ECRL Is More Than 60% Complete - Malaysia Rail
-full_normal.jpg)
Photo: Bernama.
Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak, stated that the East Coast Rail Link (ECRL) has made 62.4% progress. According to Bernama, the project's Kelantan phase is currently 75.8% complete.
“The 43km ECRL alignment in Kelantan involves the construction of two stations, Kota Bharu for passengers only and Pasir Puteh Station for passengers and cargo.
The alignment from Kota Bharu to the integrated transport terminal in Gombak, Selangor, is expected to be completed on time in December 2026, with services beginning in January 2027. Meanwhile, the ECRL alignment from Gombak to Port Klang is scheduled to be completed by December 2027, Darwis added.
To recap, the ECRL project is a 665-kilometer, RM50.3 billion rail network that connects the east and west coasts, specifically Kota Bharu in Kelantan and Gombak (Selangor). The travel time between these points is expected to be reduced to four hours from the current seven-hour road journey, or more than 12 hours during the holiday season.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VPY4627
SELANGOR
BSK173
JOHOR
JYK7418
PULAU PINANG
PRV5289
PERAK
APC3978
PAHANG
CFE856
KEDAH
KGC9101
NEGERI SEMBILAN
NEH5637
KOTA KINABALU
SJN5907
KUCHING
QAB4931M
Last updated 10 Nov, 2025
Fuel Price
Petrol
RON 95
RM 2.60
RON 97
RM 3.20
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.02
+0.07
EURO 5 B7
RM 3.22
+0.07
Last updated 06 Nov, 2025
Related News
ECRL Hits 88% Milestone As Key C1B Stretch Completed
The ECRL project has hit 88% completion with the C1B Segment now successfully completed.
05-11-2025
MOT Eyes Rail Expansion, Road Safety and Airport Improvements
Transport Minister YB Loke Siew Fook outlines major transport projects and safety reforms under the 2026 Budget.
30-10-2025
ECRL Project On Track Despite RM2.9mil Theft Losses
MRL boosts security after 38 theft cases but says the ECRL project remains on schedule.
30-10-2025
ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses
The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.
14-10-2025
Budget 2026: Prasarana Seeks Continued Support for Travel Passes and LRT3
Prasarana moots continued support for travel passes, LRT 3 line completion, cites them as key to easing living costs and improving urban mobility.
09-10-2025
ECRL Project Hits 87% Completion by August 2025 – MoT
The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.
23-09-2025
ECRL Work Halted - Petronas Gas Pipeline Leak, Safety Zone Declared
Petronas Gas pipeline leak at the ECRL project has halted works, emergency crews racing to purge butane gas.
22-09-2025
ECRL Cites Potential Delay From Escalated Cable and Wire Theft
ECRL says thefts of cable and wires could derail construction progress on the 665 km railway project.
11-09-2025
Latest News
PLUS To Close Two Bangi Ramps Nightly Until Nov 28
PLUS will close two ramps near Bangi nightly from 10PM to 5AM starting today until Nov 28.
10-11-2025
KLIA Aerotrain Halts Daily Midnight To 5am For Maintenance
KLIA Aerotrain will stop running every night from midnight to 5am for routine checks and maintenance.
10-11-2025
4.4 Mil Old Vehicles Threaten Road Safety, Incentive Alone Insufficient
JPJ data shows over 4.4 million old vehicles are still on the road making up about 17% of the country’s 25.7m active vehicles.
10-11-2025
Proton Shifts 15,575 Units In Oct 2025, Outgoing Saga Still Leads
Proton closes Oct 2025 by shifting 15,575 units, outgoing Saga sales spikes to 12-year high ahead of successor’s debut.
10-11-2025
JPJ Warns Public Against Fake “Free Driving Licence” TikTok Scams
JPJ has warned the public about fake TikTok posts claiming people can get free driving licences without any tests.
10-11-2025
RM3b Juru–Sungai Dua Link Cuts Travel Time To Just 20 Minutes
RM3 billion traffic dispersal project aims to slash travel time between Juru and Sungai Dua from an hour to just 20 minutes.
10-11-2025
Nanta: Barrier-Free ANPR Toll System Still at RFP Stage
The Works Ministry is inviting proposals for an ANPR-based barrier-free MLFF toll system.
10-11-2025
New Leapmotor 3S Showroom Opens In Ipoh, Perak
Perak state capital of Ipoh gains new Leapmotor brand 3S showroom and service outlet operated by dealers CST Auto.
07-11-2025
Show More
trending_flat