"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

According to Transport Minister Anthony Loke, the East Coast Rail Link (ECRL) is currently 42.06% complete.
Loke stated today, while visiting the Genting ECRL Tunnel construction site, that the rail line's construction progress is on track to be completed by December 2026.
However, Loke also stated that the ECRL project is currently facing a difficult challenge with the completion of the Genting ECRL tunnel, a twin tunnel spanning 16.39km in length that connects Bukit Tinggi, Pahang with Gombak, Selangor.
According to Loke, the tunnel will be built using a tunnel boring machine (TBM) rather than the drilling and explosives used in other ECRL tunnels.
“I am confident with the management and workforce for the ECRL project to complete the project using two TBMs which were made in China.
"When the construction crosses the Titiwangsa Range, these highly technological machines will be able to face engineering challenges and geological conditions," Loke said.

Construction on the first Genting tunnel has already begun, and approval to use the TBM for the second tunnel was obtained in November. “Boring works for the first Genting ECRL Tunnel have already reached a depth of 2.602km while the second reached 2.497km.

"For your information, the Genting ECRL Tunnel construction site spans 11.6ha in width and employs over 300 people."
"We hope that by January 2027, the ECRL will be fully operational, saving three hours of travel time from Kota Baru to Gombak," Loke added.
Gallery
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VRD8264
SELANGOR
BSR1865
JOHOR
JYB4276
PULAU PINANG
PSD3559
PERAK
APJ4418
PAHANG
CFG8970
KEDAH
KGG6901
NEGERI SEMBILAN
NEK7490
KOTA KINABALU
SJS5970
KUCHING
QAB672P
Last updated 28 Jun, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses
The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.
14-10-2025
ECRL Project Hits 87% Completion by August 2025 – MoT
The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.
23-09-2025
ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO
MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.
24-06-2025
ECRL Is More Than 60% Complete - Malaysia Rail
ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.
25-03-2024
ECRL Project Progress Surpasses 56% - Loke
ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.
11-12-2023
ECRL Kelantan Expected To Be Completed Six Months Earlier
The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.
26-06-2023
ECRL Project In Terengganu Reaches 55% Progress
The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.
05-04-2023
ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%
ECRL project's Kuantan Tunnel will be completed by the end of April.
08-03-2023
Latest News
Ferrari’s 16-Year Marketing Chief Stepped Down—But Was It Really His Choice?
Ferrari’s 16-year marketing lead has stepped down following the controversial Luce EV launch. Was this a planned exit or a high-profile design disaster casualty?
26-06-2026
Foreigners Are Using Local MyKads to Buy Vehicles—And Leaving Locals With a Legal Nightmare
Think renting your car to a foreigner is easy money? Think again. JPJ's Ops PeWA is seizing vehicles and hauling local owners to court. Learn the risks.
26-06-2026
From 80 Sen To RM4.30: A Simple Breakdown Of The New LRT3 Fares
Planning to ride the new LRT3? Get a simple breakdown of the Shah Alam Line fares.
25-06-2026
BUDI Diesel Explained: 200L Quota, No Deadlines, And The New 'Approved Person' Rule You Need To Know
Confused by the new RM2.10 diesel subsidy? Our ultimate guide covers quotas, how to claim your extra 100L, and the latest 'Approved Person' rules.
25-06-2026
RM500 Saman & Jail For Racing? 5 Massive Traffic Law Changes Coming To Malaysia
Transport Minister Anthony Loke tables the Road Transport (Amendment) Bill 2026. Here are 5 massive proposed traffic law changes coming to Malaysia.
24-06-2026
Government Pouring RM25.2 Million To Light Up 32 Dangerous Stretches So We Don't Have To Drive Blind At Night
The Ministry of Works approved RM25.24 mil to install 3,000 solar LED streetlights at 32 hazardous highway blackspots by November 2026. Is your route on the list?
24-06-2026
"Not Our Priority" — Minister Reveals The 4 Major Road Crimes JPJ Is Hunting Instead Of Sunshades
Transport Minister Anthony Loke clarifies that JPJ will not target motorists using removable car window sunshades, choosing instead to focus enforcement priorities on illegal racing, mat rempit, drunk driving, and reckless driving.
22-06-2026
M'sia Is Moving Toward Barrier-Free Tolls, But Gov Just Dropped One Non-Negotiable Rule
Works Minister Datuk Seri Alexander Nanta Linggi reveals that while Malaysia's barrier-free MLFF toll system negotiations are advanced, the government has set a strict, non-negotiable condition: road users must not pay higher toll fares.
22-06-2026
Show More
trending_flat