The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.

The East Coast Rail Link (ECRL) project spanning Kelantan, Terengganu, Pahang, and Selangor has recorded an overall completion of 87% as of August this year, said Transport Minister Anthony Loke.

As reported by Bernama, the minister said the project segment in Terengganu is among the fastest to be completed, as land issues were resolved earlier, coupled with its overall flat geographical terrain, thus possessing fewer construction challenges.

548195012_1374359560713294_6709422170773546027_n.jpg

Transport Minister YB Anthony Loke

“In Terengganu, track works are almost completed. The only sections yet to be finished are from Bentong to Gombak, particularly the Genting tunnel up to Gombak, which is the most challenging segment,” Loke told reporters after officiating the BAS.MY Kuala Terengganu Service Transformation Programme yesterday.

ECRL_PASIR_PUTEH_1755593670.jpgECRL_Paka_tunnel7_09042021.jpg

That said, the minister continued that progress in both Kelantan and Terengganu remains on track, as most of the major construction works there have been completed. However, he revealed that incidents of cable theft in Pahang have disrupted the work progress in the state.

“More than a kilometre of cables was stolen, which created problems for the developer. They now have to review their approach to accelerate progress.

“I have already discussed this with the Home Ministry and the police. More aggressive action is needed, including enforcing stricter laws to curb this issue,” Loke added.

Apart from causing delays and heavy losses, the minister also pointed out that cable thefts pose high risks to public safety.

ECRL-Map.jpg

Back to the ECRL project, the first phase from Kota Bharu to Gombak is scheduled for completion in December 2026, with first testing and certification set to take place earlier in June 2026. Meanwhile, the second phase, from Gombak to Port Klang, is scheduled to be completed later in December 2027, with the full operations expected to begin in Jan 2028.

Source: Bernama


Gallery

Share This Article

Written By

Mukhlis Azman

An avid two-wheeler that writes and talks about four-wheelers for a living, while dreaming of an urban transit-laden Malaysia. @mukhlisazman

Share via

JPJ Running Numbers

KUALA LUMPUR

VQL5224

SELANGOR

BSM4270

JOHOR

JYR3491

PULAU PINANG

PRY5642

PERAK

APF1816

PAHANG

CFF2625

KEDAH

KGE3162

NEGERI SEMBILAN

NEJ4961

KOTA KINABALU

SJQ2513

KUCHING

QAB2250N

Last updated 11 Feb, 2026

Fuel Price

Petrol

RON 95

RM 2.54

+0.02

RON 97

RM 3.10

+0.02

RON 100

RM 5.00

VPR

RM 6.23

Diesel

EURO 5 B10

RM 2.88

+0.04

EURO 5 B7

RM 3.08

+0.04

Last updated 22 Jan, 2026

Related News

Auto News
ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses

ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses

The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.

14-10-2025
Auto News
ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.

24-06-2025
Auto News
ECRL Is More Than 60% Complete - Malaysia Rail

ECRL Is More Than 60% Complete - Malaysia Rail

ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.

25-03-2024
Auto News
ECRL Project Progress Surpasses 56% - Loke

ECRL Project Progress Surpasses 56% - Loke

ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.

11-12-2023
Auto News
ECRL Kelantan Expected To Be Completed Six Months Earlier

ECRL Kelantan Expected To Be Completed Six Months Earlier

The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.

26-06-2023
Auto News
"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.

12-04-2023
Auto News
ECRL Project In Terengganu Reaches 55% Progress

ECRL Project In Terengganu Reaches 55% Progress

The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.

05-04-2023
Auto News
ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

ECRL project's Kuantan Tunnel will be completed by the end of April.

08-03-2023

Latest News

Auto News
Kuantan Welcomes ECRL’s First Trains Ahead of 2027 Operations

Kuantan Welcomes ECRL’s First Trains Ahead of 2027 Operations

The first ECRL electric passenger trains and freight locomotives have arrived in Kuantan as the project moves closer to operations in 2027.

11-02-2026
Auto News
Jan 2026 Auto Sales Down 30%, xEV Penetration Holds at 12.4%

Jan 2026 Auto Sales Down 30%, xEV Penetration Holds at 12.4%

New vehicle registrations fell to 67,995 units in Jan, a seasonal pullback from Dec’s delivery-driven surge.

Auto News
Honda Malaysia Eyes 60,000 Sales, Confirms Six New Models For 2026 Too

Honda Malaysia Eyes 60,000 Sales, Confirms Six New Models For 2026 Too

Honda Malaysia lays out target to shift up to 60,000 units, buoyed by the introduction of six new models too.

10-02-2026
Auto News
KPDN Plans Tighter Controls on RON95 Misuse

KPDN Plans Tighter Controls on RON95 Misuse

KPDN is reviewing legislative changes to prevent fraud and ensure subsidised RON95 benefits only eligible Malaysians.

Auto News
Putrajaya Pulls Plug on ART Plans Due to High Costs

Putrajaya Pulls Plug on ART Plans Due to High Costs

Putrajaya has dropped plans for a trackless ART tram after the RM212 million project was found to be too costly.

Auto News
LLM Expects 3.27 Million Vehicles This CNY

LLM Expects 3.27 Million Vehicles This CNY

Traffic on major highways is expected to surge as early as Friday, with peak congestion during the first two days of Chinese New Year.

09-02-2026
Auto News
Toyo Tires Launches New Proxes Comfort In Malaysia – From RM279 Onwards

Toyo Tires Launches New Proxes Comfort In Malaysia – From RM279 Onwards

Toyo Tires launches all-new andf EV-ready Proxes Comfort tyres promising enhanced comforts priced from RM279 onwards.

09-02-2026
Auto News
Chery Malaysia “Cherish the Nature” Mangrove Restoration Project

Chery Malaysia “Cherish the Nature” Mangrove Restoration Project

Chery Malaysia launches “Cherish the Nature”, an 18-month project restoring mangroves along the NCSC.

Show More

trending_flat
Carz Automedia Malaysia Logo
About Us

CarzAutoMedia: Stay connected to the latest car news! Get instant updates on new releases, industry trends, and automotive innovations. Your go-to source for 24/7 coverage of everything automotive.

© 2026 CariCarz.com. All Rights Reserved.