Penang LRT Project Progressing Steadily - MRT Corp
-full_normal.jpg)
Construction of the Mutiara Line Penang LRT project is on track, according to the Mass Rapid Transit Corporation on Sunday.
MRT Corp, as the project’s owner stated that it has been actively advancing the Mutiara line Penang LRT project, with obtaining approval for advance works on April 15 being one of its main initiatives.
This comes after MCA vice-president Tan Teik Cheng voiced concerns about the project's seeming lack of physical progress despite its January groundbreaking, as reported by MalaysiaKini.
-full_normal.jpg)
With 86 plots of land secured to date and gazetted ahead of the intended date of October 2025, the firm also emphasized that it has achieved great progress in terms of land purchases, assuring the public that the LRT Mutiara Line project is still on track and on schedule.
In addition, MRT Corp said that SRS Consortium Sdn Bhd, the main contractor for the first package of the LRT line, is fulfilling post-award conditions before issuing an official notice-to-proceed, emphasizing that utility relocation is a critical aspect of pre-construction work that must be completed before any station or viaduct-related construction can begin.

The Mutiara Line, with an estimated cost of RM10 billion to RM13 billion, is considered the largest inland infrastructure project on mainland Penang. The 29.5 km elevated LRT line will have 21 stations, starting from the Silicon Island off Batu Maung.
It will then pass through Weld Quay, its main interchange, the Penang Bridge, and end at the Penang Sentral transport hub in Butterworth.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VQG7003
SELANGOR
BSL4502
JOHOR
JYP2937
PULAU PINANG
PRX3536
PERAK
APD8543
PAHANG
CFE6650
KEDAH
KGD6850
NEGERI SEMBILAN
NEJ2039
KOTA KINABALU
SJP6344
KUCHING
QAB9615M
Last updated 03 Jan, 2026
Fuel Price
Petrol
RON 95
RM 2.56
RON 97
RM 3.16
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.94
EURO 5 B7
RM 3.14
Last updated 01 Jan, 2026
Related News
Penang Mutiara LRT Construction Kicks Off Jan 2026
Penang Mutiara Line LRT starts in Jan 2026, with traffic management measures ready to minimise disruptions.
19-11-2025
Penang Sentral Set to Become Mainland’s Integrated Transport Hub
The Butterworth KTM station, Mutiara Line LRT, and airport expansions will turn Penang Sentral into key transport and logistics hub.
11-11-2025
Penang Defends Mega Projects As Key To Tackling Traffic Woes
Penang’s transport councillor says flyovers, underpasses and the LRT are essential to ease congestion.
04-09-2025
MRT Corp Justifies RM16.8b Penang LRT Budget
MRT Corp says the RM16.8 billion ceiling for Penang LRT reflects market realities, but MCA wants clearer answers on taxpayers’ money.
21-08-2025
Langkawi LRT ‘Unrealistic’, Focus Stays on Penang LRT and ECRL - Loke
The government is pushing ahead with the Penang LRT and ECRL, but dismissed talk of a Langkawi LRT as unrealistic.
19-08-2025
Penang LRT Stays Within RM16 Billion Budget - MRT Corp
Penang LRT project capped at RM16 billion, with MRT Corp aiming to deliver a cost-efficient system despite rising expenses.
30-07-2025
Penang Still Waiting For Green Light From MOT For LRT project
Penang is set to begin Mutiara LRT construction but awaits final approval from MRT Corp and MOT.
02-07-2025
Mutiara LRT Issues Resolved , Earthworks Commencing Soon
Transport Minister announced that all outstanding issues regarding the Mutiara LRT project have been resolved.
11-06-2025
Latest News
Proton Shifted 157,976 Units In 2025, Charts 3.3% Growth & New Export Record
Proton closes 2025 on a high by shifting 157,976 units, logging a 3.3% growth plus a new export record.
02-01-2026
KSM Lowers Kia Spare Parts Price By 15%, Brings New Incentives Too
New prices aside, Kia Sales Malaysia (KSM) also lower Kia spare parts prices by 15%, announces a slew of new incentives too.
02-01-2026
Prasarana Moved 1.54 Million People on New Year’s Eve
Prasarana moved 1.54 million people on New Year’s Eve, marking its highest single-day ridership.
02-01-2026
Updated Fuel Prices From 1 To 7 January
The Ministry of Finance (MoF) has announced the retail prices of all fuels in Malaysia, for the coming week of 1 to 7 January, 2026, the rates are as such.
31-12-2025
Selangor Police Collect RM19.5 Million During Summons Discount Period
More than 258,000 traffic summonses were settled in Selangor during the two-month 70% discount programme, collecting RM19.5 million.
31-12-2025
Traffic Summons Discount Ends, Tougher Penalties Ahead – Should Authorities Extend?
The traffic summons discount is over, millions of fines remain unpaid, and stricter penalties kick in next year
31-12-2025
LRT3: 33 Problems Identified, Solutions Ready, Tests Ongoing
All 33 technical problems identified on the Shah Alam Line have proposed fixes, but full testing is still underway.
31-12-2025
KLIA T1 Moves Customs Checks — Here’s What You Need To Know
Customs checks at KLIA T1 will move to the departure gates from Jan 1, promising smoother departures.
31-12-2025
Show More
trending_flat