Cable Thefts Put ECRL Timeline At Risk - MRL Chief
-full_normal.jpg)
A surge in cable and equipment thefts has jeopardised the timely completion of the East Coast Rail Link (ECRL), Malaysia’s key infrastructure project linking the Klang Valley to the East Coast.
According to Malaysia Rail Link (MRL) Sdn Bhd, 81 outdoor transformer units and over 1,200 metres of signalling cables have been stolen along the route, as reported by The Star yesterday. -full-full_normal.jpg)
The theft of these custom-made components, some of which could take up to six months to replace, has raised serious concerns about potential delays.
“The thefts may delay the project delivery. We were very much looking forward to the testing and commissioning phase in June next year,” said MRL Chief Executive Officer Datuk Seri Darwis Abdul Razak. 
Slated for completion by 2027, this 665-kilometre rail line, now 82.45% complete, is designed for both passenger and freight transport, with trains capable of reaching speeds of 160 km/h for passengers and 80 km/h for cargo.
However, since the installation of Communications, Information, and Signalling (CIS) systems began at KotaSAS Station in Pahang in March, theft incidents have been reported at no fewer than seven locations across Pahang, Terengganu, and Kelantan.

According to Darwis, as the project is still under the contractor’s responsibility, any losses from the thefts will be borne by China Communications Construction Company (CCCC-ECRL).
“That said, we as the project owner will also do our part to curb this problem. The ECRL project team is working closely with police to engage those in the scrap collection or recycling business,” he said, adding that MRL will meet police and ministers to boost ECRL security with patrols, CCTV, and fencing at ground level.

In other developments, Darwis stated that all land acquisition for the main ECRL alignment from Kota Bharu, Kelantan, to Port Klang, Selangor, has been completed with the support of the respective state governments.
He also announced that 38 tunnels have been bored along the route. The last two, the Genting Twin Tunnel and Serendah Tunnel 2, are expected to be completed by the end of this month and early next month, respectively.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VQN6372
SELANGOR
BSM8276
JOHOR
JYS3421
PULAU PINANG
PSA1732
PERAK
APF5749
PAHANG
CFF5306
KEDAH
KGE5444
NEGERI SEMBILAN
NEJ6421
KOTA KINABALU
SJQ5624
KUCHING
QAB3520N
Last updated 01 Mar, 2026
Fuel Price
Petrol
RON 95
RM 2.59
+0.05
RON 97
RM 3.15
+0.05
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.04
+0.05
EURO 5 B7
RM 3.24
+0.05
Last updated 26 Feb, 2026
Related News
Kuantan Welcomes ECRL’s First Trains Ahead of 2027 Operations
The first ECRL electric passenger trains and freight locomotives have arrived in Kuantan as the project moves closer to operations in 2027.
11-02-2026
ECRL Fares To Be Announced Ahead of 2027 Launch
ECRL fares will be disclosed several months prior to the commencement of operations in January 2027, according to Transport Minister.
30-01-2026
ECRL Launch Hinges On System Integration, Jan 2027 Target Maintained
The ECRL remains on schedule, with system integration and testing now the key focus ahead of its planned Jan 2027 launch.
29-01-2026
ECRL First EMU Trains, E-Locos Head To Malaysia For Testing
Malaysia’s East Coast Rail Link gears up as its first EMUs and electric locomotives arrive for testing and future service.
17-12-2025
First ECRL Trains Depart China, Remaining Units Arriving Through 2026
First ECRL trains depart China, with remaining units scheduled to arrive through 2026.
28-11-2025
ECRL Nears Completion with 89% Progress, Operations Set for 2027
ECRL is on track to begin services from Kota Bharu to Gombak in Jan 2027, as construction progress hits 89%.
24-11-2025
ECRL Trains Fully Assembled, Ready for Malaysia
The first batch of trains for the East Coast Rail Link (ECRL) is now ready in Dalian, China.
21-11-2025
ECRL Hits 88% Milestone As Key C1B Stretch Completed
The ECRL project has hit 88% completion with the C1B Segment now successfully completed.
05-11-2025
Latest News
Kelana Jaya LRT trains “out of service” but line running normally - RapidRail
Rapid Rail clarified that temporary train withdrawals on the Kelana Jaya LRT line are part of standard safety procedures.
27-02-2026
Leapmotor C10 Plus Debuts In Malaysia - 299 hp, 510 km Range, From RM139k
The 2026 Leapmotor C10 PLUS and exclusive Night Edition arrive in Malaysia with longer range, faster charging, and upgraded performance.
27-02-2026
Chery Malaysia Teams Up with Lee Chong Wei for Youth Badminton Cup
Chery Malaysia joins forces with Lee Chong Wei to sponsor the inaugural national youth tournament with RM100,000 in prizes.
27-02-2026
Updated Fuel Prices From 26 February To 4 March
The Ministry of Finance (MoF) has announced the retail prices of all fuels in Malaysia, for the coming week of 26 February to 4 March, 2026, the rates are as such.
25-02-2026
APAD to Investigate Kelana Jaya LRT Breakdowns, Prasarana Ordered to Explain
Transport Minister has directed APAD to probe recent Kelana Jaya LRT disruptions and warned action may be taken against Prasarana.
25-02-2026
Chery TIGGO CROSS HEV Grand Prize Winner Announced
Joan Gan became the grand prize winner of a Chery TIGGO CROSS HEV, chosen from over 1,300 participants in Chery Malaysia’s year-end PHEV lucky draw.
24-02-2026
LRT3 Set for June 2026 Launch, Contractor Faces RM2.73 Million Daily Penalty for Delays
The Shah Alam LRT3 line is targeted to begin operations by June 2026, with contractors liable for RM2.73 million per day in delay penalties.
24-02-2026
Johor–Singapore RTS Link Fare Expected at RM15 to RM22 Per Trip
Transport Minister Anthony Loke says the RTS Link could cost between RM15 and RM22 per journey, with fares to be announced in 2H2026.
23-02-2026
Show More
trending_flat