Federal Road FT3210 Set to Complete in Mid-2026, Serving 52K Users
The Federal Road FT3210 upgrade project, which runs from Jalan Dato Alias to the Batu 9 intersection in Hulu Langat, is projected to be finished in mid-2026 and will serve 52,000 daily road users at the cost of RM123.66 million.
According to Works Minister Datuk Seri Alexander Nanta Linggi, the project, which was originally scheduled for completion in 2025, has been postponed due to land acquisition and utility relocation issues.
"The project aims to alleviate congestion and improve user comfort and safety, as the area grows and the current road from Hulu Langat to Kuala Lumpur can no longer handle the increasing traffic, particularly during peak hours," Nanta informed the press during the site visit.
The project, which began on August 6, 2021, entails upgrading the road from the Taman Suntex junction for one kilometre and another kilometre from the Batu 9 intersection to the Jalan Dato Alias intersection.
The current single two-lane road will be converted into a four-lane dual carriageway. A two-lane one-way flyover from Hulu Langat to Cheras will also be built, along with the replacement of the Sungai Sering Bridge.
During his visit, Nanta also examined locations along FT3210 that are frequently hit by flash floods. As a preventive measure, the minister has directed the Hulu Langat district Public Works Department (JKR) and local authorities to work with relevant agencies to solve soil erosion and clean sewer outlets at these places.
Nanta also stated that the Hulu Langat JKR has applied for a road maintenance estimate for 2024, with the goal of upgrading the drainage system at an anticipated cost of RM2 million. As of May, the Works Ministry had authorised RM18.36 million under the APJ for the Hulu Langat JKR to execute road repair works.
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VPS6523
SELANGOR
BSH8490
JOHOR
JYG8730
PULAU PINANG
PRU1713
PERAK
APB2869
PAHANG
CFD5071
KEDAH
KGC3265
NEGERI SEMBILAN
NEH1484
KOTA KINABALU
SJM6467
KUCHING
QAB1830M
Last updated 21 Sep, 2025
Fuel Price
Petrol
RON 95
RM 2.05
RON 97
RM 3.21
+0.03
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.93
+0.03
EURO 5 B7
RM 3.13
+0.03
Last updated 18 Sep, 2025
Related News
Report: Over RM1.9 billion Spent To Maintain Pen. Malaysia Roads In 2024
Works Minister revealed over RM1.9 billion was spent to maintain roads in 11 states across Peninsular Malaysia in 2024.
26-02-2025
East-West Rail Link Across Titiwangsa Could Take 10-20 Years - Nanta
The east-west rail project crossing the Titiwangsa Range could take 10 to 20 years to complete.
16-09-2025
Nanta: MYJalan Will Become National Road Database
MYJalan app set to evolve from complaint channel to key tool in managing Malaysia’s road network.
29-08-2025
NPE Extension Deal Inked, RM1.4b+ Project Starts Q4 2025
NPE extension project costing over RM1.4b promises to cut travel time by up to 25 minutes and integrate with KL’s Traffic Master Plan 2040.
28-08-2025
JKR Set To Use Solar Lights In Over 1,000 Accident Hotspots
JKR steps up safety measures with nationwide solar lighting at over 1,000 accident hotspots.
11-08-2025
RM20 Million Allocated to Upgrade Federal Highway Motorcycle Lanes – KKR
A total of RM20 million will be allocated to upgrade the motorcycle lanes on the Federal Highway, the Works Ministry says.
08-08-2025
RM25 Million Allocated to Light Up Dark Federal Roads – KKR
The Works Ministry has allocated RM25 million to light up dark federal roads to prevent future accidents.
07-08-2025
Nanta: 80% of Accidents Driver-Linked, Road Budget 70% Short
With 80% of accidents linked to drivers, the Works Ministry still grapples with limited funds to fix and rebuild roads.
04-08-2025
Latest News
Low SKPS Registrations As Drivers Struggle With Digital Process
Low awareness and digital hurdles are keeping many taxi and bus operators from signing up for the RON95 subsidy scheme.
22-09-2025
ECRL Work Halted - Petronas Gas Pipeline Leak, Safety Zone Declared
Petronas Gas pipeline leak at the ECRL project has halted works, emergency crews racing to purge butane gas.
22-09-2025
RON95 Subsidy: App, Counters and Terminals Payment Options; SKPS Up Take Low
RON95 subsidy eligibility status, access and verification done via apps, counters and terminals; SKPS registrations remain low.
22-09-2025
PMX: RM1.99 RON95 from 30 Sept, MyKad-Based Access; Non-Citizens RM2.60
RON95 drops to RM1.99 for Malaysians with MyKad-based verification from 30 Sept, RM2.60 for non-citizens, benefiting 16 million people.
22-09-2025
JPJ: 2.3 Million Malaysians Have Expired Driving Licences
JPJ claims there are over 2.3 million Malaysians with driving licences that are expired beyond three-year renewal window.
21-09-2025
Petrol Cards And Civil Servant Perks On Offer By Jetour Malaysia This Month
Up to RM1 million worth of free petrol cards plus special perks for civil servants on offer from Jetour Malaysia this month.
20-09-2025
TQ Wuling Bingo EV CKD Production Set to Begin in Dec 2025
The new SGMW-Tan Chong joint venture EV plant will start its local assembly efforts this Dec with the TQ Wuling Bingo.
19-09-2025
MyKad Checks Urged Ahead of Fuel Price Drop
Home minister urges Malaysians to fix faulty MyKad chips early to enjoy the upcoming targeted fuel subsidy.
19-09-2025
Show More
trending_flat