ECRL Project Hits 87% Completion by August 2025 – MoT

Mukhlis Azman

Share via

ecrl-genting-.jpgph06-19062024-ecrl_4279690_20240619165601.jpg

The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.

The East Coast Rail Link (ECRL) project spanning Kelantan, Terengganu, Pahang, and Selangor has recorded an overall completion of 87% as of August this year, said Transport Minister Anthony Loke.

As reported by Bernama, the minister said the project segment in Terengganu is among the fastest to be completed, as land issues were resolved earlier, coupled with its overall flat geographical terrain, thus possessing fewer construction challenges.

548195012_1374359560713294_6709422170773546027_n.jpg

Transport Minister YB Anthony Loke

“In Terengganu, track works are almost completed. The only sections yet to be finished are from Bentong to Gombak, particularly the Genting tunnel up to Gombak, which is the most challenging segment,” Loke told reporters after officiating the BAS.MY Kuala Terengganu Service Transformation Programme yesterday.

ECRL_PASIR_PUTEH_1755593670.jpgECRL_Paka_tunnel7_09042021.jpg

That said, the minister continued that progress in both Kelantan and Terengganu remains on track, as most of the major construction works there have been completed. However, he revealed that incidents of cable theft in Pahang have disrupted the work progress in the state.

“More than a kilometre of cables was stolen, which created problems for the developer. They now have to review their approach to accelerate progress.

“I have already discussed this with the Home Ministry and the police. More aggressive action is needed, including enforcing stricter laws to curb this issue,” Loke added.

Apart from causing delays and heavy losses, the minister also pointed out that cable thefts pose high risks to public safety.

ECRL-Map.jpg

Back to the ECRL project, the first phase from Kota Bharu to Gombak is scheduled for completion in December 2026, with first testing and certification set to take place earlier in June 2026. Meanwhile, the second phase, from Gombak to Port Klang, is scheduled to be completed later in December 2027, with the full operations expected to begin in Jan 2028.

Source: Bernama


Gallery

Share This Article

Written By

Mukhlis Azman

An avid two-wheeler that writes and talks about four-wheelers for a living, while dreaming of an urban transit-laden Malaysia. @mukhlisazman

Share via

JPJ Running Numbers

KUALA LUMPUR

VPS9429

SELANGOR

BSH9196

JOHOR

JYH547

PULAU PINANG

PRU2331

PERAK

APB3335

PAHANG

CFD5277

KEDAH

KGC3540

NEGERI SEMBILAN

NEH1677

KOTA KINABALU

SJM6903

KUCHING

QAB2009M

Last updated 24 Sep, 2025

Fuel Price

Petrol

RON 95

RM 2.05

RON 97

RM 3.21

+0.03

RON 100

RM 5.00

VPR

RM 6.23

Diesel

EURO 5 B10

RM 2.93

+0.03

EURO 5 B7

RM 3.13

+0.03

Last updated 18 Sep, 2025

Related News

Auto News
ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.

24-06-2025
Auto News
ECRL Is More Than 60% Complete - Malaysia Rail

ECRL Is More Than 60% Complete - Malaysia Rail

ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.

25-03-2024
Auto News
ECRL Project Progress Surpasses 56% - Loke

ECRL Project Progress Surpasses 56% - Loke

ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.

11-12-2023
Auto News
ECRL Kelantan Expected To Be Completed Six Months Earlier

ECRL Kelantan Expected To Be Completed Six Months Earlier

The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.

26-06-2023
Auto News
"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.

12-04-2023
Auto News
ECRL Project In Terengganu Reaches 55% Progress

ECRL Project In Terengganu Reaches 55% Progress

The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.

05-04-2023
Auto News
ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

ECRL project's Kuantan Tunnel will be completed by the end of April.

08-03-2023
Auto News
ECRL Land-Clearing; Enforcement Due To SOP Breach - Selangor MB’s Aide

ECRL Land-Clearing; Enforcement Due To SOP Breach - Selangor MB’s Aide

Selangor Forestry Department found that the alleged land clearing activities in the Selangor State Park are part of the ECRL project.

06-02-2023

Latest News

Auto News
Amir Hamzah: No Daily Refuel Limits Under Budi95 For Now

Amir Hamzah: No Daily Refuel Limits Under Budi95 For Now

Amir Hamzah: No limit on daily refuels, data analytics to monitor RM1.99 subsidy use to detect abuse.

Auto News
New RM22.7M JPJ Kajang Office Set for 2027

New RM22.7M JPJ Kajang Office Set for 2027

The new RM22.7M JPJ Kajang office will feature modern facilities and improved services for the public by 2027.

23-09-2025
Auto News
ECRL Project Hits 87% Completion by August 2025 – MoT

ECRL Project Hits 87% Completion by August 2025 – MoT

The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.

23-09-2025
Auto News
Amir Hamzah: No Back-to-Back Pumping of RM1.99 RON95 A Day

Amir Hamzah: No Back-to-Back Pumping of RM1.99 RON95 A Day

Amir Hamzah: Govt. won't allow multiple subsidised refuels in a day as BUDI95 takes effect Sept 30.

Auto News
Petron Lubricants Gains SIRIM Certification & Label

Petron Lubricants Gains SIRIM Certification & Label

Petron Malaysia acquires SIRIM genuine product licence certification and label for engine lubricant product line-up.

23-09-2025
Auto News
Govt Will Allow Commercial RV Rentals from 2026 - Loke

Govt Will Allow Commercial RV Rentals from 2026 - Loke

Starting January 2026, RVs can be licensed for commercial use, making self-drive RV holidays safer and regulated.

23-09-2025
Auto News
BUDI95: RON95 Ban on Foreign Cars Still On, RM1.99 for Malaysians

BUDI95: RON95 Ban on Foreign Cars Still On, RM1.99 for Malaysians

BUDI95 keeps foreign-registered cars out of subsidised RON95, only Malaysians with local vehicles can pump at RM1.99 per litre.

Auto News
Rapid Rail Set To Launch Real-Time Crowd Tracking & AI Security

Rapid Rail Set To Launch Real-Time Crowd Tracking & AI Security

Rapid Rail will introduce a live tracker showing coach crowd levels so commuters can board with less stress.

23-09-2025

Show More

trending_flat
Carz Automedia Malaysia Logo
About Us

CarzAutoMedia: Stay connected to the latest car news! Get instant updates on new releases, industry trends, and automotive innovations. Your go-to source for 24/7 coverage of everything automotive.

© 2025 CariCarz.com. All Rights Reserved.