ECRL Project Hits 87% Completion by August 2025 – MoT


The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.
The East Coast Rail Link (ECRL) project spanning Kelantan, Terengganu, Pahang, and Selangor has recorded an overall completion of 87% as of August this year, said Transport Minister Anthony Loke.
As reported by Bernama, the minister said the project segment in Terengganu is among the fastest to be completed, as land issues were resolved earlier, coupled with its overall flat geographical terrain, thus possessing fewer construction challenges.

Transport Minister YB Anthony Loke
“In Terengganu, track works are almost completed. The only sections yet to be finished are from Bentong to Gombak, particularly the Genting tunnel up to Gombak, which is the most challenging segment,” Loke told reporters after officiating the BAS.MY Kuala Terengganu Service Transformation Programme yesterday.


That said, the minister continued that progress in both Kelantan and Terengganu remains on track, as most of the major construction works there have been completed. However, he revealed that incidents of cable theft in Pahang have disrupted the work progress in the state.
“More than a kilometre of cables was stolen, which created problems for the developer. They now have to review their approach to accelerate progress.
“I have already discussed this with the Home Ministry and the police. More aggressive action is needed, including enforcing stricter laws to curb this issue,” Loke added.
Apart from causing delays and heavy losses, the minister also pointed out that cable thefts pose high risks to public safety.

Back to the ECRL project, the first phase from Kota Bharu to Gombak is scheduled for completion in December 2026, with first testing and certification set to take place earlier in June 2026. Meanwhile, the second phase, from Gombak to Port Klang, is scheduled to be completed later in December 2027, with the full operations expected to begin in Jan 2028.
Source: Bernama
Gallery
Written By
Mukhlis Azman
An avid two-wheeler that writes and talks about four-wheelers for a living, while dreaming of an urban transit-laden Malaysia. @mukhlisazman
JPJ Running Numbers
KUALA LUMPUR
VQL5224
SELANGOR
BSM4270
JOHOR
JYR3491
PULAU PINANG
PRY5642
PERAK
APF1816
PAHANG
CFF2625
KEDAH
KGE3162
NEGERI SEMBILAN
NEJ4961
KOTA KINABALU
SJQ2513
KUCHING
QAB2250N
Last updated 11 Feb, 2026
Fuel Price
Petrol
RON 95
RM 2.54
+0.02
RON 97
RM 3.10
+0.02
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.88
+0.04
EURO 5 B7
RM 3.08
+0.04
Last updated 22 Jan, 2026
Related News
ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses
The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.
14-10-2025
ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO
MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.
24-06-2025
ECRL Is More Than 60% Complete - Malaysia Rail
ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.
25-03-2024
ECRL Project Progress Surpasses 56% - Loke
ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.
11-12-2023
ECRL Kelantan Expected To Be Completed Six Months Earlier
The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.
26-06-2023
"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke
The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.
12-04-2023
ECRL Project In Terengganu Reaches 55% Progress
The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.
05-04-2023
ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%
ECRL project's Kuantan Tunnel will be completed by the end of April.
08-03-2023
Latest News
GWM Wey G9 Receives 800 Bookings Within First Week of Launch
The new GWM Wey G9 MPV has received over 800 bookings within the first week of its Malaysian debut.
11-02-2026
Kuantan Welcomes ECRL’s First Trains Ahead of 2027 Operations
The first ECRL electric passenger trains and freight locomotives have arrived in Kuantan as the project moves closer to operations in 2027.
11-02-2026
Jan 2026 Auto Sales Down 30%, xEV Penetration Holds at 12.4%
New vehicle registrations fell to 67,995 units in Jan, a seasonal pullback from Dec’s delivery-driven surge.
11-02-2026
Honda Malaysia Eyes 60,000 Sales, Confirms Six New Models For 2026 Too
Honda Malaysia lays out target to shift up to 60,000 units, buoyed by the introduction of six new models too.
10-02-2026
KPDN Plans Tighter Controls on RON95 Misuse
KPDN is reviewing legislative changes to prevent fraud and ensure subsidised RON95 benefits only eligible Malaysians.
10-02-2026
Putrajaya Pulls Plug on ART Plans Due to High Costs
Putrajaya has dropped plans for a trackless ART tram after the RM212 million project was found to be too costly.
10-02-2026
LLM Expects 3.27 Million Vehicles This CNY
Traffic on major highways is expected to surge as early as Friday, with peak congestion during the first two days of Chinese New Year.
09-02-2026
Toyo Tires Launches New Proxes Comfort In Malaysia – From RM279 Onwards
Toyo Tires launches all-new andf EV-ready Proxes Comfort tyres promising enhanced comforts priced from RM279 onwards.
09-02-2026
Show More
trending_flat