Penang LRT Project Progressing Steadily - MRT Corp
Construction of the Mutiara Line Penang LRT project is on track, according to the Mass Rapid Transit Corporation on Sunday.
MRT Corp, as the project’s owner stated that it has been actively advancing the Mutiara line Penang LRT project, with obtaining approval for advance works on April 15 being one of its main initiatives.
This comes after MCA vice-president Tan Teik Cheng voiced concerns about the project's seeming lack of physical progress despite its January groundbreaking, as reported by MalaysiaKini.
With 86 plots of land secured to date and gazetted ahead of the intended date of October 2025, the firm also emphasized that it has achieved great progress in terms of land purchases, assuring the public that the LRT Mutiara Line project is still on track and on schedule.
In addition, MRT Corp said that SRS Consortium Sdn Bhd, the main contractor for the first package of the LRT line, is fulfilling post-award conditions before issuing an official notice-to-proceed, emphasizing that utility relocation is a critical aspect of pre-construction work that must be completed before any station or viaduct-related construction can begin.
The Mutiara Line, with an estimated cost of RM10 billion to RM13 billion, is considered the largest inland infrastructure project on mainland Penang. The 29.5 km elevated LRT line will have 21 stations, starting from the Silicon Island off Batu Maung.
It will then pass through Weld Quay, its main interchange, the Penang Bridge, and end at the Penang Sentral transport hub in Butterworth.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VPJ4305
SELANGOR
BSF9814
JOHOR
JYC6421
PULAU PINANG
PRS1815
PERAK
ANX4067
PAHANG
CFC4564
KEDAH
KGB2651
NEGERI SEMBILAN
NEG4017
KOTA KINABALU
SJL5744
KUCHING
QAB6348L
Last updated 05 Jul, 2025
Fuel Price
Petrol
RON 95
RM 2.05
RON 97
RM 3.18
-0.03
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.85
-0.03
EURO 5 B7
RM 3.05
-0.03
Last updated 03 Jul, 2025
Related News
Penang Still Waiting For Green Light From MOT For LRT project
Penang is set to begin Mutiara LRT construction but awaits final approval from MRT Corp and MOT.
02-07-2025
Mutiara LRT Issues Resolved , Earthworks Commencing Soon
Transport Minister announced that all outstanding issues regarding the Mutiara LRT project have been resolved.
11-06-2025
Mutiara Line LRT: Penang’s RM8.3 Billion Connectivity Investment
Penang’s RM8.31 billion Mutiara Line LRT project begins with the first phase contract signing.
14-01-2025
Penang Mutiara LRT Project Poised To Commence In 2025
Loke announces phase 1 of Penang Mutiara LRT project will commence early next year.
11-11-2024
Penang Confirms LRT Work Construction To Begin In December
December will see the start of work on Penang's LRT project, with Lebuh Macallum serving as the location of the first station.
09-10-2024
Maslan: 15 KM Juru-Sungai Dua Elevated Highway To Cost RM1.8B
The Juru-Sungai Dua Elevated Highway is set to cost RM1.8B, project will be undertaken by PLUS on a Public-Private Partnership basis.
06-06-2024
Penang Mutiara Line LRT Won’t Be Like Kelana Jaya LRT
Penang’s Mutiara Line LRT would run only 2-car train when it begins and would scale up if required.
31-05-2024
Analysts: Penang Mutiara LRT Important To Improve Urban Mobility And Tourism
Transport analysts say Penang Mutiara LRT would help improve mobility and tourism.
11-04-2024
Latest News
Road Detours & Diversions In KL July 4-7 & 8-11 For ASEAN Meeting
PDRM issues list of road detours and diversions for selected KL roads for ASEAN meeting set for July 4-7 and July 8-11.
05-07-2025
KLIA Aerotrain Stalls After Downpour Causes Drainage Pump Malfunction
Just days after its grand relaunch, KLIA Aerotrain service was briefly halted when a faulty pump let rainwater flood its tunnel.
04-07-2025
Kelana Jaya LRT Delayed After Passenger Falls Onto Track
A passenger fell onto the track near Subang Alam Station around 8:00AM, causing peak-hour delays on the Kelana Jaya LRT Line.
04-07-2025
Badminton Legend Burns RM285K On Dream SUV
Former world No. 1 shuttler Tan Boon Heong revealed he lost RM285,000 on his RM530,000 Range Rover Sport.
04-07-2025
JPJ Services Offline From 10 PM Friday to 6 AM Saturday
The JPJ online services will be offline from Friday 10 PM to Saturday 6 AM for scheduled system maintenance.
04-07-2025
Experts Push For Corporate Liability In Wake Of Transport Safety Failures
With most transport firms failing safety audits, experts urge a corporate liability law to hold companies accountable for crashes.
04-07-2025
Nightly Closure of Jalan Ismail Sultan for RTS Works Until July 16
Jalan Ismail Sultan (Stulang-bound) will be closed nightly from 10PM to 5AM for RTS Link construction until July 16.
04-07-2025
Tech-Driven RON95 Subsidy Rollout in the Works
The government is developing a new tech-based RON95 fuel subsidy model to reduce misuse and ensure fairness.
03-07-2025
Show More
trending_flat