Penang LRT Project Progressing Steadily - MRT Corp

Anis

Share via

Muhammad-Kifli-Ma-Hassan.-(61).png
Construction of the Mutiara Line Penang LRT project is on track, according to the Mass Rapid Transit Corporation on Sunday.


MRT Corp, as the project’s owner stated that it has been actively advancing the Mutiara line Penang LRT project, with obtaining approval for advance works on April 15 being one of its main initiatives.

This comes after MCA vice-president Tan Teik Cheng voiced concerns about the project's seeming lack of physical progress despite its January groundbreaking, as reported by MalaysiaKini.
634250378d788477a2115c11f51aa283-(1).jpg


With 86 plots of land secured to date and gazetted ahead of the intended date of October 2025, the firm also emphasized that it has achieved great progress in terms of land purchases, assuring the public that the LRT Mutiara Line project is still on track and on schedule.

In addition, MRT Corp said that SRS Consortium Sdn Bhd, the main contractor for the first package of the LRT line, is fulfilling post-award conditions before issuing an official notice-to-proceed, emphasizing that  utility relocation is a critical aspect of pre-construction work that must be completed before any station or viaduct-related construction can begin.

17977720-projek-lrt-mutiara-bernama-210425.jpeg


The Mutiara Line, with an estimated cost of RM10 billion to RM13 billion, is considered the largest inland infrastructure project on mainland Penang. The 29.5 km elevated LRT line will have 21 stations, starting from the Silicon Island off Batu Maung. It will then pass through Weld Quay, its main interchange, the Penang Bridge, and end at the Penang Sentral transport hub in Butterworth.

Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

JPJ Running Numbers

KUALA LUMPUR

VQG7003

SELANGOR

BSL4502

JOHOR

JYP2937

PULAU PINANG

PRX3536

PERAK

APD8543

PAHANG

CFE6650

KEDAH

KGD6850

NEGERI SEMBILAN

NEJ2039

KOTA KINABALU

SJP6344

KUCHING

QAB9615M

Last updated 03 Jan, 2026

Fuel Price

Petrol

RON 95

RM 2.56

RON 97

RM 3.16

RON 100

RM 5.00

VPR

RM 6.23

Diesel

EURO 5 B10

RM 2.94

EURO 5 B7

RM 3.14

Last updated 01 Jan, 2026

Related News

Auto News
Penang Mutiara LRT Construction Kicks Off Jan 2026

Penang Mutiara LRT Construction Kicks Off Jan 2026

Penang Mutiara Line LRT starts in Jan 2026, with traffic management measures ready to minimise disruptions.

19-11-2025
Auto News
Penang Sentral Set to Become Mainland’s Integrated Transport Hub

Penang Sentral Set to Become Mainland’s Integrated Transport Hub

The Butterworth KTM station, Mutiara Line LRT, and airport expansions will turn Penang Sentral into key transport and logistics hub.

Auto News
Penang Defends Mega Projects As Key To Tackling Traffic Woes

Penang Defends Mega Projects As Key To Tackling Traffic Woes

Penang’s transport councillor says flyovers, underpasses and the LRT are essential to ease congestion.

04-09-2025
Auto News
MRT Corp Justifies RM16.8b Penang LRT Budget

MRT Corp Justifies RM16.8b Penang LRT Budget

MRT Corp says the RM16.8 billion ceiling for Penang LRT reflects market realities, but MCA wants clearer answers on taxpayers’ money.

21-08-2025
Auto News
Langkawi LRT ‘Unrealistic’, Focus Stays on Penang LRT and ECRL - Loke

Langkawi LRT ‘Unrealistic’, Focus Stays on Penang LRT and ECRL - Loke

The government is pushing ahead with the Penang LRT and ECRL, but dismissed talk of a Langkawi LRT as unrealistic.

19-08-2025
Auto News
Penang LRT Stays Within RM16 Billion Budget - MRT Corp

Penang LRT Stays Within RM16 Billion Budget - MRT Corp

Penang LRT project capped at RM16 billion, with MRT Corp aiming to deliver a cost-efficient system despite rising expenses.

30-07-2025
Auto News
Penang Still Waiting For Green Light From MOT For LRT project

Penang Still Waiting For Green Light From MOT For LRT project

Penang is set to begin Mutiara LRT construction but awaits final approval from MRT Corp and MOT.

02-07-2025
Auto News
Mutiara LRT Issues Resolved , Earthworks Commencing Soon

Mutiara LRT Issues Resolved , Earthworks Commencing Soon

Transport Minister announced that all outstanding issues regarding the Mutiara LRT project have been resolved.

11-06-2025

Latest News

Auto News
Proton Shifted 157,976 Units In 2025, Charts 3.3% Growth & New Export Record

Proton Shifted 157,976 Units In 2025, Charts 3.3% Growth & New Export Record

Proton closes 2025 on a high by shifting 157,976 units, logging a 3.3% growth plus a new export record.

02-01-2026
Auto News
KSM Lowers Kia Spare Parts Price By 15%, Brings New Incentives Too

KSM Lowers Kia Spare Parts Price By 15%, Brings New Incentives Too

New prices aside, Kia Sales Malaysia (KSM) also lower Kia spare parts prices by 15%, announces a slew of new incentives too.

02-01-2026
Auto News
Prasarana Moved 1.54 Million People on New Year’s Eve

Prasarana Moved 1.54 Million People on New Year’s Eve

Prasarana moved 1.54 million people on New Year’s Eve, marking its highest single-day ridership.

Auto News
Updated Fuel Prices From 1 To 7 January

Updated Fuel Prices From 1 To 7 January

The Ministry of Finance (MoF) has announced the retail prices of all fuels in Malaysia, for the coming week of 1 to 7 January, 2026, the rates are as such.

31-12-2025
Auto News
Selangor Police Collect RM19.5 Million During Summons Discount Period

Selangor Police Collect RM19.5 Million During Summons Discount Period

More than 258,000 traffic summonses were settled in Selangor during the two-month 70% discount programme, collecting RM19.5 million.

31-12-2025
Auto News
Traffic Summons Discount Ends, Tougher Penalties Ahead – Should Authorities Extend?

Traffic Summons Discount Ends, Tougher Penalties Ahead – Should Authorities Extend?

The traffic summons discount is over, millions of fines remain unpaid, and stricter penalties kick in next year

31-12-2025
Auto News
LRT3: 33 Problems Identified, Solutions Ready, Tests Ongoing

LRT3: 33 Problems Identified, Solutions Ready, Tests Ongoing

All 33 technical problems identified on the Shah Alam Line have proposed fixes, but full testing is still underway.

Auto News
KLIA T1 Moves Customs Checks — Here’s What You Need To Know

KLIA T1 Moves Customs Checks — Here’s What You Need To Know

Customs checks at KLIA T1 will move to the departure gates from Jan 1, promising smoother departures.

Show More

trending_flat
Carz Automedia Malaysia Logo
About Us

CarzAutoMedia: Stay connected to the latest car news! Get instant updates on new releases, industry trends, and automotive innovations. Your go-to source for 24/7 coverage of everything automotive.

© 2026 CariCarz.com. All Rights Reserved.