Penang LRT Project Progressing Steadily - MRT Corp
-full_normal.jpg)
Construction of the Mutiara Line Penang LRT project is on track, according to the Mass Rapid Transit Corporation on Sunday.
MRT Corp, as the project’s owner stated that it has been actively advancing the Mutiara line Penang LRT project, with obtaining approval for advance works on April 15 being one of its main initiatives.
This comes after MCA vice-president Tan Teik Cheng voiced concerns about the project's seeming lack of physical progress despite its January groundbreaking, as reported by MalaysiaKini.
-full_normal.jpg)
With 86 plots of land secured to date and gazetted ahead of the intended date of October 2025, the firm also emphasized that it has achieved great progress in terms of land purchases, assuring the public that the LRT Mutiara Line project is still on track and on schedule.
In addition, MRT Corp said that SRS Consortium Sdn Bhd, the main contractor for the first package of the LRT line, is fulfilling post-award conditions before issuing an official notice-to-proceed, emphasizing that utility relocation is a critical aspect of pre-construction work that must be completed before any station or viaduct-related construction can begin.

The Mutiara Line, with an estimated cost of RM10 billion to RM13 billion, is considered the largest inland infrastructure project on mainland Penang. The 29.5 km elevated LRT line will have 21 stations, starting from the Silicon Island off Batu Maung.
It will then pass through Weld Quay, its main interchange, the Penang Bridge, and end at the Penang Sentral transport hub in Butterworth.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VQH3994
SELANGOR
BSL6037
JOHOR
JYP6018
PULAU PINANG
PRX5469
PERAK
APE1526
PAHANG
CFE7457
KEDAH
KGD7958
NEGERI SEMBILAN
NEJ2654
KOTA KINABALU
SJP7148
KUCHING
QAB203N
Last updated 14 Jan, 2026
Fuel Price
Petrol
RON 95
RM 2.54
-0.02
RON 97
RM 3.11
-0.05
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.89
-0.05
EURO 5 B7
RM 3.09
-0.05
Last updated 08 Jan, 2026
Latest News
Penang’s Water Taxi Service Delayed Over Safety Concerns
Penang’s water taxi plans are on hold due to safety and approval requirements, said Transport Minister Anthony Loke.
13-01-2026
Perodua Shifted 359,904 Units In 2025, Bezza Remains Its Best-Seller
Second national automaker Perodua capped off 2025 by shifting 359,904 units, Bezza continues to be its best-seller.
13-01-2026
Grab Tests Self-Driving Shuttles In Singapore, Malaysia Next?
Grab is letting locals in Singapore try out self-driving shuttles in Punggol before the service opens to the public.
13-01-2026
Proton Exploring CKD and Local Partnerships in Algeria
Proton is assessing a phased entry into Algeria starting with dealer partnerships, eyes local assembly (CKD) next.
13-01-2026
KTMB Launches Festive Train From KL-Padang Besar This Chinese New Year
KTMB is rolling out a special RTSM train running between KL Sentral and Padang Besar this Feb for Chinese New Year.
13-01-2026
Jaecoo J5 Poised To Galvanize O&J Malaysia In 2026
Fresh off a breakout 2025, O&J Malaysia is turning to the J5 to sustain its rapid growth into the new year.
12-01-2026
Rapid KL Set To Restructure Bus Routes Starting Jan 16
Rapid KL will restructure selected bus and MRT feeder routes starting Jan 16, shifting low-demand services to on-demand vans.
12-01-2026
PLUS Rolls Out ANPR Toll Pilot on Kedah–Penang Stretch
PLUS Malaysia’s ANPR toll pilot delivers lane freedom while laying the groundwork for Multi Lane Free Flow tolling.
12-01-2026
Show More
trending_flat