of 2.602km while the second reached 2.497km.

"For your information, the Genting ECRL Tunnel construction site spans 11.6ha in width and employs over 300 people."
"We hope that by January 2027, the ECRL will be fully operational, saving three hours of travel time from Kota Baru to Gombak," Loke added.
Gallery
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VRS1941
SELANGOR
BSU1362
JOHOR
JF184J
PULAU PINANG
PSF9442
PERAK
APL7973
PAHANG
CFH8701
KEDAH
KGJ2994
NEGERI SEMBILAN
NEM1378
KOTA KINABALU
SJU3475
KUCHING
QAB6563P
Last updated 29 Sep, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
Why Extending The ECRL To Rantau Panjang Could Be A Much Bigger Deal Than It Sounds
The proposed ECRL extension to Rantau Panjang could link Malaysia with Thailand and a wider Asian rail and port network. Here's why it matters.
29-09-2026
ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses
The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.
14-10-2025
ECRL Project Hits 87% Completion by August 2025 – MoT
The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.
23-09-2025
ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO
MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.
24-06-2025
ECRL Is More Than 60% Complete - Malaysia Rail
ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.
25-03-2024
ECRL Project Progress Surpasses 56% - Loke
ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.
11-12-2023
ECRL Kelantan Expected To Be Completed Six Months Earlier
The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.
26-06-2023
ECRL Project In Terengganu Reaches 55% Progress
The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.
05-04-2023
Latest News
Why Extending The ECRL To Rantau Panjang Could Be A Much Bigger Deal Than It Sounds
The proposed ECRL extension to Rantau Panjang could link Malaysia with Thailand and a wider Asian rail and port network. Here's why it matters.
29-09-2026
Malaysia's First Locally Built EV And PHEV Pick-Ups Are Coming From JAC
JAC will locally assemble its T9 EV and PHEV in Kulim, creating Malaysia's first CKD electrified pick-ups, with exports also being explored.
29-09-2026
Nearly Half A Million Summonses To Foreign Drivers: JPJ Says Some Employers Are Enabling It
JPJ issued 481,119 summonses to foreign drivers from 2024 to Sept 2026, while warning that some employers and vehicle owners are enabling illegal driving.
29-09-2026
Why Is Malaysia's Finance Ministry Testing A GWM WEY G9? Here's What We Know
Malaysia's Finance Ministry is evaluating a locally assembled GWM WEY G9 PHEV with SPANCO. Here's what the government fleet trial actually means.
25-09-2026
Several Riders Skidded At The Same 'Anti-Skid' Lane. Here's What JKR Says
Several riders skidded on an 'anti-skid' Federal Highway motorcycle lane. JKR is investigating the surface, contamination and other possible factors.
25-09-2026
Only RM10K Separates The Two CKD iCAUR 03s - Here's What You Get
Both iCAUR 03 variants are now CKD in Malaysia. With just RM10,140 between the RWD and iWD, here's what the extra money gets you.
25-09-2026
JPJ Letting Rohingya Apply For Driving Licences? Here's The Fact Check
A viral post claims JPJ is proposing to let Rohingya apply for driving licences in Malaysia. JPJ says the claim is false and has reported it to MCMC.
24-09-2026
Going To Singapore From Oct 6? Check Your VEP Or Risk Getting Turned Back
Driving to Singapore from Oct 6? Foreign vehicles will face VEP checks during SG Arrival Card submission. Here's what Malaysian drivers need to know.
24-09-2026
Show More
trending_flat