Penang LRT Project Progressing Steadily - MRT Corp
-full_normal.jpg)
Construction of the Mutiara Line Penang LRT project is on track, according to the Mass Rapid Transit Corporation on Sunday.
MRT Corp, as the project’s owner stated that it has been actively advancing the Mutiara line Penang LRT project, with obtaining approval for advance works on April 15 being one of its main initiatives.
This comes after MCA vice-president Tan Teik Cheng voiced concerns about the project's seeming lack of physical progress despite its January groundbreaking, as reported by MalaysiaKini.
-full_normal.jpg)
With 86 plots of land secured to date and gazetted ahead of the intended date of October 2025, the firm also emphasized that it has achieved great progress in terms of land purchases, assuring the public that the LRT Mutiara Line project is still on track and on schedule.
In addition, MRT Corp said that SRS Consortium Sdn Bhd, the main contractor for the first package of the LRT line, is fulfilling post-award conditions before issuing an official notice-to-proceed, emphasizing that utility relocation is a critical aspect of pre-construction work that must be completed before any station or viaduct-related construction can begin.

The Mutiara Line, with an estimated cost of RM10 billion to RM13 billion, is considered the largest inland infrastructure project on mainland Penang. The 29.5 km elevated LRT line will have 21 stations, starting from the Silicon Island off Batu Maung.
It will then pass through Weld Quay, its main interchange, the Penang Bridge, and end at the Penang Sentral transport hub in Butterworth.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VRC6572
SELANGOR
BSQ8458
JOHOR
JYY7513
PULAU PINANG
PSD1327
PERAK
APJ2534
PAHANG
CFG7913
KEDAH
KGG5227
NEGERI SEMBILAN
NEK6639
KOTA KINABALU
SJS4338
KUCHING
QAB125P
Last updated 20 Jun, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
Public Review Opens for Revised Penang Mutiara LRT with Cross-Sea Link at Core
MRT Corp opens a three-month public review for the Penang Mutiara LRT, featuring a proposed six-kilometre cross-sea link to Penang Sentral.
23-02-2026
Penang Mutiara LRT Construction Kicks Off Jan 2026
Penang Mutiara Line LRT starts in Jan 2026, with traffic management measures ready to minimise disruptions.
19-11-2025
Penang Sentral Set to Become Mainland’s Integrated Transport Hub
The Butterworth KTM station, Mutiara Line LRT, and airport expansions will turn Penang Sentral into key transport and logistics hub.
11-11-2025
Penang Defends Mega Projects As Key To Tackling Traffic Woes
Penang’s transport councillor says flyovers, underpasses and the LRT are essential to ease congestion.
04-09-2025
MRT Corp Justifies RM16.8b Penang LRT Budget
MRT Corp says the RM16.8 billion ceiling for Penang LRT reflects market realities, but MCA wants clearer answers on taxpayers’ money.
21-08-2025
Langkawi LRT ‘Unrealistic’, Focus Stays on Penang LRT and ECRL - Loke
The government is pushing ahead with the Penang LRT and ECRL, but dismissed talk of a Langkawi LRT as unrealistic.
19-08-2025
Penang LRT Stays Within RM16 Billion Budget - MRT Corp
Penang LRT project capped at RM16 billion, with MRT Corp aiming to deliver a cost-efficient system despite rising expenses.
30-07-2025
Penang Still Waiting For Green Light From MOT For LRT project
Penang is set to begin Mutiara LRT construction but awaits final approval from MRT Corp and MOT.
02-07-2025
Latest News
42 Clauses Are Changing: M'sia Is Facing Its Biggest Road Law Overhaul Since 2020, And Yes, It Affects Your Saman
Malaysia is introducing 42 new clauses to the Road Transport Act in its biggest traffic law overhaul since 2020. Here is how it affects your fines and roadblocks.
19-06-2026
Good News For 5 Million Perodua Owners! Don't Go To Outside Workshops As Service Prices Just Dropped
Thinking of visiting an outside mechanic? Perodua is slashing overall service maintenance parts and labor costs by 10% nationwide starting 19 June.
18-06-2026
It’s Happening! After Years Of Delays, The LRT3 Is Finally Ready To Start Operations
The long-awaited LRT3 Shah Alam Line is officially set to begin operations by the end of this month, as confirmed by Transport Minister Anthony Loke.
18-06-2026
No More Just 'Screwing Parts Together', Malaysia Wants Local Talents To Design The Next Big ASEAN Car Tech
At KLIMS 2026, Deputy Transport Minister Datuk Hasbi Habibollah urged Malaysia's automotive industry to evolve from car assemblers into technology creators.
18-06-2026
It Costs Up To RM300K To Protect One School Zone, And The Government Is Inviting Private Companies To Step Up
Why does a single Safe School Zone cost up to RM300K to build? Transport Minister Anthony Loke breaks down the new physical 30km/h traffic-calming blueprint and why private companies are being asked to step up.
17-06-2026
Prime, Premium, Or Premium Plus? 4 Major Differences Between The 3 Proton e.Mas 7 Tiers
Prime, Premium, or Premium Plus? We break down the 4 massive differences in battery range, price, and luxury features across the new Proton eMas 7 EV tiers.
12-06-2026
15 Drug Records But Still Driving?! Malaysians Are Furious Over The Viral Penang Highway Triton Rampage
Shocking details emerge on the viral Mitsubishi Triton highway crash in Penang. The drugged driver has 17 prior convictions, leaving 18 cars damaged.
10-06-2026
Don't Buy A Car Full Price! Perodua Just Quietly Slashed Prices On 5 Models & The Discounts Vanish After June 30
Perodua just quietly slashed prices on 5 popular models for June 2026! Check out the exact cash rebates for the Myvi, Ativa, Aruz, Bezza, and Axia here.
09-06-2026
Show More
trending_flat