Loke: ECRL Project Will Complete In 2026, Operational In January 2027
-full_normal.webp)
The Minister of Transport, YB Anthony Loke Siew Fook, revealed yesterday during the East Coast Rail Link (ECRL) breaking fast ceremony with the ECRL team that the ECRL project remains on track for completion in Dec 2026, with operations slated to begin in Jan 2027.
This megaproject aims to dramatically cut the travel time between Kota Bharu and Kuala Lumpur to four hours, down from the current seven hours by automobile.
As of March, the ECRL is 64% complete throughout four states: Kelantan, Terengganu, Pahang, and Selangor.
-full_normal.webp)
Loke adds that the project has entered a new phase since 2023, with a focus on important infrastructure features such as flyover installations, track laying, and station and railway depot building. There have been approximately 1,900 work sites, of which nearly 650 are still active.
Notable milestones along the 665 KM line include excavation depths of more than 8 KM You through the Genting Tunnel's twin bore, which is set to become Asia's longest rail tunnel when it breaks through in the second quarter of 2025.
-full_normal.webp)
Furthermore, the use of the unique track-laying machine CCPG-500A, a first in Malaysia's rail industry, commenced on March 9, laying tracks for the second phase between Kuantan Port and Maran in Pahang.
The second phase of the 97 KM line is planned to be finished in June 2024. After which, track installation between Dungun and Kota Bharu will commence followed by electrification system installation at the Cherating Station in May.
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VPY9427
SELANGOR
BSK1615
JOHOR
JYL423
PULAU PINANG
PRV6478
PERAK
APC4854
PAHANG
CFE1516
KEDAH
KGC9732
NEGERI SEMBILAN
NEH5933
KOTA KINABALU
SJN6467
KUCHING
QAB5123M
Last updated 13 Nov, 2025
Fuel Price
Petrol
RON 95
RM 2.65
+0.05
RON 97
RM 3.25
+0.05
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.07
+0.05
EURO 5 B7
RM 3.27
+0.05
Last updated 13 Nov, 2025
Related News
ECRL Hits 88% Milestone As Key C1B Stretch Completed
The ECRL project has hit 88% completion with the C1B Segment now successfully completed.
05-11-2025
ECRL Project On Track Despite RM2.9mil Theft Losses
MRL boosts security after 38 theft cases but says the ECRL project remains on schedule.
30-10-2025
MOT Eyes Rail Expansion, Road Safety and Airport Improvements
Transport Minister YB Loke Siew Fook outlines major transport projects and safety reforms under the 2026 Budget.
30-10-2025
ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses
The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.
14-10-2025
Budget 2026: Prasarana Seeks Continued Support for Travel Passes and LRT3
Prasarana moots continued support for travel passes, LRT 3 line completion, cites them as key to easing living costs and improving urban mobility.
09-10-2025
ECRL Project Hits 87% Completion by August 2025 – MoT
The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.
23-09-2025
ECRL Work Halted - Petronas Gas Pipeline Leak, Safety Zone Declared
Petronas Gas pipeline leak at the ECRL project has halted works, emergency crews racing to purge butane gas.
22-09-2025
ECRL Cites Potential Delay From Escalated Cable and Wire Theft
ECRL says thefts of cable and wires could derail construction progress on the 665 km railway project.
11-09-2025
Latest News
Genting Highlands Set To Introduce Vehicle Fee to Boost Safety
Motorists heading to Genting Highlands will soon pay a fee to fund maintenance and safety on the 24 km private road.
13-11-2025
ACCCIM Calls For Gradual Enforcement Of Lorry Bridge Load Limits
ACCCIM urges a phased rollout of lorry bridge load limit rules to avoid disrupting logistics and the supply chain.
13-11-2025
Malaysia’s First BYD Tech Discovery Day Kicks Off in KL – Nov 14-16, Plaza Arkadia
Malaysia’s first BYD Tech Discovery Day is set to take place later this week on Nov 14-16 at Plaza Arkadia, KL.
13-11-2025
MOF: RM36.3B Collected from Vehicle Taxes Over Three Years
Import and excise duties alone contributed more than RM26 billion, underscoring the auto sector’s economic weight.
13-11-2025
Johor Regent Flags Traffic Concerns Ahead Of RTS Link Launch
Tunku Mahkota Ismail flags potential congestion around Bukit Chagar as the JB–SG RTS Link nears completion.
13-11-2025
Diesel Subsidy Reform Cuts Over 300 Million Litres In Sales
Diesel subsidy rationalisation cuts sales by over 300 million litres a month, helping curb smuggling.
13-11-2025
Updated Fuel Prices From 13 To 19 November
The Ministry of Finance (MoF) has announced the retail prices of all fuels in Malaysia, for the coming week of 13 to 19 November, 2025, the rates are as such.
12-11-2025
RM1.7b NPE2 Extension To Ease KL Congestion By 2029 - Nanta
The NPE2 will connect Pantai Dalam to Jalan Istana, cutting travel time by up to 25 minutes and improving traffic flow across KL.
12-11-2025
Show More
trending_flat