Penang LRT Stays Within RM16 Billion Budget - MRT Corp
The Penang Mutiara LRT Line will move ahead with a firm budget cap of RM16 billion, despite inflation and escalating construction costs, said MRT Corp chief executive Datuk Mohd Zarif Hashim.
Speaking at a media luncheon, Zarif explained that the earlier RM10 billion estimate, made prior to the federal government's involvement, did not factor in key costs such as land acquisition. He added that even the RM13 billion budget approved by the Cabinet had not fully accounted for inflation, rising material prices, and land-related expenses.
-full_normal.jpg)
“If we included everything without strict cost controls, the project could reach RM19 billion
“But we won’t let that happen. Through competitive tenders and careful planning, we’re determined to keep it under RM16 billion,” he said.
Zarif added that the Mutiara Line is expected to be the most cost-efficient LRT system in the country. To manage land expenses, MRT Corp is working with the Penang government to secure nominal charges for state-owned land.
The 29.5-kilometre line will run from Silicon Island to Komtar, then cross the channel to Penang Sentral in Butterworth. It will feature 21 stations, including a five-kilometre sea bridge standing 62 metres above sea level, designed to accommodate large shipping vessels.

The line will also include an open-air walkway for pedestrians and cyclists, which will be closed during adverse weather. An optimised depot site at Pesta has been downsized from 37 acres to 11 acres through design efficiency.
The trains will use a Level 3 autonomous system that operates without a driver but includes an onboard attendant, allowing for reduced operational and maintenance costs.
Zarif said the Mutiara Line must become financially self-sufficient within five years of operation, funded through fare collection and advertising revenue. He added that this would free up public funds for future transit lines.

“The Mutiara Line won’t solve everything, but it’s a vital first step
“Penang needs at least four LRT lines to see real change. Once all are in place, the impact will be dramatic,” he was quoted as saying.
The Mutiara Line is scheduled for completion in 2031, with the full four-line network expected by 2050.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VQK9401
SELANGOR
BSM3042
JOHOR
JYQ9740
PULAU PINANG
PRY4164
PERAK
APE9454
PAHANG
CFF1670
KEDAH
KGE2329
NEGERI SEMBILAN
NEJ4577
KOTA KINABALU
SJQ1732
KUCHING
QAB1963N
Last updated 04 Feb, 2026
Fuel Price
Petrol
RON 95
RM 2.54
+0.02
RON 97
RM 3.10
+0.02
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.88
+0.04
EURO 5 B7
RM 3.08
+0.04
Last updated 22 Jan, 2026
Related News
Penang Mutiara LRT Construction Kicks Off Jan 2026
Penang Mutiara Line LRT starts in Jan 2026, with traffic management measures ready to minimise disruptions.
19-11-2025
Penang Sentral Set to Become Mainland’s Integrated Transport Hub
The Butterworth KTM station, Mutiara Line LRT, and airport expansions will turn Penang Sentral into key transport and logistics hub.
11-11-2025
Penang Defends Mega Projects As Key To Tackling Traffic Woes
Penang’s transport councillor says flyovers, underpasses and the LRT are essential to ease congestion.
04-09-2025
MRT Corp Justifies RM16.8b Penang LRT Budget
MRT Corp says the RM16.8 billion ceiling for Penang LRT reflects market realities, but MCA wants clearer answers on taxpayers’ money.
21-08-2025
Langkawi LRT ‘Unrealistic’, Focus Stays on Penang LRT and ECRL - Loke
The government is pushing ahead with the Penang LRT and ECRL, but dismissed talk of a Langkawi LRT as unrealistic.
19-08-2025
Penang Still Waiting For Green Light From MOT For LRT project
Penang is set to begin Mutiara LRT construction but awaits final approval from MRT Corp and MOT.
02-07-2025
Mutiara LRT Issues Resolved , Earthworks Commencing Soon
Transport Minister announced that all outstanding issues regarding the Mutiara LRT project have been resolved.
11-06-2025
Penang LRT Project Progressing Steadily - MRT Corp
Construction of the Mutiara Line Penang LRT project is on track, according to MRT Corp.
21-04-2025
Latest News
Martin Schulz Succeeds Amanda Zhang As Mercedes-Benz Malaysia CEO
Mercedes-Benz Cars Malaysia has named Martin Schulz as as its new CEO and president, effective February 1, 2026.
03-02-2026
JPJ Enforces Heavy Vehicle Road Ban Ahead of CNY To Ease Traffic
JPJ enforces heavy vehicle bans to ensure safer, smoother travel this Chinese New Year.
03-02-2026
MITI: Malaysia Poised as High-Value Auto Hub
Malaysia’s skilled workforce and 640+ vendors fuel its rise as a high-value auto export hub.
03-02-2026
Another Singapore Car Caught Pumping Subsidised RON95 In Johor
Another Singapore-registered vehicle has been caught pumping subsidised RON95 petrol in Johor.
03-02-2026
RTS Link to Deploy 100 E-Gates at Bukit Chagar ICQ
RTS Link to deploy 100 e-gates at Bukit Chagar ICQ as part of a high-capacity, congestion-reducing clearance system.
03-02-2026
BateriHub Reaches 200 Stores Nationwide, Sets New ASEAN Record
BateriHub’s ever-expanding local outlet network has now reached 200 locations nationwide.
03-02-2026
Isuzu Reels In ‘Strong’ 2025 Sales Figures Despite Downward Demands
Isuzu Malaysia says its 2025 sales remain strong despite downward demands for diesel vehicles in Malaysia.
02-02-2026
KLIA Aerotrain Performance Stabilising
Independent assessors say the KLIA Aurotrain system is operating as intended, with early service disruptions performance stabilising.
02-02-2026
Show More
trending_flat