LRT3 Won’t Launch This Year As Glitches Persist, No New Date Set

Anis

Share via

download-(47)-full_normal-(1).jpg The LRT3 Shah Alam Line will not open this year, with Prasarana confirming that the line failed to complete its fault-free run (FFR) due to multiple software issues.

Prasarana officials said 33 glitches were detected during FFR tests that began on Aug 26, 2025. These included problems with train docking, door functions, trains failing to depart stations, and false speed or stopping alarms. 

"Because these faults surfaced during mandatory testing, the main contractor, Setia Utama LRT 3 Sdn Bhd, will not face penalties," Prasarana CEO Amir Hamdan said.

LRT3-Line-integration-map-full_normal-(1).jpg
For approval, the first train must complete 4,000km fault-free while other trains must each cover 2,500km. So far, the first train has met its requirement, and three others have surpassed 3,000km.

"The delay will not incur extra government costs as the project uses a fixed-price contract. All testing is expected to be completed by the end of Jan, with a new launch date to be announced next month," he added.

11102023-MRCB-having-analyst-briefing-at-LRT3-Training-Centre-in-Johan-Setia-ABDUL-RAZAK-LATIF-001-1-scaled-1920x1280-1-(1).jpg2159939-(1).jpg
He further noted that the project timeline remains aligned with the Transport Ministry’s expectations, although unforeseen software issues caused the missed December 2025 deadline.





Tagged:

Light Rail Transit 3 (LRT3)
LRT3 Shah Alam Line
LRT3 delay
Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

Related News

Auto News

LRT3 Might Be Delayed Again As Testing Encounters Issues - Report

The LRT3, expected to open early next year, may face further delays due to ongoing signalling system issues.

07-12-2025
Auto News

Budget 2026: Prasarana Seeks Continued Support for Travel Passes and LRT3

Prasarana moots continued support for travel passes, LRT 3 line completion, cites them as key to easing living costs and improving urban mobility.

Auto News

LRT3 Will Begin Operations On Sept 30 - Loke

LRT3 will begin operating on September 30 this year, Transport Minister Anthony Loke announced.

27-02-2025
Auto News

Loke: LRT3 Set To Begin Operations In Q3 2025 - 95.6% Complete

The LRT3 project is currently 95.6% complete and is scheduled to start ferrying passengers by Q3 2025.

Auto News

LRT3: Intermittent Road Closure On PLUS & SPRINT from July 2 to Sept 30

A series of intermittent road closures will take place on PLUS and SPRINT highways from July 2 to Sept 30 for LRT3 construction works.

Auto News

LRT 3: Subang Airport Road, Lane Closure & Road Diversion - 16 Sept To 31 Dec 2023

Lane closures and traffic diversions on Subang Airport Road in both the Subang and Kuala Lumpur directions will be extended for the LRT3 works

Auto News

LRT 3: NKVE Intermittent Lane Closure, KM14.9 To KM16.2 From 26 Aug - 28 Aug

LRT3 would carry out intermittent lane closures and traffic diversions on NKVE between KM14.9 and KM16.2 (for both Kuala Lumpur/Sungai Buloh and Shah Alam/Subang-bound lanes).

Auto News

LOKE : LRT3 86% Complete, To Begin Service 1 March 2025 - 67,000 Daily Capacity

Light Rail Transit 3 (LRT3) project 86% complete - Service to begin on 1 March, 2025

Latest News

Auto News

Hyundai Partners EON, Expands Local Network

Hyundai and EON have signed a LOI to open two new dealerships in Klang Valley and Penang.

Auto News

Perodua Traz/Nexis D66B Set to Debut on December 17

The long-awaited Perodua Traz/Nexis D66B SUV is set to make its official debut later on December 17, 2025.

12-12-2025
Auto News

Gemas-JB Electrified Train Cuts KL-Johor Travel To 4 Hours

The new electrified Gemas-Johor Bahru train line slashes travel time from KL to Johor to just 4 hours 20 minutes.

12-12-2025
Auto News

PLUS and KEC Ink MoU to Advance Smart Mobility

PLUS and KEC Smart Mobility signs agreement to develop smarter, greener and more connected expressway operations.

Auto News

LRT3 Won’t Launch This Year As Glitches Persist, No New Date Set

The LRT3 faces another delay after 33 software glitches were discovered during fault-free tests and no new opening date has been fixed yet.

12-12-2025
Auto News

CKD GWM WEY G9 Rolls Out at New EPMB Plant

CKD GWM WEY G9 rolls out from EPMB’s new Phase 2 plant, strengthening Malaysia’s NEV localisation ecosystem.

Auto News

Proton Shifts 13,451 Units Throughout Nov 2025

Proton closes Nov 2025 by shifting 13,451 units, touts to be “on target” for record exports growth too.

11-12-2025
Auto News

EV9, Carnival & Sportage Set To Kick-Start Local Kia Brand Revival

Newly formed Kia Sales Malaysia (KSM) principal-led entity set to reboot brand locally with EV9, Carnival and Sportage models first.

11-12-2025