R&M, Govt in Final Talks to Revive Stalled MEX II Highway

Kumeran Sagathevan

Share via

MEX-II-Caricarz-(2).jpg


The stalled MEX II Highway project has taken a step forward as discussions near completion between the government, sukuk holders, and the Receivers and Managers (R&M) appointed to take over from the original concessionaire.

Works Minister Datuk Seri Alexander Nanta Linggi said the talks are aimed at determining the most viable path to finishing the 18KM highway, which has remained incomplete since 2019.


MEX-II-Caricarz-(3).jpg


The negotiations, which follow a notice of default issued to the concessionaire in Jan 2022, cover updated completion costs, cash flow projections, traffic studies, toll rates and other measures to ensure the project remains financially and technically sound. 

The MEX II project, fully funded under a Build-Operate-Transfer (BOT) model, has no direct government financing, with all obligations now managed by the R&M on behalf of sukuk holders.

Nanta stressed that all progress claims are vetted by the concessionaire, supervising consultant and independent consulting engineer before being submitted to the sukuk holders. 


MEX-II-Caricarz-(1).jpegMEX-II-Caricarz-(7).jpg


He also clarified that any alleged false claims, including the RM416 million figure raised by Jerantut MP Khairil Nizam Khirudin fall outside the Works Ministry’s purview, as the project is privately financed.

Originally intended to ease congestion on the existing MEX Expressway, the MEX II extension was slated for completion in Dec 2019. Cash flow problems stalled the works, and the project later drew public attention amid investigations into hundreds of millions of ringgit in suspected false claims. 

With talks now in their final stages, a revised plan will be presented to the Cabinet, offering the clearest sign yet that the long-delayed highway may finally reach the finish line.


Source: NST

Tagged:

MEX II
Lebuhraya Maju Expressway Sdn. Bhd (MEX)
MEX Highway
Works Minister YB Alexander Nanta Linggi
MEX II Highway
Share This Article

Written By

Kumeran Sagathevan

More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!

Share via

Related News

Auto News

Govt Moves to Revive Delayed MEX II Project

From missed deadlines to MACC probes, troubled MEX II project finally see a turning point as govt swoops in to revive it.

Auto News

MACC: RM32 Million Seized From ‘Tan Sri’ Over Expressway Scandal

MACC seizes RM32 Million in luxury assets from a highway concessionaire amid a probe into the misuse of sukuk funds.

Auto News

Govt Moves to Revive Delayed MEX II Project

From missed deadlines to MACC probes, troubled MEX II project finally see a turning point as govt swoops in to revive it.

Auto News

MEX Highway To Test Out Contra-flow Route Starting 16 November From KM 11.5 to KM 7.9 North Bound

Contra-flow route on a trial basis on the MEX Highway heading north from Putrajaya towards Kuala Lumpur (KM 11.5 - KM 7.9) starting this November 16

Auto News

KKR Will Accelerate Melaka Road Works Ahead of 2025 ASEAN Chairman’s Meeting

64 locations identified in Melaka by KKR for road repairs ahead of 2025 ASEAN Chairman's meeting and Visit Melaka Year 2024.

Auto News

Smart Lane Not Implemented on KLK Due to Hilly Conditions – KKR

Works Minister says that Smart Lanes cannot be implemented on the KL-Karak highway due to its hilly conditions.

30-07-2024

Latest News

Auto News

PDRM: Elderly Drivers Involved in Nearly 7,000 Fatalities from 2019–2024

PDRM is urging a nationwide study on elderly driver safety after almost 7,000 fatalities between 2019 and 2024.

Auto News

RM15Mil A Year To Keep Awas Traffic Cameras Running - Loke

The government spends about RM15 million a year maintaining the Automated Awareness Safety System (Awas).

14-08-2025
Auto News

KTMB and SRT to Revive Iconic Bangkok–Butterworth Rail Link

Malaysia and Thailand agree to revive the Bangkok–Butterworth rail route.

Auto News

Updated Fuel Prices From 14 To 20 August

The Ministry of Finance (MoF) has announced the retail prices of all fuels in Malaysia, for the coming week of 14 to 20 August, 2025, the rates are as such.

13-08-2025
Auto News

iCaur Malaysia Established New Components Hub

iCaur Malaysia, ahead of the iCaur 03 launch, has opened an 88,000 square feet Components Hub in Shah Alam.

Auto News

Abandoned Cars In Cyberjaya Stir Safety Fears

Viral TikTok shows abandoned, damaged cars in Cyberjaya sparking public frustration and safety concerns.

13-08-2025
Auto News

R&M, Govt in Final Talks to Revive Stalled MEX II Highway

The government and sukuk holders are finalising a rescue plan for the stalled MEX II Highway.

Auto News

Malaysian Transport Safety Board Proposal Back on Table – MOT

The Ministry of Transport is drafting a policy to establish the Malaysian Transport Safety Board (MTSB).

13-08-2025