ECRL Project Hits 87% Completion by August 2025 – MoT


The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.
The East Coast Rail Link (ECRL) project spanning Kelantan, Terengganu, Pahang, and Selangor has recorded an overall completion of 87% as of August this year, said Transport Minister Anthony Loke.
As reported by Bernama, the minister said the project segment in Terengganu is among the fastest to be completed, as land issues were resolved earlier, coupled with its overall flat geographical terrain, thus possessing fewer construction challenges.

Transport Minister YB Anthony Loke
“In Terengganu, track works are almost completed. The only sections yet to be finished are from Bentong to Gombak, particularly the Genting tunnel up to Gombak, which is the most challenging segment,” Loke told reporters after officiating the BAS.MY Kuala Terengganu Service Transformation Programme yesterday.


That said, the minister continued that progress in both Kelantan and Terengganu remains on track, as most of the major construction works there have been completed. However, he revealed that incidents of cable theft in Pahang have disrupted the work progress in the state.
“More than a kilometre of cables was stolen, which created problems for the developer. They now have to review their approach to accelerate progress.
“I have already discussed this with the Home Ministry and the police. More aggressive action is needed, including enforcing stricter laws to curb this issue,” Loke added.
Apart from causing delays and heavy losses, the minister also pointed out that cable thefts pose high risks to public safety.

Back to the ECRL project, the first phase from Kota Bharu to Gombak is scheduled for completion in December 2026, with first testing and certification set to take place earlier in June 2026. Meanwhile, the second phase, from Gombak to Port Klang, is scheduled to be completed later in December 2027, with the full operations expected to begin in Jan 2028.
Source: Bernama
Gallery
Written By
Mukhlis Azman
An avid two-wheeler that writes and talks about four-wheelers for a living, while dreaming of an urban transit-laden Malaysia. @mukhlisazman
JPJ Running Numbers
KUALA LUMPUR
VQF3625
SELANGOR
BSL2681
JOHOR
JYN6170
PULAU PINANG
PRX184
PERAK
APD6394
PAHANG
CFE5664
KEDAH
KGD5779
NEGERI SEMBILAN
NEJ1098
KOTA KINABALU
SJP4608
KUCHING
QAB8443M
Last updated 27 Dec, 2025
Fuel Price
Petrol
RON 95
RM 2.64
-0.02
RON 97
RM 3.27
-0.02
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.06
-0.02
EURO 5 B7
RM 3.26
-0.02
Last updated 11 Dec, 2025
Related News
ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses
The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.
14-10-2025
ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO
MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.
24-06-2025
ECRL Is More Than 60% Complete - Malaysia Rail
ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.
25-03-2024
ECRL Project Progress Surpasses 56% - Loke
ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.
11-12-2023
ECRL Kelantan Expected To Be Completed Six Months Earlier
The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.
26-06-2023
"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke
The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.
12-04-2023
ECRL Project In Terengganu Reaches 55% Progress
The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.
05-04-2023
ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%
ECRL project's Kuantan Tunnel will be completed by the end of April.
08-03-2023
Latest News
Ops Lancar: Johor Police Issue Over 4,400 Summonses In Two Days
Johor police issued 4,433 traffic summonses in just the first two days of their Christmas and New Year road operations.
26-12-2025
MOF Extends OMV Relief: CKD Vehicle Prices Safe Until June 2026
MOF confirms that non-manufacturing costs under OMV remain fully excise-exempt for another six-months.
26-12-2025
iCaur V23 Earns 5-Star ASEAN NCAP Rating
Newly launched iCaur V23 EV SUV posts strong 91.02-point score in ASEAN NCAP 2021–2025 protocol crash-tests.
24-12-2025
Chery Tiggo 7 PHEV Earns 5-Star ASEAN NCAP Score
Chery Tiggo 7 PHEV C-SUV earns 5-star ASEAN NCAP rating, posting an impressive 94.68-point score.
24-12-2025
Updated Fuel Prices From 25 To 31 December
The Ministry of Finance (MoF) has announced the retail prices of all fuels in Malaysia, for the coming week of 25 to 31 December, 2025, the rates are as such.
24-12-2025
Malaysian EV Market Buzzing Ahead Of Year-End Tax Changes
EV registrations jump as buyers rush to beat the fully imported tax exemption, with Tesla, BYD, and Proton leading the charge.
24-12-2025
DBKL Deploys Smart Traffic Light System Worth RM42 Million
DBKL deploys and maintains new ITMAX adaptive, data-driven smart traffic light systems across Kuala Lumpur.
24-12-2025
Penang Expects 2.2M Vehicles This Christmas, School Holidays
More than 2.2 million vehicles are expected to enter Penang during the Christmas season and school holidays.
24-12-2025
Show More
trending_flat