ECRL: Phase 1 Testing & Certification Will Begin in June 2026
![]()
The testing and certification phase for the ECRL Phase 1 from Kota Bharu to Gombak will begin in June 2026.
The testing and certification phase for the East Coast Rail Link (ECRL) Phase 1 project from Kota Bharu, Kelantan, to Gombak, Selangor, will begin in June 2026, according to Malaysia Rail Link (MRL) CEO Datuk Seri Darwis Abdul Razak.
Speaking to Bernama, the CEO explained that the testing process will be conducted to ensure the system is fully operational before the official launch date of the Phase 1 ECRL, which is set to take place in Jan 2027. Adding to that, Datuk Seri Darwis also said that the first set of 11 six-carriage Electric Multiple Unit (EMU) trains for passenger service is expected to arrive by year-end, along with the first 12 electric locomotives for freight service.

MRL CEO Datuk Seri Darwis Abdul Razak & Second Finance Minister YB Senator Datuk Seri Amir Hamzah Azizan
“The first EMU trains and locomotives are expected by November or December, with the remaining units arriving in stages next year,” he said after the launch of the Sustainable Development Goals (SDG) Sukuk Impact Report for the ECRL project, which was officiated by the Second Finance Minister Datuk Seri Amir Hamzah Azizan yesterday.
-full.jpg)
-full.jpg)
Darwis also revealed that all track installation works for the ECRL in Kelantan, Terengganu, and Pahang are set for completion by the end of the year. Meanwhile, an estimated 14.3 KM of excavation for the Genting Tunnel has been completed, with full tunnel penetration expected by May this year.
“The 400 KM track from Maran, Pahang, to Kota Bharu was completed on Jan 15. Installation works for the 100 KM stretch from Maran to Bentong will begin in April and be completed in three months,” the CEO added.
Finally, Datuk Seri Darwis has also confirmed that the overall progress of the ECRL project covering Kelantan, Terengganu, Pahang, and Selangor has reached 78.5% as of last month.
Source: Bernama
Gallery
Written By
Mukhlis Azman
An avid two-wheeler that writes and talks about four-wheelers for a living, while dreaming of an urban transit-laden Malaysia. @mukhlisazman
JPJ Running Numbers
KUALA LUMPUR
VQR5543
SELANGOR
BSN5529
JOHOR
JYT6261
PULAU PINANG
PSA7961
PERAK
APG2359
PAHANG
CFF9175
KEDAH
KGE9038
NEGERI SEMBILAN
NEJ8524
KOTA KINABALU
SJR351
KUCHING
QAB4536N
Last updated 29 Mar, 2026
Fuel Price
Petrol
RON 95
RM 2.59
+0.05
RON 97
RM 3.15
+0.05
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.04
+0.05
EURO 5 B7
RM 3.24
+0.05
Last updated 26 Feb, 2026
Related News
Kuantan Welcomes ECRL’s First Trains Ahead of 2027 Operations
The first ECRL electric passenger trains and freight locomotives have arrived in Kuantan as the project moves closer to operations in 2027.
11-02-2026
ECRL Fares To Be Announced Ahead of 2027 Launch
ECRL fares will be disclosed several months prior to the commencement of operations in January 2027, according to Transport Minister.
30-01-2026
ECRL Launch Hinges On System Integration, Jan 2027 Target Maintained
The ECRL remains on schedule, with system integration and testing now the key focus ahead of its planned Jan 2027 launch.
29-01-2026
ECRL First EMU Trains, E-Locos Head To Malaysia For Testing
Malaysia’s East Coast Rail Link gears up as its first EMUs and electric locomotives arrive for testing and future service.
17-12-2025
First ECRL Trains Depart China, Remaining Units Arriving Through 2026
First ECRL trains depart China, with remaining units scheduled to arrive through 2026.
28-11-2025
ECRL Nears Completion with 89% Progress, Operations Set for 2027
ECRL is on track to begin services from Kota Bharu to Gombak in Jan 2027, as construction progress hits 89%.
24-11-2025
ECRL Trains Fully Assembled, Ready for Malaysia
The first batch of trains for the East Coast Rail Link (ECRL) is now ready in Dalian, China.
21-11-2025
ECRL Hits 88% Milestone As Key C1B Stretch Completed
The ECRL project has hit 88% completion with the C1B Segment now successfully completed.
05-11-2025
Latest News
Motorcyclist Dies After Being Hit by Speeding Car in Klang
Tragic fatal crash in Klang: A motorcyclist was killed on the spot after a car allegedly speeding and overtaking on a double yellow line struck him on Jalan Bunga Raya Barat behind MBDK on 29 March 2026.
29-03-2026
The RM5,000 Raya Flex: Why Malaysians are Risking a Monthly Salary to Rent an Alphard
Is renting an Alphard for RM5,000 a waste or a genius move? We break down the 'Raya Flex' cost, from RM10k insurance premiums to the 'Executive Lounge' comfort that saves your back on an 18-hour East Coast jam.
27-03-2026
Safe Passage at Hormuz: Why Malaysia’s Special Deal with Iran Won't Lower Your Petrol Price
PM Anwar secured safe passage for Malaysian ships, so why is RON95 hitting RM3.87/L? We decode the 400% insurance surge and the new 200L BUDI95 quota.
27-03-2026
Fuel Subsidy Update: Your 300L Monthly Quota Could Drop to 200L This April
If you rely on subsidised RON95 petrol to get to work, take note: a major change is coming to your monthly fuel budget.
26-03-2026
Fuel Price Shock: Diesel Spikes to RM5.52, Unsubsidised RON95 Jumps 60 Sen
Massive 80-sen spike for Diesel (RM5.52) and 60-sen jump for unsubsidised RON95 (RM3.87). Learn how the Budi Madani RM300 aid and BUDI95 quota protect Malaysian drivers this week.
26-03-2026
Strait of Hormuz to Malaysia: Why We’re Paying for a War 6,000km Away
Why is RON97 at RM4.55/L? We decode the Strait of Hormuz conflict, the May 2026 subsidy deadline, and why Malaysia imports oil despite being a producer.
19-03-2026
From 82 Minutes to 8: How the Mutiara Line is Giving Penangites Their Time Back
Is the 80-minute Penang Bridge crawl finally ending? The Mutiara Line LRT links Butterworth to Komtar in just 8 minutes. Get the latest 2026 project updates, station lists, and more.
17-03-2026
The 2026 Proton X90 Buyer’s Warning: 5 Critical Safety Features You Are No Longer Getting
ASEAN NCAP revokes Proton X90’s 5-star rating. The 2026 facelift is downgraded to 1-star after stripping critical ADAS features. Is your family safe? Get the full safety specs here.
16-03-2026
Show More
trending_flat