Govt Open To Reviving KL-SG HSR With Private Sector Involvement - PM Anwar
The government has decided that the Kuala Lumpur-Singapore High-Speed Rail (HSR) project can be resurrected with little government engagement and full private sector participation, according to Prime Minister Datuk Seri Anwar Ibrahim.
Anwar, who is also the finance minister, stated that the government's present position is to welcome private sector engagement due to budget constraints and the need to await potential proposals.
“We have to put the issues of poverty alleviation, flood mitigation, basic infrastructure, education and public health as our priority, at least for the next one or two years, so the mega projects have to be deferred because of the commitment to settling some outstanding issues.
“We are still waiting for some promising and positive contribution or participation by the private sector to proceed when necessary... there have been proposals and the task force is looking at it,” he said during a joint press conference with Singapore’s Prime Minister Lawrence Wong in conjunction with Wong’s two-day official visit to Malaysia which started yesterday.
Even though there have been preliminary plans for the HSR, Anwar added that no decision would be taken until all factors have been carefully considered. The project won't proceed unless the private sector is fully involved and requires little government funding.
Singapore's prime minister, Lawrence Wong, stated that the city-state is prepared to talk about the issue while awaiting another proposal from Malaysia in the event that the train project is to be revived.
“As far as the HSR is concerned, it’s unfortunate that we could not proceed with it originally. However, we are open to reviewing new proposals from Malaysia. From our perspective, greater connectivity between our two countries is always a plus,” Wong said.
Since the first agreement on the Kuala Lumpur-Singapore HSR project was reached in 2013, negotiations have been going on for 12 years, with postponements and cancellations in 2021. Signed in December 2016, the first bilateral agreement was expected to be completed in 2025 and go into effect in 2026.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VPM8257
SELANGOR
BSG8453
JOHOR
JYE6362
PULAU PINANG
PRT1721
PERAK
ANY8521
PAHANG
CFD1278
KEDAH
KGB6823
NEGERI SEMBILAN
NEG6617
KOTA KINABALU
SJL9999*
KUCHING
QAB8707L
Last updated 07 Aug, 2025
Fuel Price
Petrol
RON 95
RM 2.05
RON 97
RM 3.17
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.94
+0.03
EURO 5 B7
RM 3.14
+0.03
Last updated 07 Aug, 2025
Related News
Govt Finalising Key Parameters For KL-SG HSR Project - MOT
MOT announced that the government is in the process of finalizing key parameters for the KL-SG HSR project.
18-02-2025
KL-SG HSR Project: MRCB Withdraws from MyHSR Corp
Berjaya led MyHSR consortium now better aligned with project target following MRCB’s exit.
19-12-2024
KL-SG HSR Project Will Cost 30% Less Than Projected RM110 Billion
The KL-SG HSR project will cost roughly RM70 billion, roughly 30% lesser than the initial projected RM110 Billion.
19-04-2024
HSR Project Receives 7 Concept Proposal, Govt Needs Two Months To Review
The Transport Ministry announced on parliament’s website that the HSR Project has received 7 Concept Proposals.
05-03-2024
Why Japanese Companies Not Interested On Malaysia's Bullet Train Project
Japanese companies are not keen on Malaysia’s HSR project due to worries about the Malaysian government's lack of funding.
26-01-2024
KL-Bangkok Line Possible - MyHSR Corp Head
According to MyHSR Corporation chairman Datuk Seri Fauzi, there is a chance that the bullet train will be extended to Malaysia's northern region.
08-01-2024
KL-Singapore High Speed Rail Project Is Back On
yHSR Corp, has called for concept proposals for the long-shelved HSR project.
13-07-2023
Johor Ready To Collaborate On Potential KL-Singapore HSR Project Revival - State Exco
The state government of Johor has declared its willingness to work with the federal government to resurrect the Kuala Lumpur-Singapore High-Speed Rail (HSR) project.
14-12-2022
Latest News
Over 39,000 Road Issues Flagged On MyJalan App Since Launch
MyJalan app logs over 39,000 complaints, but most fall outside federal jurisdiction, says Deputy Works Minister.
07-08-2025
PLUS Eyes MLFF ANPR Toll Trials This Month - JustGo Digital App
PLUS will begin trials for automatic number plate recognition (ALPR) toll system with its JustGo Digital App, part of proposed MLFF system, across nine toll plazas this month.
07-08-2025
Kelana Jaya Line Signalling Works Delayed, Phase 2 Work Starts Sept 6
Kelana Jaya Line Phase 2 and 3 signalling works will now begin on Sept 6, with select stations opening later on affected dates.
07-08-2025
UMW Toyota Jul y2025 Sales Total At 8,877 Units
UMW Toyota sees its sales for July 2025 total at 8,877 units, YTD total now up to 53,163 units.
07-08-2025
RM25 Million Allocated to Light Up Dark Federal Roads – KKR
The Works Ministry has allocated RM25 million to light up dark federal roads to prevent future accidents.
07-08-2025
Ops Pengarah: 252 Fined, One With Road Tax Expired For 2 Years
JPJ’s Ops Pengarah nabs dozens driving without licence, including one with road tax expired for two years.
07-08-2025
Aerotrain Disruption A Minor Glitch, ETS3 Project On Track - Loke
KLIA’s Aerotrain glitch was a minor software bug, not a breakdown, while ETS3 to Johor Bahru is on track, says Transport Minister.
07-08-2025
Updated Fuel Prices From 07 To 13 August
The Ministry of Finance (MoF) has announced the retail prices of all fuels in Malaysia, for the coming week of 07 to 13 August, 2025, the rates are as such.
06-08-2025
Show More
trending_flat