Traffic Diversion On Bukit Gambir-Tangkak From Aug 5
Drivers travelling along the North-South Expressway near Tangkak can expect traffic diversions starting August 5, as construction kicks off on a new bridge.
The affected stretch spans KM166.79 to KM168.26 between the Bukit Gambir and Tangkak Elevated Interchange, and the diversion will be activated in both directions.
The works are expected to continue until December 30.
PLUS Malaysia Berhad (PLUS) confirmed that the diversions will be introduced in stages to make way for bridge construction works carried out by contractors from the Public Works Department (JKR).
“Highway users are encouraged to plan their routes ahead and follow all traffic signs and directions from on-site personnel,” PLUS said in a statement on Sunday.
Real-time traffic updates will be available through the PLUS mobile app, the PUTRI Virtual Assistant, the @plustrafik account on X, and electronic message boards (VMS) along the highway.

For urgent help or emergencies, motorists can also call PLUSLine at 1800-88-0000.
PLUS is reminding drivers to stay alert in the area throughout the construction period and to be patient as the work progresses.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VRD1482
SELANGOR
BSQ9457
JOHOR
JYB1251
PULAU PINANG
PSD2078
PERAK
APJ3231
PAHANG
CFG8230
KEDAH
KGG5841
NEGERI SEMBILAN
NEK6951
KOTA KINABALU
SJS4722
KUCHING
QAB269P
Last updated 23 Jun, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
PLUS Activates Contra Lane On Elite Until Nov 27
A nightly contra lane will run between Bandar Saujana Putra and Putrajaya with lane diversions in place.
25-11-2025
PLUS To Close Two Bangi Ramps Nightly Until Nov 28
PLUS will close two ramps near Bangi nightly from 10PM to 5AM starting today until Nov 28.
10-11-2025
RM3b Juru–Sungai Dua Link Cuts Travel Time To Just 20 Minutes
RM3 billion traffic dispersal project aims to slash travel time between Juru and Sungai Dua from an hour to just 20 minutes.
10-11-2025
Work Begins On Juru–Sungai Dua Traffic Dispersal Project To Ease Penang Congestion
Work has officially kicked off on the long-awaited traffic dispersal project between the Juru and Sungai Dua toll plazas (PTJSD).
21-10-2025
Seremban R&R Set To House Terra ChargEV – Nation’s First Integrated Charging Hub
Terra ChargEV announces first project at Seremban R&R Southbound, will bring 20 high-speed DC chargers and solar-ready infra by 2027.
16-10-2025
Court Tells PLUS to Install Streetlights Along Dark Stretches of the NSE
The Court of Appeal has urged PLUS to install streetlights along dark stretches of the NSE after a fatal crash case.
25-09-2025
PLUS Announces Partial Lane Closures On NKVE, 10-11 Sept
Closures between Jalan Duta and Bukit Lanjan will take place from 11PM to 5AM for billboard gantry installation.
09-09-2025
Maintenance on NKVE & ELITE – KM 19.3 – KM 20.0, July 19 to Oct 14
PLUS has issued a statement regarding the maintenance works and contraflow activations on both the NKVE & ELITE.
21-07-2025
Latest News
"Not Our Priority" — Minister Reveals The 4 Major Road Crimes JPJ Is Hunting Instead Of Sunshades
Transport Minister Anthony Loke clarifies that JPJ will not target motorists using removable car window sunshades, choosing instead to focus enforcement priorities on illegal racing, mat rempit, drunk driving, and reckless driving.
22-06-2026
M'sia Is Moving Toward Barrier-Free Tolls, But Gov Just Dropped One Non-Negotiable Rule
Works Minister Datuk Seri Alexander Nanta Linggi reveals that while Malaysia's barrier-free MLFF toll system negotiations are advanced, the government has set a strict, non-negotiable condition: road users must not pay higher toll fares.
22-06-2026
Tolls Are Here To Stay. Minister Explains The Mind-Boggling Financial Nightmare Of Abolishing Them Completely
Works Minister Datuk Seri Alexander Nanta Linggi explains why abolishing tolls would cause a multi-billion ringgit financial nightmare for Malaysia, shifting crucial infrastructure funds away from schools and hospitals.
22-06-2026
500k Cars In Just 8 Months?! Leapmotor Has Conquered 40 Countries And Now They're Assembling In M'sia
Leapmotor hits a historic global milestone of 1.5 million vehicle deliveries, adding a stunning 500k sales in just 8 months. See how this 40-country EV giant is scaling up local CKD assembly lines in Gurun, Kedah.
22-06-2026
42 Clauses Are Changing: M'sia Is Facing Its Biggest Road Law Overhaul Since 2020, And Yes, It Affects Your Saman
Malaysia is introducing 42 new clauses to the Road Transport Act in its biggest traffic law overhaul since 2020. Here is how it affects your fines and roadblocks.
19-06-2026
Good News For 5 Million Perodua Owners! Don't Go To Outside Workshops As Service Prices Just Dropped
Thinking of visiting an outside mechanic? Perodua is slashing overall service maintenance parts and labor costs by 10% nationwide starting 19 June.
18-06-2026
It’s Happening! After Years Of Delays, The LRT3 Is Finally Ready To Start Operations
The long-awaited LRT3 Shah Alam Line is officially set to begin operations by the end of this month, as confirmed by Transport Minister Anthony Loke.
18-06-2026
No More Just 'Screwing Parts Together', Malaysia Wants Local Talents To Design The Next Big ASEAN Car Tech
At KLIMS 2026, Deputy Transport Minister Datuk Hasbi Habibollah urged Malaysia's automotive industry to evolve from car assemblers into technology creators.
18-06-2026
Show More
trending_flat