ECRL Breakthrough: Genting Tunnel Becomes SEA’s Longest Rail Tunnel

The East Coast Rail Link (ECRL) project has hit a major milestone recently with the breakthrough of the Genting Tunnel, a 16.39KM twin-bore tunnel running through the Titiwangsa mountain range.
Transport Minister YB Anthony Loke, who officiated the event, called it a historic moment for Malaysian infrastructure. The tunnel was completed on schedule after more than two years of digging.
It is now officially the longest rail tunnel in Southeast Asia and the most challenging of the 41 tunnels along the ECRL route.


Genting Tunnel’s construction used both Tunnel Boring Machines (TBM) and traditional drill-and-blast methods. The TBMs, built in China and designed for Malaysia’s hard rock terrain, each weigh over 1,600 tonnes and measure nearly 9 metres in diameter.
Malaysia Rail Link (MRL) CEO Datuk Seri Darwis Abdul Razak said completing the tunnel on time was a big achievement, especially given the tough conditions of the mountainous terrain.
The tunnel also highlights ECRL’s commitment to protecting the environment. With the revised alignment, the amount of forest clearing was reduced from 2,000 hectares to just 276 hectares by using more tunnels and elevated tracks.


It also helps maintain a consistent track gradient of 0.9%, which allows passenger trains to run up to 160 KM/H and freight trains up to 80 KM/H.
With the Genting Tunnel boring complete, the project now moves into the next phase. This includes laying tracks and installing electrical systems, signals, communications, and station facilities.
The ECRL is on track to be completed by the end of 2026, with passenger services starting in stages from January 2027.



The Transport Ministry is also looking into extending the line from Kota Bharu to Rantau Panjang to improve cross-border rail links with Thailand. If it goes ahead, the ECRL could eventually connect with rail networks connecting all the way to Kunming in China.
As part of Malaysia’s Belt and Road Initiative, the ECRL will link Kuantan Port on the East Coast to Port Klang on the West Coast. This could cut cargo shipping time by up to 2.5 days and improve logistics efficiency.
Once fully operational, the electrified railway is expected to earn 70% of its revenue from freight services, with the rest coming from passenger travel.
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VRH4549
SELANGOR
BSR8671
JOHOR
JA8445J
PULAU PINANG
PSE1592
PERAK
APK1817
PAHANG
CFH2600
KEDAH
KGH2589
NEGERI SEMBILAN
NEL1429
KOTA KINABALU
SJT2473
KUCHING
QAB2481P
Last updated 25 Jul, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
Kuantan Welcomes ECRL’s First Trains Ahead of 2027 Operations
The first ECRL electric passenger trains and freight locomotives have arrived in Kuantan as the project moves closer to operations in 2027.
11-02-2026
ECRL Fares To Be Announced Ahead of 2027 Launch
ECRL fares will be disclosed several months prior to the commencement of operations in January 2027, according to Transport Minister.
30-01-2026
ECRL Launch Hinges On System Integration, Jan 2027 Target Maintained
The ECRL remains on schedule, with system integration and testing now the key focus ahead of its planned Jan 2027 launch.
29-01-2026
ECRL First EMU Trains, E-Locos Head To Malaysia For Testing
Malaysia’s East Coast Rail Link gears up as its first EMUs and electric locomotives arrive for testing and future service.
17-12-2025
First ECRL Trains Depart China, Remaining Units Arriving Through 2026
First ECRL trains depart China, with remaining units scheduled to arrive through 2026.
28-11-2025
ECRL Nears Completion with 89% Progress, Operations Set for 2027
ECRL is on track to begin services from Kota Bharu to Gombak in Jan 2027, as construction progress hits 89%.
24-11-2025
ECRL Trains Fully Assembled, Ready for Malaysia
The first batch of trains for the East Coast Rail Link (ECRL) is now ready in Dalian, China.
21-11-2025
ECRL Hits 88% Milestone As Key C1B Stretch Completed
The ECRL project has hit 88% completion with the C1B Segment now successfully completed.
05-11-2025
Latest News
Honda Built A Giant RM14 Million 'Power Bank' In Melaka—Here’s What It Does
Honda Malaysia self-invested RM14M to install 8,960 solar panels and a pioneer BESS battery system at its Melaka factory, slashing CO2 emissions by 10%.
24-07-2026
Is Now A Good Time To Buy A New Car In Malaysia? Stable Prices & EV Trends Explained
EVs are officially outselling hybrids in Malaysia! See how 106% sales growth and affordable models like Proton e.MAS are powering the 2026 boom. Malaysia car market 2026, MAA H1 2026 report, Malaysia EV sales growth, Proton eMAS 5 sales, Proton eMAS 7 price, best EV to buy Malaysia 2026, MAA 800k sa
22-07-2026
Can You Service Your Car Outside Official Service Centres? KPDN Proposes 'Right To Repair' Law
Can you service your car outside official service centres? KPDN studies a 'Right to Repair' law under the Consumer Protection Act to empower vehicle owners.
22-07-2026
5 Game-Changing Upgrades Coming To The New RM100M Seremban Sentral Station By March 2027
Discover 5 major upgrades coming to the RM100M Seremban Sentral railway station by March 2027, featuring Minangkabau design, new platforms, and flood fixes.
21-07-2026
RM1.50 Petrol Is Off The Table – PM Anwar Finally Responds To Netizens
PM Anwar responds to calls for RM1.50 petrol, explaining why fuel prices won't drop further as Malaysia spends RM40 billion yearly on subsidies.
21-07-2026
A M'sian Man Sued JPJ Director-General Over 'MADANI' Plate Idea... And He Actually Won!
The High Court finds the JPJ Director-General liable for copyright infringement over the MADANI number plate proposal. Here is the legal breakdown.
20-07-2026
Dunlop’s 2026 Comeback: The Legacy That Started in 1962, Now with 18-Month Road Hazard Protection
The flying 'D' is back. Dunlop Malaysia expands its network to over 200 dealers under Toyotsu Binter and Sumitomo, rolling out a massive 18-month road hazard warranty.
20-07-2026
5 Reasons to Visit BMW Clubhouse This Weekend: M-Power Debuts & Limited-Time Offers
BMW Clubhouse opens at Factory 19 PJ. Experience the all-new M2 CS and M3 Touring debuts alongside limited-time offers with up to RM55k off!
17-07-2026
Show More
trending_flat