Penang LRT Project Progressing Steadily - MRT Corp
-full_normal.jpg)
Construction of the Mutiara Line Penang LRT project is on track, according to the Mass Rapid Transit Corporation on Sunday.
MRT Corp, as the project’s owner stated that it has been actively advancing the Mutiara line Penang LRT project, with obtaining approval for advance works on April 15 being one of its main initiatives.
This comes after MCA vice-president Tan Teik Cheng voiced concerns about the project's seeming lack of physical progress despite its January groundbreaking, as reported by MalaysiaKini.
-full_normal.jpg)
With 86 plots of land secured to date and gazetted ahead of the intended date of October 2025, the firm also emphasized that it has achieved great progress in terms of land purchases, assuring the public that the LRT Mutiara Line project is still on track and on schedule.
In addition, MRT Corp said that SRS Consortium Sdn Bhd, the main contractor for the first package of the LRT line, is fulfilling post-award conditions before issuing an official notice-to-proceed, emphasizing that utility relocation is a critical aspect of pre-construction work that must be completed before any station or viaduct-related construction can begin.

The Mutiara Line, with an estimated cost of RM10 billion to RM13 billion, is considered the largest inland infrastructure project on mainland Penang. The 29.5 km elevated LRT line will have 21 stations, starting from the Silicon Island off Batu Maung.
It will then pass through Weld Quay, its main interchange, the Penang Bridge, and end at the Penang Sentral transport hub in Butterworth.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VQH6824
SELANGOR
BSL6927
JOHOR
JYP7855
PULAU PINANG
PRX6563
PERAK
APE2651
PAHANG
CFE7917
KEDAH
KGD8407
NEGERI SEMBILAN
NEJ2906
KOTA KINABALU
SJP7458
KUCHING
QAB371N
Last updated 17 Jan, 2026
Fuel Price
Petrol
RON 95
RM 2.52
-0.02
RON 97
RM 3.08
-0.03
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.84
-0.05
EURO 5 B7
RM 3.04
-0.05
Last updated 15 Jan, 2026
Related News
Penang Mutiara LRT Construction Kicks Off Jan 2026
Penang Mutiara Line LRT starts in Jan 2026, with traffic management measures ready to minimise disruptions.
19-11-2025
Penang Sentral Set to Become Mainland’s Integrated Transport Hub
The Butterworth KTM station, Mutiara Line LRT, and airport expansions will turn Penang Sentral into key transport and logistics hub.
11-11-2025
Penang Defends Mega Projects As Key To Tackling Traffic Woes
Penang’s transport councillor says flyovers, underpasses and the LRT are essential to ease congestion.
04-09-2025
MRT Corp Justifies RM16.8b Penang LRT Budget
MRT Corp says the RM16.8 billion ceiling for Penang LRT reflects market realities, but MCA wants clearer answers on taxpayers’ money.
21-08-2025
Langkawi LRT ‘Unrealistic’, Focus Stays on Penang LRT and ECRL - Loke
The government is pushing ahead with the Penang LRT and ECRL, but dismissed talk of a Langkawi LRT as unrealistic.
19-08-2025
Penang LRT Stays Within RM16 Billion Budget - MRT Corp
Penang LRT project capped at RM16 billion, with MRT Corp aiming to deliver a cost-efficient system despite rising expenses.
30-07-2025
Penang Still Waiting For Green Light From MOT For LRT project
Penang is set to begin Mutiara LRT construction but awaits final approval from MRT Corp and MOT.
02-07-2025
Mutiara LRT Issues Resolved , Earthworks Commencing Soon
Transport Minister announced that all outstanding issues regarding the Mutiara LRT project have been resolved.
11-06-2025
Latest News
Proton X50 Makes Overseas Debut in Brunei - From RM86,500
Proton X50 makes its overseas debut in Brunei, marking a milestone in Proton’s export expansion.
16-01-2026
Johor Bahru Becomes First City To Launch Driverless Tourist Buses
Johor Bahru is set to become Malaysia’s first city to operate autonomous tourist buses, alongside AI CCTV and drones.
16-01-2026
Johor Bahru-Singapore RTS Nears Completion as Testing Begins
The JB-SG RTS Link is on track for completion by Dec, with train testing underway and passenger services expected to begin in Jan 2027.
15-01-2026
Kedah Steps Up Border Patrols Against Fuel Abuse
Kedah authorities are monitoring petrol stations along state borders to stop foreign vehicles from buying subsidised RON95.
15-01-2026
BMW Group Malaysia Reports Strong 2025 Sales And EV Growth
BMW Group Malaysia delivered over 10,800 vehicles in 2025, including more than 2,700 fully-electric models, continuing growth in premium and EV segments.
15-01-2026
OMODA & JAECOO Malaysia CNY 2026 Ang Pow Deals
OMODA & JAECOO Malaysia CNY 2026 Ang Pow Deals offer up to RM18,888 in savings, paired with free service across all models.
15-01-2026
Updated Fuel Prices From 15 To 21 January
The Ministry of Finance (MoF) has announced the retail prices of all fuels in Malaysia, for the coming week of 15 to 21 January, 2026, the rates are as such.
14-01-2026
Malaysian Taxis Entering Singapore Must Install ERP 2.0, Tamper-Proof Plates
Licensed Malaysian taxis entering Singapore will be required to install the ERP 2.0 on-board unit to regulate cross-border taxi services.
14-01-2026
Show More
trending_flat