ECRL Breakthrough: Genting Tunnel Becomes SEA’s Longest Rail Tunnel

The East Coast Rail Link (ECRL) project has hit a major milestone recently with the breakthrough of the Genting Tunnel, a 16.39KM twin-bore tunnel running through the Titiwangsa mountain range.
Transport Minister YB Anthony Loke, who officiated the event, called it a historic moment for Malaysian infrastructure. The tunnel was completed on schedule after more than two years of digging.
It is now officially the longest rail tunnel in Southeast Asia and the most challenging of the 41 tunnels along the ECRL route.


Genting Tunnel’s construction used both Tunnel Boring Machines (TBM) and traditional drill-and-blast methods. The TBMs, built in China and designed for Malaysia’s hard rock terrain, each weigh over 1,600 tonnes and measure nearly 9 metres in diameter.
Malaysia Rail Link (MRL) CEO Datuk Seri Darwis Abdul Razak said completing the tunnel on time was a big achievement, especially given the tough conditions of the mountainous terrain.
The tunnel also highlights ECRL’s commitment to protecting the environment. With the revised alignment, the amount of forest clearing was reduced from 2,000 hectares to just 276 hectares by using more tunnels and elevated tracks.


It also helps maintain a consistent track gradient of 0.9%, which allows passenger trains to run up to 160 KM/H and freight trains up to 80 KM/H.
With the Genting Tunnel boring complete, the project now moves into the next phase. This includes laying tracks and installing electrical systems, signals, communications, and station facilities.
The ECRL is on track to be completed by the end of 2026, with passenger services starting in stages from January 2027.



The Transport Ministry is also looking into extending the line from Kota Bharu to Rantau Panjang to improve cross-border rail links with Thailand. If it goes ahead, the ECRL could eventually connect with rail networks connecting all the way to Kunming in China.
As part of Malaysia’s Belt and Road Initiative, the ECRL will link Kuantan Port on the East Coast to Port Klang on the West Coast. This could cut cargo shipping time by up to 2.5 days and improve logistics efficiency.
Once fully operational, the electrified railway is expected to earn 70% of its revenue from freight services, with the rest coming from passenger travel.
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VQJ4751
SELANGOR
BSL8945
JOHOR
JYQ2710
PULAU PINANG
PRX9482
PERAK
APE4703
PAHANG
CFE8867
KEDAH
KGD9571
NEGERI SEMBILAN
NEJ3497
KOTA KINABALU
SJP8418
KUCHING
QAB760N
Last updated 23 Jan, 2026
Fuel Price
Petrol
RON 95
RM 2.54
+0.02
RON 97
RM 3.10
+0.02
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.88
+0.04
EURO 5 B7
RM 3.08
+0.04
Last updated 22 Jan, 2026
Related News
ECRL First EMU Trains, E-Locos Head To Malaysia For Testing
Malaysia’s East Coast Rail Link gears up as its first EMUs and electric locomotives arrive for testing and future service.
17-12-2025
First ECRL Trains Depart China, Remaining Units Arriving Through 2026
First ECRL trains depart China, with remaining units scheduled to arrive through 2026.
28-11-2025
ECRL Nears Completion with 89% Progress, Operations Set for 2027
ECRL is on track to begin services from Kota Bharu to Gombak in Jan 2027, as construction progress hits 89%.
24-11-2025
ECRL Trains Fully Assembled, Ready for Malaysia
The first batch of trains for the East Coast Rail Link (ECRL) is now ready in Dalian, China.
21-11-2025
ECRL Hits 88% Milestone As Key C1B Stretch Completed
The ECRL project has hit 88% completion with the C1B Segment now successfully completed.
05-11-2025
ECRL Project On Track Despite RM2.9mil Theft Losses
MRL boosts security after 38 theft cases but says the ECRL project remains on schedule.
30-10-2025
MOT Eyes Rail Expansion, Road Safety and Airport Improvements
Transport Minister YB Loke Siew Fook outlines major transport projects and safety reforms under the 2026 Budget.
30-10-2025
ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses
The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.
14-10-2025
Latest News
UPSI Bus Crash: Brake Fade, Speed Cited as Key Factors
Mechanical faults, speeding, and poor oversight behind deadly Gerik bus crash, according to report.
23-01-2026
Volvo Teases ES90 Launch With ‘SELAMAT’ Campaign
Volvo Malaysia briefly presented “SELAMAT” as a new brand before revealing it as a safety-themed teaser campaign ahead of the ES90 launch.
23-01-2026
LEPAS Confirms 20-Outlets Ahead of 2026 Malaysia Launch
LEPAS signals serious intent ahead of its 2026 launch, confirming 20 sales and service outlets across Malaysia.
23-01-2026
JPJ Lifts Travel Proof Rule for Physical Driving Licence
JPJ lifts the travel proof rule, allowing motorists to apply for a physical licence without overseas travel justification.
23-01-2026
KL’s Lalaport Hub Nears Approval for Singapore Express Buses
KL’s Lalaport transport hub nears approval, set to streamline express bus travel to Singapore by February.
22-01-2026
Overloaded Lorry Crackdown Reduces Road Deaths
Stricter JPJ checks on overloaded lorries are helping make Malaysian roads safer with fewer fatal accidents.
22-01-2026
Bukit Chagar RTS Link Station Roof Completed, Final Facade Works Underway
Bukit Chagar station reaches a major milestone as the RTS Link roof is completed.
22-01-2026
Puspakom - New Brake Inspection Rules for Heavy Vehicles
Puspakom’s new brake inspection rules for heavy vehicles target unsafe brake settings that increase accident risks.
22-01-2026
Show More
trending_flat