"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke
According to Transport Minister Anthony Loke, the East Coast Rail Link (ECRL) is currently 42.06% complete.
Loke stated today, while visiting the Genting ECRL Tunnel construction site, that the rail line's construction progress is on track to be completed by December 2026.
However, Loke also stated that the ECRL project is currently facing a difficult challenge with the completion of the Genting ECRL tunnel, a twin tunnel spanning 16.39km in length that connects Bukit Tinggi, Pahang with Gombak, Selangor.
According to Loke, the tunnel will be built using a tunnel boring machine (TBM) rather than the drilling and explosives used in other ECRL tunnels.
“I am confident with the management and workforce for the ECRL project to complete the project using two TBMs which were made in China.
"When the construction crosses the Titiwangsa Range, these highly technological machines will be able to face engineering challenges and geological conditions," Loke said.
Construction on the first Genting tunnel has already begun, and approval to use the TBM for the second tunnel was obtained in November. “Boring works for the first Genting ECRL Tunnel have already reached a depth of 2.602km while the second reached 2.497km.
"For your information, the Genting ECRL Tunnel construction site spans 11.6ha in width and employs over 300 people."
"We hope that by January 2027, the ECRL will be fully operational, saving three hours of travel time from Kota Baru to Gombak," Loke added.
Gallery




Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VPS2448
SELANGOR
BSH7417
JOHOR
JYG6345
PULAU PINANG
PRT9872
PERAK
APB2057
PAHANG
CFD4686
KEDAH
KGC2710
NEGERI SEMBILAN
NEH1090
KOTA KINABALU
SJM5854
KUCHING
QAB1588M
Last updated 16 Sep, 2025
Fuel Price
Petrol
RON 95
RM 2.05
RON 97
RM 3.18
+0.02
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.90
+0.02
EURO 5 B7
RM 3.10
+0.02
Last updated 11 Sep, 2025
Related News
ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO
MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.
24-06-2025
ECRL Is More Than 60% Complete - Malaysia Rail
ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.
25-03-2024
ECRL Project Progress Surpasses 56% - Loke
ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.
11-12-2023
ECRL Kelantan Expected To Be Completed Six Months Earlier
The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.
26-06-2023
ECRL Project In Terengganu Reaches 55% Progress
The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.
05-04-2023
ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%
ECRL project's Kuantan Tunnel will be completed by the end of April.
08-03-2023
ECRL Land-Clearing; Enforcement Due To SOP Breach - Selangor MB’s Aide
Selangor Forestry Department found that the alleged land clearing activities in the Selangor State Park are part of the ECRL project.
06-02-2023
Kelantan And Terengganu ECRL Project Affected By Floods
The floods last week impacted around 70% of the construction work at sections 1 and 2 of the East Coast Rail Line (ECRL), which spans 82 kilometres from Tunjong here to Setiu in Terengganu.
28-12-2022
Latest News
East-West Rail Link Across Titiwangsa Could Take 10-20 Years - Nanta
The east-west rail project crossing the Titiwangsa Range could take 10 to 20 years to complete.
16-09-2025
CAAM, MET Malaysia Inks Deal To Boost Flight Safety
CAAM and MET Malaysia have signed a new agreement to enhance aviation safety and operational efficiency.
16-09-2025
GM Number Plate Series Launched for Malaysia Day 2025
JPJ marks Malaysia Day 2025 with the launch of the GM number plate series, symbolising Gemilang Malaysia.
16-09-2025
GWM Wey 80 Teased Again, Now Renamed ‘Wey G9’ Instead
Upcoming GWM Wey 80 teased on social media, now bearing new ‘Wey G9’ nameplate too.
15-09-2025
Proton Iriz Production Ends – No Successor Planned, But Should There Be One?
Proton Iriz hatch production ends without a successor, leaving automaker without a new hatch model since 1994.
12-09-2025
West Ipoh Span Expressway Construction Will Begin After 2026
Construction of the West Ipoh Span Expressway is set to start after 2026, providing an alternative to the busy Menora Tunnel route.
12-09-2025
SSLR2 Highway Launched: RM7.6b Project Will Link Sarawak and Sabah
The 335km Sarawak–Sabah Link Road Phase 2 will connect key towns across northern Sarawak into Sabah.
12-09-2025
Proton: We Are Prepared To Serve New X50 After Sales In East Malaysia
Proton reassures it is more than capable of handling after sales coverage for face-lifted new X50 model in East Malaysia.
12-09-2025
Show More
trending_flat