Putrajaya P15H Slip Road Now Open, No Highway Lane Closure During Aidiladha

Kumeran Sagathevan

Share via

447981595_18030647414079211_3720582267749590776_n.jpg


Datuk Seri Alexander Nanta Linggi, Minister of Works, today officiated the handover ceremony of the 300-metre-long slip road project from Jalan P15H to Persiaran Timur in Putrajaya to Dr Zaliha Mustafa, Minister in the Prime Minister's Department (Federal Territory).

According to Nanta, the slip road construction which began on Dec 29, 2020, was only completed on May 15 of this year, after numerous hurdles along the way.


447970935_18030647501079211_7755285677274691871_n.jpg447969488_18030647444079211_5497934012209521434_n.jpg


The biggest hurdle for the RM12.63 million project was the Covid-19 pandemic, as well as the project's position along the main utility corridor in Persiaran Timur, Putrajaya, which had an indirect impact on the project's completion schedule.

This project includes the installation of a drainage system, environmental conservation, and upgraded traffic signals at the P15H intersection.


447861583_18030647435079211_2895269413971214195_n.jpg447861782_18030647453079211_8205748410318092614_n.jpg


According to Nanta, this slip road would be able to reduce traffic congestion on Precinct 15's main road (Roundabout 5 intersection) during peak hours and provide an alternative route to nearly 35,000 people at Precinct 15, and the surrounding areas to government offices in Putrajaya.

On a separate note, Nanta stated that there will be no highway closures for maintenance work during the Aidiladha celebrations from June 12 to 19, unless it was an emergency.


447969786_18030647387079211_181821602291834799_n.jpg


Furthermore, highway concessionaires have been encouraged to activate smart lanes at specific areas to improve traffic flow. The Highway Authority (LLM) would also monitor the advocacy to motorists on smart lanes and their effectiveness for future improvements.



Share This Article

More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!

Share via

JPJ Running Numbers

KUALA LUMPUR

VQE4077

SELANGOR

BSL409

JOHOR

JYN2436

PULAU PINANG

PRW7096

PERAK

APD4764

PAHANG

CFE4955

KEDAH

KGD4892

NEGERI SEMBILAN

NEH9565

KOTA KINABALU

SJP3604

KUCHING

QAB7750M

Last updated 20 Dec, 2025

Fuel Price

Petrol

RON 95

RM 2.64

-0.02

RON 97

RM 3.27

-0.02

RON 100

RM 5.00

VPR

RM 6.23

Diesel

EURO 5 B10

RM 3.06

-0.02

EURO 5 B7

RM 3.26

-0.02

Last updated 11 Dec, 2025

Related News

Auto News

Federal Highway Won’t Be Upgraded, Costs Deemed Too High

Despite worsening traffic conditions, the Federal Highway will not be upgraded, with the government citing high costs.

Auto News

MEX II Putrajaya-KLIA Extension Could Cost RM449 Million – Nanta

Works Minister Dato Sri Alexander Nanta Linggi said the MEX II extension project could cost as much as RM449 million.

03-12-2025
Auto News

Review Underway For 12 Loss-Making Highways - Nanta

Works Ministry will conduct a detailed review of the issue involving 12 highway concessions that recorded losses last year.

28-11-2025
Auto News

Govt Mulls Putting Streetlight Upkeep Under Concessionaires

Government may soon place highway streetlight upkeep under concessionaires for quicker, more organised repairs.

Auto News

RM1.7b NPE2 Extension To Ease KL Congestion By 2029 - Nanta

The NPE2 will connect Pantai Dalam to Jalan Istana, cutting travel time by up to 25 minutes and improving traffic flow across KL.

12-11-2025
Auto News

RM3b Juru–Sungai Dua Link Cuts Travel Time To Just 20 Minutes

RM3 billion traffic dispersal project aims to slash travel time between Juru and Sungai Dua from an hour to just 20 minutes.

Auto News

New Audit Move To Keep Highway Concessionaires In Check

Works Ministry will introduce independent audits for highway concessionaires in early 2026.

04-11-2025
Auto News

East-West Rail Link Across Titiwangsa Could Take 10-20 Years - Nanta

The east-west rail project crossing the Titiwangsa Range could take 10 to 20 years to complete.

16-09-2025

Latest News

Auto News

MAA: Nov 2025 Vehicle Sales Dip 4.6% from Oct, BEV Rush Keeps Market Strong

MAA reported solid vehicle sales in Nov 2025, with 72,509 units sold, slightly lower than Oct’s 75,992 units.

19-12-2025
Auto News

Perodua QV-E Sales Outlets Now Expanded to 34 Locations

Perodua has expanded the number of sales outlets for its QV-E EV to 34 locations from the original 9 outlets.

19-12-2025
Auto News

E-Hailing Drivers Must Hit 2,000KM To Unlock BUDI95 Extra Quota

E-hailing drivers must now clock at least 2,000km a month to qualify for higher BUDI95 petrol quotas.

19-12-2025
Auto News

Honda Malaysia’s 25th Anniversary Campaign – November Winners Announced

Honda Malaysia has announced the November winners of its 25th anniversary “Because of You” campaign.

19-12-2025
Auto News

Cable Theft Paralyzes Rail Services, Prasarana Urges Action From Govt

Prasarana urges urgent nationwide measures to tackle rampant cable theft as RM20.6 million of lost has been reported.

19-12-2025
Auto News

Govt Announces 50% Christmas Toll Discount On Dec 23-24

Private car users will enjoy a 50% toll discount nationwide on Dec 23, 24 as the government rolls out festive travel relief for Christmas.

19-12-2025
Auto News

No Toll Hikes in 2026 As Govt Commits To Absorb Costs

No toll hikes in 2026 as the government steps in and commits to absorb costs for which.

Auto News

O&J Highlights J7 PHEV Capabilities Through Customer Drive

O&J's nationwide drive brings customers together showcasing the J7 PHEV's efficiency in everyday conditions.

Show More

trending_flat
About Us

CarzAutoMedia: Stay connected to the latest car news! Get instant updates on new releases, industry trends, and automotive innovations. Your go-to source for 24/7 coverage of everything automotive.

© 2025 CariCarz.com. All Rights Reserved.