Penang LRT Project Progressing Steadily - MRT Corp
Anis
21-4-2025
Construction of the Mutiara Line Penang LRT project is on track, according to the Mass Rapid Transit Corporation on Sunday.
MRT Corp, as the project’s owner stated that it has been actively advancing the Mutiara line Penang LRT project, with obtaining approval for advance works on April 15 being one of its main initiatives.
This comes after MCA vice-president Tan Teik Cheng voiced concerns about the project's seeming lack of physical progress despite its January groundbreaking, as reported by MalaysiaKini.
With 86 plots of land secured to date and gazetted ahead of the intended date of October 2025, the firm also emphasized that it has achieved great progress in terms of land purchases, assuring the public that the LRT Mutiara Line project is still on track and on schedule.
In addition, MRT Corp said that SRS Consortium Sdn Bhd, the main contractor for the first package of the LRT line, is fulfilling post-award conditions before issuing an official notice-to-proceed, emphasizing that utility relocation is a critical aspect of pre-construction work that must be completed before any station or viaduct-related construction can begin.
The Mutiara Line, with an estimated cost of RM10 billion to RM13 billion, is considered the largest inland infrastructure project on mainland Penang. The 29.5 km elevated LRT line will have 21 stations, starting from the Silicon Island off Batu Maung.
It will then pass through Weld Quay, its main interchange, the Penang Bridge, and end at the Penang Sentral transport hub in Butterworth.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VPD5920
SELANGOR
BSE8143
JOHOR
JXX6702
PULAU PINANG
PRQ7269
PERAK
ANV8184
PAHANG
CFB7859
KEDAH
KGA6086
NEGERI SEMBILAN
NEF9162
KOTA KINABALU
SJK9847
KUCHING
QAB3745L
Last updated 21 May, 2025
Fuel Price
Petrol
RON 95
RM 2.05
RON 97
RM 3.07
-0.03
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.77
-0.03
EURO 5 B7
RM 2.97
-0.03
Last updated 15 May, 2025
Related News
Mutiara Line LRT: Penang’s RM8.3 Billion Connectivity Investment
Penang’s RM8.31 billion Mutiara Line LRT project begins with the first phase contract signing.
14-01-2025
Penang Mutiara LRT Project Poised To Commence In 2025
Loke announces phase 1 of Penang Mutiara LRT project will commence early next year.
11-11-2024
Penang Confirms LRT Work Construction To Begin In December
December will see the start of work on Penang's LRT project, with Lebuh Macallum serving as the location of the first station.
09-10-2024
Maslan: 15 KM Juru-Sungai Dua Elevated Highway To Cost RM1.8B
The Juru-Sungai Dua Elevated Highway is set to cost RM1.8B, project will be undertaken by PLUS on a Public-Private Partnership basis.
06-06-2024
Penang Mutiara Line LRT Won’t Be Like Kelana Jaya LRT
Penang’s Mutiara Line LRT would run only 2-car train when it begins and would scale up if required.
31-05-2024
Analysts: Penang Mutiara LRT Important To Improve Urban Mobility And Tourism
Transport analysts say Penang Mutiara LRT would help improve mobility and tourism.
11-04-2024
Penang Mutiara Line LRT Project Set to Complete in 2030
The cabinet has approved the construction of the Penang Mutiara Line LRT Project, with completion expected by 2023.
30-03-2024
Penang LRT: Nine “Park and Ride” Facilities With 1,100 Parking Space
Penang LRT line to offer 1,100 parking spaces at nine "Park and Ride” Facilities.
27-11-2024
Latest News
Omoda | Jaecoo Malaysia Sets Up New Shah Alam Warehouse
Newly rebranded Omoda | Jaecoo Malaysia estasblishes new warehouse in Shah Alam to boost after-sales efforts.
20-05-2025
RON95 Subsidy Now Under MOF’s Purview - Rafizi
The implementation of targeted RON95 fuel subsidies is now under MOF, according to Rafizi Ramli.
20-05-2025
KL-Karak Highway Expansion Project Set to Begin in Q2 2025
AFA Prime Berhad announces that the KL-Karak highway expansion project is set to commence in Q2 2025.
20-05-2025
KL Monorail Lift Upgrades At five stations Completed, Other six Due By May
Lifts at five monorail stations are operational; the remaining lifts and one escalator at six stations will be operational by May.
20-05-2025
One Death Every 36 Hours In Malaysia From Lorry Crashes - MIROS
MIROS study reveals that lorry and trailer accidents have caused at least 1,457 deaths in the past six years, averaging one death every 36 hours.
20-05-2025
MAA: April 2025 Auto Sales Drops 16.8%
MAA reports that vehicle sales fell sharply from March by 16.8% to 60,527 units in April 2025, cites post-Raya slowdown.
19-05-2025
Prasarana Aims For 40% Public Transit Ridership By 2030
Prasarana plans to boost public transport usage to 40% by 2030 through ongoing service and facility improvements.
19-05-2025
ASEAN Summit 2025: Road Closures & Diversions Announced
Road closures and diversions in Klang Valley announced ahead of the upcoming 46th ASEAN Summit.
19-05-2025
Show More
trending_flat