ECRL: Phase 1 Testing & Certification Will Begin in June 2026

Mukhlis Azman

Share via

thumb-ECRL-Testing.jpg

The testing and certification phase for the ECRL Phase 1 from Kota Bharu to Gombak will begin in June 2026.

The testing and certification phase for the East Coast Rail Link (ECRL) Phase 1 project from Kota Bharu, Kelantan, to Gombak, Selangor, will begin in June 2026, according to Malaysia Rail Link (MRL) CEO Datuk Seri Darwis Abdul Razak.

Speaking to Bernama, the CEO explained that the testing process will be conducted to ensure the system is fully operational before the official launch date of the Phase 1 ECRL, which is set to take place in Jan 2027. Adding to that, Datuk Seri Darwis also said that the first set of 11 six-carriage Electric Multiple Unit (EMU) trains for passenger service is expected to arrive by year-end, along with the first 12 electric locomotives for freight service.

476250072_1163854502410103_838206193011837866_n.jpg

MRL CEO Datuk Seri Darwis Abdul Razak & Second Finance Minister YB Senator Datuk Seri Amir Hamzah Azizan

“The first EMU trains and locomotives are expected by November or December, with the remaining units arriving in stages next year,” he said after the launch of the Sustainable Development Goals (SDG) Sukuk Impact Report for the ECRL project, which was officiated by the Second Finance Minister Datuk Seri Amir Hamzah Azizan yesterday.

ECRL-KotaBharu-Tunjong-(1).jpgECRL-KotaBharu-Tunjong-(2).jpg

Darwis also revealed that all track installation works for the ECRL in Kelantan, Terengganu, and Pahang are set for completion by the end of the year. Meanwhile, an estimated 14.3 KM of excavation for the Genting Tunnel has been completed, with full tunnel penetration expected by May this year.

“The 400 KM track from Maran, Pahang, to Kota Bharu was completed on Jan 15. Installation works for the 100 KM stretch from Maran to Bentong will begin in April and be completed in three months,” the CEO added.

Finally, Datuk Seri Darwis has also confirmed that the overall progress of the ECRL project covering Kelantan, Terengganu, Pahang, and Selangor has reached 78.5% as of last month.

Source: Bernama


Gallery

Share This Article

Written By

Mukhlis Azman

An avid two-wheeler that writes and talks about four-wheelers for a living, while dreaming of an urban transit-laden Malaysia. @mukhlisazman

Share via

JPJ Running Numbers

KUALA LUMPUR

VPM5604

SELANGOR

BSG7745

JOHOR

JYE5042

PULAU PINANG

PRT1080

PERAK

ANY7246

PAHANG

CFD721

KEDAH

KGB6454

NEGERI SEMBILAN

NEG6404

KOTA KINABALU

SJL9999*

KUCHING

QAB8459L

Last updated 05 Aug, 2025

Fuel Price

Petrol

RON 95

RM 2.05

RON 97

RM 3.17

-0.04

RON 100

RM 5.00

VPR

RM 6.23

Diesel

EURO 5 B10

RM 2.91

EURO 5 B7

RM 3.11

Last updated 31 Jul, 2025

Related News

Auto News
Anwar: 13MP Pushes for Improved Connectivity – Better Buses, Trains and Roads

Anwar: 13MP Pushes for Improved Connectivity – Better Buses, Trains and Roads

The 13th Malaysia Plan focuses on better connectivity through buses, trains, roads, and smarter planning.

Auto News
ECRL Extension from Kota Bharu to Pasir Mas Under Review

ECRL Extension from Kota Bharu to Pasir Mas Under Review

Kelantan is pushing for the ECRL to extend to Rantau Panjang, eyeing cross-border rail links with Thailand.

23-07-2025
Auto News
ECRL Set To Receive First Two EMU Trains, E-Locos By Year-End

ECRL Set To Receive First Two EMU Trains, E-Locos By Year-End

ECRL is expected to receive its first two EMU trains and two E-Loco by the end of this year.

16-07-2025
Auto News
ECRL Breakthrough: Genting Tunnel Becomes SEA’s Longest Rail Tunnel

ECRL Breakthrough: Genting Tunnel Becomes SEA’s Longest Rail Tunnel

The 16.39KM Genting Tunnel is now Southeast Asia’s longest rail tunnel, marking a major leap for ECRL.

Auto News
Kuantan-Bound KL-Karak Lanes Diverted For ECRL Work Until Aug 31

Kuantan-Bound KL-Karak Lanes Diverted For ECRL Work Until Aug 31

Kuantan-bound lanes (KM25.75–KM26.39) are being diverted for ECRL works until Aug 31.

10-07-2025
Auto News
ECRL Project 85% Completed

ECRL Project 85% Completed

The ECRL is 85% complete and on track to start operations by early 2027, says Chief Secretary.

09-07-2025
Auto News
RM300K Lost To Cable Thefts At Terengganu ECRL Sites

RM300K Lost To Cable Thefts At Terengganu ECRL Sites

Police recorded 22 theft-related cases at Terengganu ECRL sites, costing an estimated RM300,000 in losses.

25-06-2025
Auto News
ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.

24-06-2025

Latest News

Auto News
KPDN Probes SG Driver Sighted Pumping RON95 in Johor

KPDN Probes SG Driver Sighted Pumping RON95 in Johor

KPDN is probing a viral incident where a Singapore-registered car was seen pumping subsidised RON95 fuel.

Auto News
Traffic Diversion On Bukit Gambir-Tangkak From Aug 5

Traffic Diversion On Bukit Gambir-Tangkak From Aug 5

Traffic along the NSE near Tangkak will be diverted in both directions from Aug 5 for bridge construction.

04-08-2025
Auto News
1,489 Summonses Issued in VEP Enforcement Operation – JPJ

1,489 Summonses Issued in VEP Enforcement Operation – JPJ

JPJ has issued a total of 1,489 summonses during an enforcement operation on VEP at the JB-Singapore land border.

04-08-2025
Auto News
No Green Light Yet For Cross-Border Ride-Hailing Between SG, JB.

No Green Light Yet For Cross-Border Ride-Hailing Between SG, JB.

Singapore holds off on cross-border ride-hailing plans, opting instead to improve its existing taxi scheme with Malaysia.

04-08-2025
Auto News
RM110 Million Collected from Special Plate Sales Since 2023 – MoT

RM110 Million Collected from Special Plate Sales Since 2023 – MoT

A total of RM110 million has been collected from sales of special number plates since 2023, the Transport Ministry says.

04-08-2025
Auto News
Nanta: 80% of Accidents Driver-Linked, Road Budget 70% Short

Nanta: 80% of Accidents Driver-Linked, Road Budget 70% Short

With 80% of accidents linked to drivers, the Works Ministry still grapples with limited funds to fix and rebuild roads.

Auto News
LRT3 Shah Alam Line Opening Could Be Delayed to Oct 31 – Report

LRT3 Shah Alam Line Opening Could Be Delayed to Oct 31 – Report

The LRT3 Shah Alam line opening could be delayed until Oct 31 instead of the planned launch date of Sept 30.

04-08-2025
Auto News
ETS to JB Sentral ‘On Track’, But Not Quite There Yet

ETS to JB Sentral ‘On Track’, But Not Quite There Yet

KTMB says electrification works between Kluang to JB Sentral are ongoing and the extension will proceed once conditions are met.