Putrajaya P15H Slip Road Now Open, No Highway Lane Closure During Aidiladha
Datuk Seri Alexander Nanta Linggi, Minister of Works, today officiated the handover ceremony of the 300-metre-long slip road project from Jalan P15H to Persiaran Timur in Putrajaya to Dr Zaliha Mustafa, Minister in the Prime Minister's Department (Federal Territory).
According to Nanta, the slip road construction which began on Dec 29, 2020, was only completed on May 15 of this year, after numerous hurdles along the way.
The biggest hurdle for the RM12.63 million project was the Covid-19 pandemic, as well as the project's position along the main utility corridor in Persiaran Timur, Putrajaya, which had an indirect impact on the project's completion schedule.
This project includes the installation of a drainage system, environmental conservation, and upgraded traffic signals at the P15H intersection.
According to Nanta, this slip road would be able to reduce traffic congestion on Precinct 15's main road (Roundabout 5 intersection) during peak hours and provide an alternative route to nearly 35,000 people at Precinct 15, and the surrounding areas to government offices in Putrajaya.
On a separate note, Nanta stated that there will be no highway closures for maintenance work during the Aidiladha celebrations from June 12 to 19, unless it was an emergency.
Furthermore, highway concessionaires have been encouraged to activate smart lanes at specific areas to improve traffic flow. The Highway Authority (LLM) would also monitor the advocacy to motorists on smart lanes and their effectiveness for future improvements.
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VPM6307
SELANGOR
BSG8025
JOHOR
JYE5436
PULAU PINANG
PRT1287
PERAK
ANY7544
PAHANG
CFD964
KEDAH
KGB6538
NEGERI SEMBILAN
NEG6459
KOTA KINABALU
SJL9999*
KUCHING
QAB8573L
Last updated 05 Aug, 2025
Fuel Price
Petrol
RON 95
RM 2.05
RON 97
RM 3.17
-0.04
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.91
EURO 5 B7
RM 3.11
Last updated 31 Jul, 2025
Related News
Nanta: 80% of Accidents Driver-Linked, Road Budget 70% Short
With 80% of accidents linked to drivers, the Works Ministry still grapples with limited funds to fix and rebuild roads.
04-08-2025
Toll Freeze Only For 2025, No Extensions Planned
The toll freeze is limited to 2025, with no changes planned for existing concession terms.
31-07-2025
Toll Hike Delay Spares Private Car Users Up to 83% in Fare Increase – Nanta
Class 1 car owners would have faced a toll hike of up to 83% if not for the postponed toll rate adjustment, says the Works Minister.
29-07-2025
KKR: RM94 Million Spent on Restoring Roads After 2024 Floods
The government spent RM94 million to restore roads and infrastructure damaged by the 2024 floods, with most repairs now completed.
15-07-2025
Nanta: Damaged Road Surface Linked to Cyclist’s Death
Road damage blamed on heavy lorry traffic; urgent repairs ordered following fatal crash.
16-06-2025
Malaysia Deploys AI In Road Management - Works Minister
Works Minister has announced the adoption of AI for enhanced road management in this country.
29-05-2025
Govt Moves to Revive Delayed MEX II Project
From missed deadlines to MACC probes, troubled MEX II project finally see a turning point as govt swoops in to revive it.
13-05-2025
Works Minister Scheduled To Meet Concessionaire Over Fatal Johor Pothole Accident
Works minister has scheduled an urgent meeting with concessionaire after the fatal Johor pothole accident.
26-03-2025
Latest News
JPJeID Registration Now Available at Driving Institutes
JPJeID registration is now available at all driving institutes, streamlining access to MySIKAP and MyJPJ services.
05-08-2025
Couple Killed In Ford Mustang Crash Near Segamat
A married couple died after their Ford Mustang crashed into an electric pole along Jalan Segamat-Kuantan.
05-08-2025
Proton e.MAS 5 ‘MISI 5’ National Tour – Aug to Oct, Launching Soon?
The upcoming Proton e.MAS 5 is going on a ‘MISI 5’ national tour from August to October, 2025. Launch imminent?
05-08-2025
MoF: Fuel Subsidy Rollout Under Testing, Launches End-Sept
MoF is finalising the targeted fuel subsidy system, with full rollout details expected by end-Sept.
05-08-2025
Ferraris, Lambos Among 1,000 Untaxed Vehicles - JPJ
JPJ flags over 1,000 luxury cars, including Ferraris and Lambos, for missing road tax and insurance.
05-08-2025
KLIA Apologises After Aerotrain Breaks Down Again
KLIA’s Aerotrain stalled for 15 minutes due to a door glitch, prompting an apology and public frustration.
05-08-2025
Amir Hamzah: PADU at the Core of RON95 Subsidy Implementation
With over 30 million individual profiles, PADU will guide MOF’s effort to roll out a more precise RON95 petrol subsidy.
05-08-2025
KPDN Probes SG Driver Sighted Pumping RON95 in Johor
KPDN is probing a viral incident where a Singapore-registered car was seen pumping subsidised RON95 fuel.
04-08-2025
Show More
trending_flat