ECRL Project Achieved 52.9 Percent Completion
The East Coast Rail Link (ECRL) project has reached 52.9 percent completion and is expected to be completed by 2027, The Star reported.
According to Transport Minister Anthony Loke Siew Fook, major construction works such as beam launching, structural work and track laying are currently underway along the ECRL line.
Loke also stated that the ECRL project from Kota Baru, Kelantan to Gombak is scheduled to be completed on December 31, 2026, with the stretch from Gombak to Port Klang scheduled to be completed on December 31, 2027.
-full-full_normal.jpg)
"Following this, the tunnel borring works for the first tunnel in Genting has reached 3.1 kilometres (km), while the second Genting tunnel has reached 4.29 km.
"At the same time, a total of 25 tunnels have been penetrated as of Aug 25, including 21 tunnels in Section A and B of the project, while the remaining four in Section C," he said.
Meanwhile, he stated that the ECRL corridor would have an agglomeration (assemblage) effect, increasing job opportunities and serving as an economic centre to stimulate economic growth.

At the same time, Loke stated that the project site had been finalised and approved by relevant technical agencies, with more than 70% completion.
He stated that ECRL developers discovered the area to be prone to flooding through studies conducted by hydrology and hydraulics consultants on previous flood situations in the area.
"Following this, they proposed an optimal design, by taking into account technical aspects, value engineering and flood risk in the area. "The ministry will also ensure that the project's main developer, Malaysia Rail Link Sdn Bhd (MRL), alongside its main contractor, China Communications Construction Company (CCCC) maintains public safety during project implementation."
MRL and CCCC signed a supplementary agreement in 2019 to restart the ECRL project at a lower cost.
The new ECRL alignment is now 40 kilometres shorter, from 688 kilometres to 648 kilometres, because it no longer tunnels through the Titiwangsa Main Range, which separates Selangor and Pahang. It runs south from Kota Baru to Port Klang, passing through Mentakab, Jelebu, Kuala Kelawang, Bangi/Kajang, and Putrajaya.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VQQ9557
SELANGOR
BSN4490
JOHOR
JYT4137
PULAU PINANG
PSA6256
PERAK
APG967
PAHANG
CFF8337
KEDAH
KGE8161
NEGERI SEMBILAN
NEJ8037
KOTA KINABALU
SJQ8463
KUCHING
QAB4203N
Last updated 19 Mar, 2026
Fuel Price
Petrol
RON 95
RM 2.59
+0.05
RON 97
RM 3.15
+0.05
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.04
+0.05
EURO 5 B7
RM 3.24
+0.05
Last updated 26 Feb, 2026
Related News
Kuantan Welcomes ECRL’s First Trains Ahead of 2027 Operations
The first ECRL electric passenger trains and freight locomotives have arrived in Kuantan as the project moves closer to operations in 2027.
11-02-2026
ECRL Fares To Be Announced Ahead of 2027 Launch
ECRL fares will be disclosed several months prior to the commencement of operations in January 2027, according to Transport Minister.
30-01-2026
ECRL Launch Hinges On System Integration, Jan 2027 Target Maintained
The ECRL remains on schedule, with system integration and testing now the key focus ahead of its planned Jan 2027 launch.
29-01-2026
ECRL First EMU Trains, E-Locos Head To Malaysia For Testing
Malaysia’s East Coast Rail Link gears up as its first EMUs and electric locomotives arrive for testing and future service.
17-12-2025
First ECRL Trains Depart China, Remaining Units Arriving Through 2026
First ECRL trains depart China, with remaining units scheduled to arrive through 2026.
28-11-2025
ECRL Nears Completion with 89% Progress, Operations Set for 2027
ECRL is on track to begin services from Kota Bharu to Gombak in Jan 2027, as construction progress hits 89%.
24-11-2025
ECRL Trains Fully Assembled, Ready for Malaysia
The first batch of trains for the East Coast Rail Link (ECRL) is now ready in Dalian, China.
21-11-2025
ECRL Hits 88% Milestone As Key C1B Stretch Completed
The ECRL project has hit 88% completion with the C1B Segment now successfully completed.
05-11-2025
Latest News
From 82 Minutes to 8: How the Mutiara Line is Giving Penangites Their Time Back
Is the 80-minute Penang Bridge crawl finally ending? The Mutiara Line LRT links Butterworth to Komtar in just 8 minutes. Get the latest 2026 project updates, station lists, and more.
17-03-2026
The 2026 Proton X90 Buyer’s Warning: 5 Critical Safety Features You Are No Longer Getting
ASEAN NCAP revokes Proton X90’s 5-star rating. The 2026 facelift is downgraded to 1-star after stripping critical ADAS features. Is your family safe? Get the full safety specs here.
16-03-2026
9,000+ Drivers Chose Toyota Hybrids This Year: Proof That Toyota’s Multi-Pathway Strategy Works
Toyota Malaysia hits 9,556 sales in early 2026, proving the "Multi-Pathway" strategy works. From Vios Hybrid to Vellfire HEV, see why hybrids are winning the sales war.
12-03-2026
Chery Tiggo 7 is Now the Safest Chinese SUV on the Planet, This Is Why
The Chery Tiggo 7 makes history as the only Chinese SUV to sweep 5-star ratings from Euro NCAP, ANCAP, and ASEAN NCAP. With a record 94.68 points, see why this is 2026’s safest family SUV.
11-03-2026
Sepang Dates Confirmed: Catch Team Porsche Malaysia in Action on 21–23 August
While the 2026 Porsche Carrera Cup Asia (PCCA) season kicks off in Shanghai this weekend, Malaysian fans are already looking ahead to the highlight of the year: the homecoming.
10-03-2026
Iran-US War Day 10: It’s Not Just Fuel — Malaysia’s Automotive Industry Faces New Risks
While the BUDI95 subsidy program is already feeling the heat of oil prices flirting with US$120 a barrel, the true threat to our automotive sector lies beneath the surface.
09-03-2026
Prasarana to Reveal LRT3 Launch Date This April—Here’s Everything We Know So Far
The wait for the LRT3 Shah Alam Line is entering its final stretch. After months of "will they, won't they" speculation, Prasarana has officially pointed to April 2026 as the month of truth.
05-03-2026
EV King is Here: How Proton e.MAS 5 Dethroned Popular Petrol Cars in 60 Days
PRO-NET has announced that the Proton e.MAS 5 has officially surpassed the 5,000-unit delivery milestone in just two months.
05-03-2026
Show More
trending_flat