ECRL: Phase 1 Testing & Certification Will Begin in June 2026
The testing and certification phase for the ECRL Phase 1 from Kota Bharu to Gombak will begin in June 2026.
The testing and certification phase for the East Coast Rail Link (ECRL) Phase 1 project from Kota Bharu, Kelantan, to Gombak, Selangor, will begin in June 2026, according to Malaysia Rail Link (MRL) CEO Datuk Seri Darwis Abdul Razak.
Speaking to Bernama, the CEO explained that the testing process will be conducted to ensure the system is fully operational before the official launch date of the Phase 1 ECRL, which is set to take place in Jan 2027. Adding to that, Datuk Seri Darwis also said that the first set of 11 six-carriage Electric Multiple Unit (EMU) trains for passenger service is expected to arrive by year-end, along with the first 12 electric locomotives for freight service.
MRL CEO Datuk Seri Darwis Abdul Razak & Second Finance Minister YB Senator Datuk Seri Amir Hamzah Azizan
“The first EMU trains and locomotives are expected by November or December, with the remaining units arriving in stages next year,” he said after the launch of the Sustainable Development Goals (SDG) Sukuk Impact Report for the ECRL project, which was officiated by the Second Finance Minister Datuk Seri Amir Hamzah Azizan yesterday.
Darwis also revealed that all track installation works for the ECRL in Kelantan, Terengganu, and Pahang are set for completion by the end of the year. Meanwhile, an estimated 14.3 KM of excavation for the Genting Tunnel has been completed, with full tunnel penetration expected by May this year.
“The 400 KM track from Maran, Pahang, to Kota Bharu was completed on Jan 15. Installation works for the 100 KM stretch from Maran to Bentong will begin in April and be completed in three months,” the CEO added.
Finally, Datuk Seri Darwis has also confirmed that the overall progress of the ECRL project covering Kelantan, Terengganu, Pahang, and Selangor has reached 78.5% as of last month.
Source: Bernama
Gallery








Written By
Mukhlis Azman
An avid two-wheeler that writes and talks about four-wheelers for a living, while dreaming of an urban transit-laden Malaysia. @mukhlisazman
JPJ Running Numbers
KUALA LUMPUR
VPG4347
SELANGOR
BSF5076
JOHOR
JYA5080
PULAU PINANG
PRR4984
PERAK
ANW6804
PAHANG
CFC1457
KEDAH
KGA9451
NEGERI SEMBILAN
NEG2394
KOTA KINABALU
SJL3102
KUCHING
QAB5152L
Last updated 18 Jun, 2025
Fuel Price
Petrol
RON 95
RM 2.05
RON 97
RM 3.07
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.74
EURO 5 B7
RM 2.94
Last updated 12 Jun, 2025
Related News
ECRL: KotaSAS Station System Installation Completed
KotaSAS Station becomes first along ECRL route to complete installation of critical systems.
30-05-2025
MiTRANS: ECRL-Sungai Golok Link Key to Regional Rail
MiTRANS: Extending the ECRL to Sungai Golok would complete a key missing link in the ASEAN rail network.
22-05-2025
Thai Ambassador Proposes ECRL Extension To Sungai Golok
Thai Ambassador Lada Phumas suggested extending the ECRL to Sungai Golok for better rail links.
16-05-2025
ECRL Hits 82% Completion, Promises 1,800 Jobs - 80% For Locals
ECRL, Malaysia’s largest rail project is nearing completion, with passenger service set to begin by Jan 2027.
06-05-2025
ECRL to Boost East Coast Growth, Strengthen Malaysia-China Ties
The ECRL project is set to unlock new growth for Malaysia’s east coast and strengthen links with China.
29-04-2025
ECRL Railway Construction Along Kota Bharu-Selangor Over 80% Complete
ECRL project along Kota Bharu-Selangor alignment is over 81% complete and remains on track for completion in Dec 2026.
18-04-2025
ECRL Concludes 38 Tunnel Excavations Ahead Of Schedule
MRL announces the completion of excavation work for 38 tunnels along the ECRL rail line.
09-04-2025
ECRL 80% Complete, Shifting To Above-Ground Work
The ECRL project, which is nearing 80% completion, is transitioning from the underground construction phase to above-ground work.
27-03-2025
Latest News
Amir Hamzah: RON95 Subsidy Coming Reform Before 2026 Carbon Tax
RON95 petrol subsidies to be rationalised ahead of 2026 carbon tax rollout, comes as part of Malaysia’s energy transition.
17-06-2025
Malaysian Single-Mom Truckers Make Local Headlines
In a male-dominated industry, 39-year-old Irzunika Idris and 40-year-old Marlia Ramli became truck drivers to support their kids.
17-06-2025
Rapid KL On-Demand Adds 5 New Zones — Cyberjaya & Putrajaya Included
The Rapid KL On-Demand service has been expanded to five new zones, including Cyberjaya and Putrajaya.
17-06-2025
PRO-NET Opens Three New Proton e.MAS & smart Dealerships
PRO-NET has expanded both its Proton e.MAS and smart dealer network by opening three new outlets in Malaysia.
17-06-2025
FT Dept, JPJ Told To Deal With Abandoned Vehicles
FT Dept and JPJ ordered to review and improve laws on abandoned vehicle disposal in KL and Putrajaya.
17-06-2025
Gerik Crash: PSV Licence Suspended, RM1.7M Aid Raised
JPJ suspends Gerik crash bus driver’s PSV licence as investigations rule out technical failure.
17-06-2025
PLUS Opens Three New Lanes At Rawang Selatan Toll Plaza
PLUS has announced the addition of three new lanes at the Rawang Selatan toll plaza (Exit 115).
16-06-2025
RON95 Petrol Subsidy Rationalisation Will Proceed – PMX
The government will proceed with the RON95 fuel subsidy rationalisation, says Prime Minister Anwar Ibrahim.
16-06-2025
Show More
trending_flat