ART Smart Tram Prototype Will Begin Test Run In Kuching Next Month
According to state Transport Minister Datuk Seri Lee Kim Shin, the engineering run for the world's first prototype hydrogen-powered Autonomous Rapid Transit (ART) smart tram will begin at the Isthmus here on September 4 and will last until October 31, Malay Mail reported.
Lee stated in a statement that the test run will take place along the Jalan Keruing loop, passing Menara LCDA, Menara SEDC, Menara Sarawak Energy, and Borneo Convention Centre Kuching (BCCK).
“The engineering run is to identify any potential issues before the start of the Proof of Concept (POC) exercise in Samarahan,” he said.
Lee said the smart tram, developed by China's CRRC Zhuzhou Institute Co Ltd, had been fully assembled over the past two weeks after arriving at Senari Terminal from Shanghai Port on August 5.
“The hydrogen vehicle will be moved to Kuching Port Authority’s Pending Terminal where it will be stabled (parked) until the end of the engineering run period in October.
“Refuelling of the prototype ART hydrogen vehicle will be done at Pending Terminal because Mobile Hydrogen Refuelling Station will be based there,” he said.
During a special briefing last week, he added, the ministry met with industry players and government agencies with offices on the Isthmus, as well as the relevant enforcement authorities.
“To prepare for the engineering run, works to close certain sections of the road in the area will begin tomorrow (August 23).
“The road closures will be advertised on Sarawak Metro’s social media platforms and in local newspapers from August 22. This initiative aims to notify residents and employees who work in the vicinity, enabling them to adjust their daily travel routines during the two-month period,” he added.
"From August 22, the road closures will be advertised on Sarawak Metro's social media platforms and in local newspapers." "The goal of this initiative is to notify residents and employees who work nearby so that they can adjust their daily travel routines during the two-month period," he said.
Lee also stated that the smart tram would travel to Kota Samarahan in November for a month-long proof-of-concept test.
This second test would begin on a 3km permanent dedicated lane constructed between two roundabouts on a section of the Kuching-Samarahan Expressway.
“The dedicated lane is near the Sarawak Heart Centre to the roundabout near SAINS. This POC exercise is conducted to gather data to evaluate the feasibility of the prototype for the final design of the ART to accommodate a maximum capacity of passengers,” he said.
However, Lee stated that the passenger service will be closed to the public during both test runs, and that only selected stakeholders from the relevant public and private sectors will be able to use it.
“The main reason we are not opening this up to the public, in terms of riding on the ART, is due to the fact that this is still a prototype vehicle and the main aim is to test its performance here in Sarawak.”
Gallery






Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VPS9429
SELANGOR
BSH9196
JOHOR
JYH547
PULAU PINANG
PRU2331
PERAK
APB3335
PAHANG
CFD5277
KEDAH
KGC3540
NEGERI SEMBILAN
NEH1677
KOTA KINABALU
SJM6903
KUCHING
QAB2009M
Last updated 24 Sep, 2025
Fuel Price
Petrol
RON 95
RM 2.05
RON 97
RM 3.21
+0.03
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.93
+0.03
EURO 5 B7
RM 3.13
+0.03
Last updated 18 Sep, 2025
Related News
Govt Calls For Bids For Elevated ART In JB
Public-Private Partnership Unit (UKAS) will soon be initiating the process of soliciting proposals for ART in JB.
14-02-2025
Is Sarawak’s Hydrogen-Powered ART Project a Risky Gamble?
Sarawak’s decision to pursue hydrogen-powered Autonomous Rapid Transit (ART) quizzed.
12-09-2024
Latest News
Amir Hamzah: No Daily Refuel Limits Under Budi95 For Now
Amir Hamzah: No limit on daily refuels, data analytics to monitor RM1.99 subsidy use to detect abuse.
23-09-2025
New RM22.7M JPJ Kajang Office Set for 2027
The new RM22.7M JPJ Kajang office will feature modern facilities and improved services for the public by 2027.
23-09-2025
ECRL Project Hits 87% Completion by August 2025 – MoT
The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.
23-09-2025
Amir Hamzah: No Back-to-Back Pumping of RM1.99 RON95 A Day
Amir Hamzah: Govt. won't allow multiple subsidised refuels in a day as BUDI95 takes effect Sept 30.
23-09-2025
Petron Lubricants Gains SIRIM Certification & Label
Petron Malaysia acquires SIRIM genuine product licence certification and label for engine lubricant product line-up.
23-09-2025
Govt Will Allow Commercial RV Rentals from 2026 - Loke
Starting January 2026, RVs can be licensed for commercial use, making self-drive RV holidays safer and regulated.
23-09-2025
BUDI95: RON95 Ban on Foreign Cars Still On, RM1.99 for Malaysians
BUDI95 keeps foreign-registered cars out of subsidised RON95, only Malaysians with local vehicles can pump at RM1.99 per litre.
23-09-2025
Rapid Rail Set To Launch Real-Time Crowd Tracking & AI Security
Rapid Rail will introduce a live tracker showing coach crowd levels so commuters can board with less stress.
23-09-2025
Show More
trending_flat