ECRL: KotaSAS Station System Installation Completed

The East Coast Rail Link (ECRL) project is set to mark a significant milestone as system installation works at the KotaSAS Central Station are now complete.
It’s now the first station along the 665-KM alignment to achieve this progress. KotaSAS holds symbolic value for the project - it was the site of the groundbreaking ceremony in Aug 2017, officiated by former PM Datuk Seri Najib Razak.

The ECRL spans four states - Kelantan, Terengganu, Pahang, and Selangor - and will feature 20 stations. It is expected to reach 90% overall completion by the end of this year.

Malaysia Rail Link Sdn Bhd (MRL) CEO Datuk Seri Darwis Abdul Razak said the project had recorded 82.45% overall progress as of April. Regionally, progress stands at 89% in Kelantan, 91% in Terengganu, 84% in Pahang and 67% in Selangor.
“These figures show the project is advancing steadily. With continued support from all involved states, we’re confident of hitting the 90% mark by year-end,” he said during a ceremony at the KotaSAS Station.

The event marked the successful installation of the Communication, Information and Signalling (CIS) systems at the station. These systems ensure safe, efficient and reliable train operations through automated train protection, traffic control and real-time passenger information.
Darwis further noted the completion reflects years of collaboration between MRL and project contractor China Communications Construction Company (CCCC).


The ECRL plans to begin testing and commissioning in June 2026. Two six-car Electric Multiple Unit (EMU) trains for passengers and two Electric Locomotives (E-Loco) for freight are expected to arrive in Malaysia by year-end. Full delivery of all 11 EMU sets and 12 E-Locos is scheduled by June 2026.
The ECRL will link Kota Baru to the Gombak Integrated Transport Terminal, with operations slated to begin in Jan 2027. Meanwhile the final stretch to Port Klang is expected to open by Jan 2028.
Source: NSTP
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VPX7430
SELANGOR
BSJ8364
JOHOR
JYK4711
PULAU PINANG
PRV3934
PERAK
APC2632
PAHANG
CFD9516
KEDAH
KGC8197
NEGERI SEMBILAN
NEH5064
KOTA KINABALU
SJN4985
KUCHING
QAB4624M
Last updated 31 Oct, 2025
Fuel Price
Petrol
RON 95
RM 2.60
RON 97
RM 3.20
+0.06
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.95
+0.06
EURO 5 B7
RM 3.15
+0.06
Last updated 30 Oct, 2025
Related News
ECRL Project On Track Despite RM2.9mil Theft Losses
MRL boosts security after 38 theft cases but says the ECRL project remains on schedule.
30-10-2025
MOT Eyes Rail Expansion, Road Safety and Airport Improvements
Transport Minister YB Loke Siew Fook outlines major transport projects and safety reforms under the 2026 Budget.
30-10-2025
ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses
The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.
14-10-2025
Budget 2026: Prasarana Seeks Continued Support for Travel Passes and LRT3
Prasarana moots continued support for travel passes, LRT 3 line completion, cites them as key to easing living costs and improving urban mobility.
09-10-2025
ECRL Project Hits 87% Completion by August 2025 – MoT
The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.
23-09-2025
ECRL Work Halted - Petronas Gas Pipeline Leak, Safety Zone Declared
Petronas Gas pipeline leak at the ECRL project has halted works, emergency crews racing to purge butane gas.
22-09-2025
ECRL Cites Potential Delay From Escalated Cable and Wire Theft
ECRL says thefts of cable and wires could derail construction progress on the 665 km railway project.
11-09-2025
Govt Studying ECRL Extension to Thai Border Town Rantau Panjang
Anwar says the ECRL extension to Rantau Panjang could open new growth at the Malaysia–Thailand border.
03-09-2025
Latest News
BUDI95 Fuel Shortfall Claims Untrue - KPDN
KPDN says claims of fuel shortfalls under the BUDI95 are unfounded after inspections found all petrol pumps accurate.
31-10-2025
LPT3 Will Proceed Under Public-Private Partnership Model - Ahmad Maslan
RM9.8b East Coast Expressway 3 (LPT3) will be developed via public-private partnership at no cost to the government.
31-10-2025
Suzuki Fronx Secures 5-Star ASEAN NCAP Rating
The new Suzuki Fronx achieves full 5-star ASEAN NCAP rating, scoring 77.70 points under latest 2021–2025 protocol.
31-10-2025
Loke Orders MAHB To Keep Shuttle Bus Amid KLIA Aerotrain Woes
Transport minister says shuttle buses must stay as investigations continue into repeated aerotrain breakdowns.
31-10-2025
KPDN Busts Pig Slaughterhouse For Illegal Diesel Storage
Authorities seized 2,000L of subsidised diesel hidden inside a Perak pig slaughterhouse.
30-10-2025
Govt Won’t Suspend KLIA Aerotrain, MAHB Facing Action - Loke
Loke says the government won’t halt the KLIA Aerotrain, but MAHB is facing action.
30-10-2025
MOT Eyes Rail Expansion, Road Safety and Airport Improvements
Transport Minister YB Loke Siew Fook outlines major transport projects and safety reforms under the 2026 Budget.
30-10-2025
ECRL Project On Track Despite RM2.9mil Theft Losses
MRL boosts security after 38 theft cases but says the ECRL project remains on schedule.
30-10-2025
Show More
trending_flat