Link Copiedcheck_circle
Auto News

Loke: LRT3 Set To Begin Operations In Q3 2025 - 95.6% Complete

Kumeran Sagathevan

Share via

453218537_1007686224479436_6295259034249152090_n.jpg


The Light Rail Transit 3 (LRT3) project is on track to ferry passengers by the third quarter (Q3) of next year (2025), says Transport Minister Anthony Loke.

According to Loke, the physical construction on the LRT3 project is expected to be finished by Oct this year, having progressed to a 95.6% completion rate. Subsequently, there will be a three to four month testing and commissioning phase after system integration, followed by further tests through early next year.


453382648_1007686204479438_2704506612600314558_n.jpg453252451_1007686131146112_7532968729376801684_n.jpg


Set to serve more than two million people, the LRT3 project in Petaling Jaya extends from Klang to Bandar Utama. Even though the Covid-19 epidemic caused delays, Prasarana Malaysia Bhd and its contractors have been working hard to make up for lost time and keep the project on schedule.


453495284_1007686081146117_6793017307642832688_n.jpg


Loke went on to say that the cabinet decided on July 5 to bring back five stations that had been cancelled: Tropicana, Temasya, Raja Muda, Bukit Raja, and Bandar Botanik. However, this would necessitate more work, like building three bus depots, expanding the train station at Johan Setia, as well as acquiring 150 feeder electric buses and seven sets of three-car trains.


453219303_1007686217812770_6307662427527364152_n.jpg


It is anticipated to cost RM3.8 billion to reopen these five stations, which were first put on hold in 2018 owing to low passenger ridership projections. This budget pays for contractors, rolling stock acquisitions, electronic bus construction, bus depot construction, infrastructure, system costs, and the restoration of the project scope.


453083082_1007686077812784_7157571752057684711_n.jpg453183840_1007686161146109_8992891956263002173_n.jpg


Loke promised that LRT3, which will have 20 stops, would not be affected by the extra work needed for these stations when it first opens and goes into service. Two more years will be needed for the installation of these five stations. But this won't have an impact on the LRT3's opening or regular operations," he reaffirmed.

The RM16 billion LRT3 project is expected to boost connectivity and public transport choices for Klang Valley residents. LRT3 is expected to be completed and put into service early in the following year, marking a major turning point in the development of public transit in Malaysia.



Source: NewStraitsTimes & FB Warga Prasarana 

Tagged:

Light Rail Transit 3 (LRT3)
Minister of Transport YB Anthony Loke
Prasarana Malaysia Bhd
Share This Article

Written By

Kumeran Sagathevan

More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!

Share via

Related News

Auto News
LRT3 Will Begin Operations On Sept 30 - Loke

LRT3 Will Begin Operations On Sept 30 - Loke

LRT3 will begin operating on September 30 this year, Transport Minister Anthony Loke announced.

27-02-2025
Auto News
LRT3: Intermittent Road Closure On PLUS & SPRINT from July 2 to Sept 30

LRT3: Intermittent Road Closure On PLUS & SPRINT from July 2 to Sept 30

A series of intermittent road closures will take place on PLUS and SPRINT highways from July 2 to Sept 30 for LRT3 construction works.

Auto News
LRT 3: Subang Airport Road, Lane Closure & Road Diversion - 16 Sept To 31 Dec 2023

LRT 3: Subang Airport Road, Lane Closure & Road Diversion - 16 Sept To 31 Dec 2023

Lane closures and traffic diversions on Subang Airport Road in both the Subang and Kuala Lumpur directions will be extended for the LRT3 works

Auto News
LRT 3: NKVE Intermittent Lane Closure, KM14.9 To KM16.2 From 26 Aug - 28 Aug

LRT 3: NKVE Intermittent Lane Closure, KM14.9 To KM16.2 From 26 Aug - 28 Aug

LRT3 would carry out intermittent lane closures and traffic diversions on NKVE between KM14.9 and KM16.2 (for both Kuala Lumpur/Sungai Buloh and Shah Alam/Subang-bound lanes).

Auto News
LOKE : LRT3 86% Complete, To Begin Service 1 March 2025 - 67,000 Daily Capacity

LOKE : LRT3 86% Complete, To Begin Service 1 March 2025 - 67,000 Daily Capacity

Light Rail Transit 3 (LRT3) project 86% complete - Service to begin on 1 March, 2025

Auto News
LRT3 Hits 99% Completion - Loke

LRT3 Hits 99% Completion - Loke

LRT3, which will connect Bandar Utama to Johan Setia, is 99% complete and on track for launch, says Transport Minister.

30-07-2025
Auto News
Bas.My Launched with Focus on Accessibility and Affordability

Bas.My Launched with Focus on Accessibility and Affordability

Loke: 48 brand-new buses and 13 routes, Bas.My is setting a new standards for stage buses in Kedah.

Auto News
Turun Anwar Rally: Loke Urges Train Use, PDRM May Divert 16 Roads

Turun Anwar Rally: Loke Urges Train Use, PDRM May Divert 16 Roads

Transport Minister and PDRM urges public to plan ahead and use public transportation to ease congestion caused by Turun Anwar rally.

Latest News

Auto News
KPDN Probes SG Driver Sighted Pumping RON95 in Johor

KPDN Probes SG Driver Sighted Pumping RON95 in Johor

KPDN is probing a viral incident where a Singapore-registered car was seen pumping subsidised RON95 fuel.

Auto News
Traffic Diversion On Bukit Gambir-Tangkak From Aug 5

Traffic Diversion On Bukit Gambir-Tangkak From Aug 5

Traffic along the NSE near Tangkak will be diverted in both directions from Aug 5 for bridge construction.

04-08-2025
Auto News
1,489 Summonses Issued in VEP Enforcement Operation – JPJ

1,489 Summonses Issued in VEP Enforcement Operation – JPJ

JPJ has issued a total of 1,489 summonses during an enforcement operation on VEP at the JB-Singapore land border.

04-08-2025
Auto News
No Green Light Yet For Cross-Border Ride-Hailing Between SG, JB.

No Green Light Yet For Cross-Border Ride-Hailing Between SG, JB.

Singapore holds off on cross-border ride-hailing plans, opting instead to improve its existing taxi scheme with Malaysia.

04-08-2025
Auto News
RM110 Million Collected from Special Plate Sales Since 2023 – MoT

RM110 Million Collected from Special Plate Sales Since 2023 – MoT

A total of RM110 million has been collected from sales of special number plates since 2023, the Transport Ministry says.

04-08-2025
Auto News
Nanta: 80% of Accidents Driver-Linked, Road Budget 70% Short

Nanta: 80% of Accidents Driver-Linked, Road Budget 70% Short

With 80% of accidents linked to drivers, the Works Ministry still grapples with limited funds to fix and rebuild roads.

Auto News
LRT3 Shah Alam Line Opening Could Be Delayed to Oct 31 – Report

LRT3 Shah Alam Line Opening Could Be Delayed to Oct 31 – Report

The LRT3 Shah Alam line opening could be delayed until Oct 31 instead of the planned launch date of Sept 30.

04-08-2025
Auto News
ETS to JB Sentral ‘On Track’, But Not Quite There Yet

ETS to JB Sentral ‘On Track’, But Not Quite There Yet

KTMB says electrification works between Kluang to JB Sentral are ongoing and the extension will proceed once conditions are met.