ECRL: KotaSAS Station System Installation Completed

Kumeran Sagathevan

Share via

500930148_1264181722377380_3321655277337348046_n.jpg


The East Coast Rail Link (ECRL) project is set to mark a significant milestone as system installation works at the KotaSAS Central Station are now complete.

It’s now the first station along the 665-KM alignment to achieve this progress. KotaSAS holds symbolic value for the project - it was the site of the groundbreaking ceremony in Aug 2017, officiated by former PM Datuk Seri Najib Razak.


ECRL-EMU-TrainSet.jpg


The ECRL spans four states - Kelantan, Terengganu, Pahang, and Selangor - and will feature 20 stations. It is expected to reach 90% overall completion by the end of this year.


489529434_1096858725817108_4171642192043904876_n.jpg


Malaysia Rail Link Sdn Bhd (MRL) CEO Datuk Seri Darwis Abdul Razak said the project had recorded 82.45% overall progress as of April. Regionally, progress stands at 89% in Kelantan, 91% in Terengganu, 84% in Pahang and 67% in Selangor.

“These figures show the project is advancing steadily. With continued support from all involved states, we’re confident of hitting the 90% mark by year-end,” he said during a ceremony at the KotaSAS Station.


500773660_1264181729044046_8551383766751082143_n.jpg


The event marked the successful installation of the Communication, Information and Signalling (CIS) systems at the station. These systems ensure safe, efficient and reliable train operations through automated train protection, traffic control and real-time passenger information.

Darwis further noted the completion reflects years of collaboration between MRL and project contractor China Communications Construction Company (CCCC).


500765794_1264181725710713_5169612591415662045_n.jpg500765059_1264181735710712_3615609946491117187_n.jpg


The ECRL plans to begin testing and commissioning in June 2026. Two six-car Electric Multiple Unit (EMU) trains for passengers and two Electric Locomotives (E-Loco) for freight are expected to arrive in Malaysia by year-end. Full delivery of all 11 EMU sets and 12 E-Locos is scheduled by June 2026.

The ECRL will link Kota Baru to the Gombak Integrated Transport Terminal, with operations slated to begin in Jan 2027. Meanwhile the final stretch to Port Klang is expected to open by Jan 2028.


Source: NSTP

Share This Article

More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!

Share via

JPJ Running Numbers

KUALA LUMPUR

VQK8720

SELANGOR

BSM2849

JOHOR

JYQ9301

PULAU PINANG

PRY3979

PERAK

APE9142

PAHANG

CFF1571

KEDAH

KGE2158

NEGERI SEMBILAN

NEJ4527

KOTA KINABALU

SJQ1638

KUCHING

QAB1935N

Last updated 03 Feb, 2026

Fuel Price

Petrol

RON 95

RM 2.54

+0.02

RON 97

RM 3.10

+0.02

RON 100

RM 5.00

VPR

RM 6.23

Diesel

EURO 5 B10

RM 2.88

+0.04

EURO 5 B7

RM 3.08

+0.04

Last updated 22 Jan, 2026

Related News

Auto News
ECRL Fares To Be Announced Ahead of 2027 Launch

ECRL Fares To Be Announced Ahead of 2027 Launch

ECRL fares will be disclosed several months prior to the commencement of operations in January 2027, according to Transport Minister.

30-01-2026
Auto News
ECRL Launch Hinges On System Integration, Jan 2027 Target Maintained

ECRL Launch Hinges On System Integration, Jan 2027 Target Maintained

The ECRL remains on schedule, with system integration and testing now the key focus ahead of its planned Jan 2027 launch.

29-01-2026
Auto News
ECRL First EMU Trains, E-Locos Head To Malaysia For Testing

ECRL First EMU Trains, E-Locos Head To Malaysia For Testing

Malaysia’s East Coast Rail Link gears up as its first EMUs and electric locomotives arrive for testing and future service.

17-12-2025
Auto News
First ECRL Trains Depart China, Remaining Units Arriving Through 2026

First ECRL Trains Depart China, Remaining Units Arriving Through 2026

First ECRL trains depart China, with remaining units scheduled to arrive through 2026.

28-11-2025
Auto News
ECRL Nears Completion with 89% Progress, Operations Set for 2027

ECRL Nears Completion with 89% Progress, Operations Set for 2027

ECRL is on track to begin services from Kota Bharu to Gombak in Jan 2027, as construction progress hits 89%.

Auto News
ECRL Trains Fully Assembled, Ready for Malaysia

ECRL Trains Fully Assembled, Ready for Malaysia

The first batch of trains for the East Coast Rail Link (ECRL) is now ready in Dalian, China.

21-11-2025
Auto News
ECRL Hits 88% Milestone As Key C1B Stretch Completed

ECRL Hits 88% Milestone As Key C1B Stretch Completed

The ECRL project has hit 88% completion with the C1B Segment now successfully completed.

05-11-2025
Auto News
ECRL Project On Track Despite RM2.9mil Theft Losses

ECRL Project On Track Despite RM2.9mil Theft Losses

MRL boosts security after 38 theft cases but says the ECRL project remains on schedule.

30-10-2025

Latest News

Auto News
MITI: Malaysia Poised as High-Value Auto Hub

MITI: Malaysia Poised as High-Value Auto Hub

Malaysia’s skilled workforce and 640+ vendors fuel its rise as a high-value auto export hub.

Auto News
Another Singapore Car Caught Pumping Subsidised RON95 In Johor

Another Singapore Car Caught Pumping Subsidised RON95 In Johor

Another Singapore-registered vehicle has been caught pumping subsidised RON95 petrol in Johor.

03-02-2026
Auto News
RTS Link to Deploy 100 E-Gates at Bukit Chagar ICQ

RTS Link to Deploy 100 E-Gates at Bukit Chagar ICQ

RTS Link to deploy 100 e-gates at Bukit Chagar ICQ as part of a high-capacity, congestion-reducing clearance system.

Auto News
BateriHub Reaches 200 Stores Nationwide, Sets New ASEAN Record

BateriHub Reaches 200 Stores Nationwide, Sets New ASEAN Record

BateriHub’s ever-expanding local outlet network has now reached 200 locations nationwide.

03-02-2026
Auto News
Isuzu Reels In ‘Strong’ 2025 Sales Figures Despite Downward Demands

Isuzu Reels In ‘Strong’ 2025 Sales Figures Despite Downward Demands

Isuzu Malaysia says its 2025 sales remain strong despite downward demands for diesel vehicles in Malaysia.

02-02-2026
Auto News
KLIA Aerotrain Performance Stabilising

KLIA Aerotrain Performance Stabilising

Independent assessors say the KLIA Aurotrain system is operating as intended, with early service disruptions performance stabilising.

Auto News
WISE Highway Project May Get Six-Month Extension To Strengthen Financial

WISE Highway Project May Get Six-Month Extension To Strengthen Financial

KKR may grant a six-month extension to the WISE Highway developer to secure funding and complete preparations.

02-02-2026
Auto News
Ford, Xiaomi Denies EV Joint Venture Talks In US

Ford, Xiaomi Denies EV Joint Venture Talks In US

Ford and Xiaomi dismiss reports of joint venture discussions for EV production in the US.

02-02-2026

Show More

trending_flat
Carz Automedia Malaysia Logo
About Us

CarzAutoMedia: Stay connected to the latest car news! Get instant updates on new releases, industry trends, and automotive innovations. Your go-to source for 24/7 coverage of everything automotive.

© 2026 CariCarz.com. All Rights Reserved.