Govt Open To Reviving KL-SG HSR With Private Sector Involvement - PM Anwar
The government has decided that the Kuala Lumpur-Singapore High-Speed Rail (HSR) project can be resurrected with little government engagement and full private sector participation, according to Prime Minister Datuk Seri Anwar Ibrahim.
Anwar, who is also the finance minister, stated that the government's present position is to welcome private sector engagement due to budget constraints and the need to await potential proposals.
“We have to put the issues of poverty alleviation, flood mitigation, basic infrastructure, education and public health as our priority, at least for the next one or two years, so the mega projects have to be deferred because of the commitment to settling some outstanding issues.

“We are still waiting for some promising and positive contribution or participation by the private sector to proceed when necessary... there have been proposals and the task force is looking at it,” he said during a joint press conference with Singapore’s Prime Minister Lawrence Wong in conjunction with Wong’s two-day official visit to Malaysia which started yesterday.
Even though there have been preliminary plans for the HSR, Anwar added that no decision would be taken until all factors have been carefully considered. The project won't proceed unless the private sector is fully involved and requires little government funding.
Singapore's prime minister, Lawrence Wong, stated that the city-state is prepared to talk about the issue while awaiting another proposal from Malaysia in the event that the train project is to be revived.
“As far as the HSR is concerned, it’s unfortunate that we could not proceed with it originally. However, we are open to reviewing new proposals from Malaysia. From our perspective, greater connectivity between our two countries is always a plus,” Wong said.
Since the first agreement on the Kuala Lumpur-Singapore HSR project was reached in 2013, negotiations have been going on for 12 years, with postponements and cancellations in 2021. Signed in December 2016, the first bilateral agreement was expected to be completed in 2025 and go into effect in 2026.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VQL8065
SELANGOR
BSM4786
JOHOR
JYR4712
PULAU PINANG
PRY6463
PERAK
APF2524
PAHANG
CFF2996
KEDAH
KGE3525
NEGERI SEMBILAN
NEJ5183
KOTA KINABALU
SJQ2847
KUCHING
QAB2387N
Last updated 13 Feb, 2026
Fuel Price
Petrol
RON 95
RM 2.54
RON 97
RM 3.10
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.99
+0.03
EURO 5 B7
RM 3.19
+0.03
Last updated 12 Feb, 2026
Related News
Govt Still Weighing Options For KL–Singapore HSR Project - Loke
Malaysia is still reviewing options for the KL–Singapore HSR, with a final model yet to be determined.
08-10-2025
Govt Finalising Key Parameters For KL-SG HSR Project - MOT
MOT announced that the government is in the process of finalizing key parameters for the KL-SG HSR project.
18-02-2025
KL-SG HSR Project: MRCB Withdraws from MyHSR Corp
Berjaya led MyHSR consortium now better aligned with project target following MRCB’s exit.
19-12-2024
KL-SG HSR Project Will Cost 30% Less Than Projected RM110 Billion
The KL-SG HSR project will cost roughly RM70 billion, roughly 30% lesser than the initial projected RM110 Billion.
19-04-2024
HSR Project Receives 7 Concept Proposal, Govt Needs Two Months To Review
The Transport Ministry announced on parliament’s website that the HSR Project has received 7 Concept Proposals.
05-03-2024
Why Japanese Companies Not Interested On Malaysia's Bullet Train Project
Japanese companies are not keen on Malaysia’s HSR project due to worries about the Malaysian government's lack of funding.
26-01-2024
KL-Bangkok Line Possible - MyHSR Corp Head
According to MyHSR Corporation chairman Datuk Seri Fauzi, there is a chance that the bullet train will be extended to Malaysia's northern region.
08-01-2024
KL-Singapore High Speed Rail Project Is Back On
yHSR Corp, has called for concept proposals for the long-shelved HSR project.
13-07-2023
Latest News
Traffic Nightmare Hits Klang Valley, Economy Feels the Burn
Commuters face unprecedented jams as KL and Selangor grind to a halt this festive season.
13-02-2026
Proton Partners MSU For Automotive Design Workshop
More than 20 students aged 15 to 25 took part in an automotive styling workshop led by PROTON designers in Subang Jaya.
12-02-2026
Budi95: 14.6 Million Malaysians Save on RON95
14.6 million Malaysians enjoy RM1.99 RON95 petrol through the MyKad-based Budi95 subsidy system.
12-02-2026
Stellantis Now Exports CKD Peugeot 408 To Taiwan
Stellantis starts local production (CKD) of Peugeot 408 at its Gurun plant for export to Taiwan.
12-02-2026
PDRM Suggests Making Dashcams Compulsory for All Road Users
PDRM’s Traffic Investigation and Enforcement Department suggests making dashcams compulsory for all road users.
12-02-2026
CNY 2026: 50% Toll Discount on Second Penang Bridge
50% Toll Discount on Second Penang Bridge, Feb 14–15.
12-02-2026
Malaysia Tables RTS Link Bill 2026 to Enable Joint CIQ at JB–Singapore Stations
RTS Link Bill 2026 is set to enable joint customs, immigration, and security operations between Bukit Chagar Station and Woodlands North Station
12-02-2026
Updated Fuel Prices From 12 To 18 February
The Ministry of Finance (MoF) has announced the retail prices of all fuels in Malaysia, for the coming week of 12 to 18 February, 2026, the rates are as such.
11-02-2026
Show More
trending_flat