ECRL Hits 88% Milestone As Key C1B Stretch Completed
Photo: Bernama.
The East Coast Rail Link (ECRL) has reached 88% overall progress following the completion of the C1B Segment, a key stretch connecting the Genting Tunnel exit to the Gombak Integrated Terminal.
Construction of the segment began in September 2022 and covers the Gombak Tunnel, two bridges, and major subgrade works linking the East and West Coast sections of the 665km rail network.
With this, progress in Selangor now stands at about 77%.

“This milestone is not merely about completing a section of track, it’s about fulfilling a national aspiration to connect people, economies and opportunities between the East Coast and the Klang Valley,” said Malaysia Rail Link (MRL) CEO Datuk Seri Darwis Abdul Razak.
China Communications Construction (ECRL) Sdn Bhd (CCCECRL) managing director Deng Bo said the C1B Segment was among the most challenging parts of the Selangor alignment due to complex geological conditions and limited working space near major highways.
-full-(1).jpg)
-full-(1).jpg)
“The segment’s location near a major transportation hub and crossing key highways further added to the engineering and logistical challenges,” he stated.
The team used advanced engineering tools such as structural simulations, modular prefabrication and digital precision systems to ensure safety and efficiency.

The C1B completion paves the way for the next phase which are track laying, system installation and testing as the project moves toward full completion by end-2026.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VQR1758
SELANGOR
BSN4692
JOHOR
JYT4665
PULAU PINANG
PSA6584
PERAK
APG1363
PAHANG
CFF8496
KEDAH
KGE8326
NEGERI SEMBILAN
NEJ8149
KOTA KINABALU
SJQ8651
KUCHING
QAB4273N
Last updated 23 Mar, 2026
Fuel Price
Petrol
RON 95
RM 2.59
+0.05
RON 97
RM 3.15
+0.05
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.04
+0.05
EURO 5 B7
RM 3.24
+0.05
Last updated 26 Feb, 2026
Related News
Kuantan Welcomes ECRL’s First Trains Ahead of 2027 Operations
The first ECRL electric passenger trains and freight locomotives have arrived in Kuantan as the project moves closer to operations in 2027.
11-02-2026
ECRL Fares To Be Announced Ahead of 2027 Launch
ECRL fares will be disclosed several months prior to the commencement of operations in January 2027, according to Transport Minister.
30-01-2026
ECRL Launch Hinges On System Integration, Jan 2027 Target Maintained
The ECRL remains on schedule, with system integration and testing now the key focus ahead of its planned Jan 2027 launch.
29-01-2026
ECRL First EMU Trains, E-Locos Head To Malaysia For Testing
Malaysia’s East Coast Rail Link gears up as its first EMUs and electric locomotives arrive for testing and future service.
17-12-2025
First ECRL Trains Depart China, Remaining Units Arriving Through 2026
First ECRL trains depart China, with remaining units scheduled to arrive through 2026.
28-11-2025
ECRL Nears Completion with 89% Progress, Operations Set for 2027
ECRL is on track to begin services from Kota Bharu to Gombak in Jan 2027, as construction progress hits 89%.
24-11-2025
ECRL Trains Fully Assembled, Ready for Malaysia
The first batch of trains for the East Coast Rail Link (ECRL) is now ready in Dalian, China.
21-11-2025
MOT Eyes Rail Expansion, Road Safety and Airport Improvements
Transport Minister YB Loke Siew Fook outlines major transport projects and safety reforms under the 2026 Budget.
30-10-2025
Latest News
Strait of Hormuz to Malaysia: Why We’re Paying for a War 6,000km Away
Why is RON97 at RM4.55/L? We decode the Strait of Hormuz conflict, the May 2026 subsidy deadline, and why Malaysia imports oil despite being a producer.
19-03-2026
From 82 Minutes to 8: How the Mutiara Line is Giving Penangites Their Time Back
Is the 80-minute Penang Bridge crawl finally ending? The Mutiara Line LRT links Butterworth to Komtar in just 8 minutes. Get the latest 2026 project updates, station lists, and more.
17-03-2026
The 2026 Proton X90 Buyer’s Warning: 5 Critical Safety Features You Are No Longer Getting
ASEAN NCAP revokes Proton X90’s 5-star rating. The 2026 facelift is downgraded to 1-star after stripping critical ADAS features. Is your family safe? Get the full safety specs here.
16-03-2026
9,000+ Drivers Chose Toyota Hybrids This Year: Proof That Toyota’s Multi-Pathway Strategy Works
Toyota Malaysia hits 9,556 sales in early 2026, proving the "Multi-Pathway" strategy works. From Vios Hybrid to Vellfire HEV, see why hybrids are winning the sales war.
12-03-2026
Chery Tiggo 7 is Now the Safest Chinese SUV on the Planet, This Is Why
The Chery Tiggo 7 makes history as the only Chinese SUV to sweep 5-star ratings from Euro NCAP, ANCAP, and ASEAN NCAP. With a record 94.68 points, see why this is 2026’s safest family SUV.
11-03-2026
Sepang Dates Confirmed: Catch Team Porsche Malaysia in Action on 21–23 August
While the 2026 Porsche Carrera Cup Asia (PCCA) season kicks off in Shanghai this weekend, Malaysian fans are already looking ahead to the highlight of the year: the homecoming.
10-03-2026
Iran-US War Day 10: It’s Not Just Fuel — Malaysia’s Automotive Industry Faces New Risks
While the BUDI95 subsidy program is already feeling the heat of oil prices flirting with US$120 a barrel, the true threat to our automotive sector lies beneath the surface.
09-03-2026
Prasarana to Reveal LRT3 Launch Date This April—Here’s Everything We Know So Far
The wait for the LRT3 Shah Alam Line is entering its final stretch. After months of "will they, won't they" speculation, Prasarana has officially pointed to April 2026 as the month of truth.
05-03-2026
Show More
trending_flat