ECRL Project Hits 87% Completion by August 2025 – MoT

Mukhlis Azman

Share via

ecrl-genting-.jpgph06-19062024-ecrl_4279690_20240619165601.jpg

The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.

The East Coast Rail Link (ECRL) project spanning Kelantan, Terengganu, Pahang, and Selangor has recorded an overall completion of 87% as of August this year, said Transport Minister Anthony Loke.

As reported by Bernama, the minister said the project segment in Terengganu is among the fastest to be completed, as land issues were resolved earlier, coupled with its overall flat geographical terrain, thus possessing fewer construction challenges.

548195012_1374359560713294_6709422170773546027_n.jpg

Transport Minister YB Anthony Loke

“In Terengganu, track works are almost completed. The only sections yet to be finished are from Bentong to Gombak, particularly the Genting tunnel up to Gombak, which is the most challenging segment,” Loke told reporters after officiating the BAS.MY Kuala Terengganu Service Transformation Programme yesterday.

ECRL_PASIR_PUTEH_1755593670.jpgECRL_Paka_tunnel7_09042021.jpg

That said, the minister continued that progress in both Kelantan and Terengganu remains on track, as most of the major construction works there have been completed. However, he revealed that incidents of cable theft in Pahang have disrupted the work progress in the state.

“More than a kilometre of cables was stolen, which created problems for the developer. They now have to review their approach to accelerate progress.

“I have already discussed this with the Home Ministry and the police. More aggressive action is needed, including enforcing stricter laws to curb this issue,” Loke added.

Apart from causing delays and heavy losses, the minister also pointed out that cable thefts pose high risks to public safety.

ECRL-Map.jpg

Back to the ECRL project, the first phase from Kota Bharu to Gombak is scheduled for completion in December 2026, with first testing and certification set to take place earlier in June 2026. Meanwhile, the second phase, from Gombak to Port Klang, is scheduled to be completed later in December 2027, with the full operations expected to begin in Jan 2028.

Source: Bernama


Gallery

Share This Article

Written By

Mukhlis Azman

An avid two-wheeler that writes and talks about four-wheelers for a living, while dreaming of an urban transit-laden Malaysia. @mukhlisazman

Share via

JPJ Running Numbers

KUALA LUMPUR

VPY4510

SELANGOR

BSJ9884

JOHOR

JYK7349

PULAU PINANG

PRV5220

PERAK

APC3942

PAHANG

CFE793

KEDAH

KGC8984

NEGERI SEMBILAN

NEH5629

KOTA KINABALU

SJN5892

KUCHING

QAB4924M

Last updated 08 Nov, 2025

Fuel Price

Petrol

RON 95

RM 2.60

RON 97

RM 3.20

RON 100

RM 5.00

VPR

RM 6.23

Diesel

EURO 5 B10

RM 3.02

+0.07

EURO 5 B7

RM 3.22

+0.07

Last updated 06 Nov, 2025

Related News

Auto News
ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses

ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses

The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.

14-10-2025
Auto News
ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.

24-06-2025
Auto News
ECRL Is More Than 60% Complete - Malaysia Rail

ECRL Is More Than 60% Complete - Malaysia Rail

ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.

25-03-2024
Auto News
ECRL Project Progress Surpasses 56% - Loke

ECRL Project Progress Surpasses 56% - Loke

ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.

11-12-2023
Auto News
ECRL Kelantan Expected To Be Completed Six Months Earlier

ECRL Kelantan Expected To Be Completed Six Months Earlier

The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.

26-06-2023
Auto News
"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.

12-04-2023
Auto News
ECRL Project In Terengganu Reaches 55% Progress

ECRL Project In Terengganu Reaches 55% Progress

The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.

05-04-2023
Auto News
ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

ECRL project's Kuantan Tunnel will be completed by the end of April.

08-03-2023

Latest News

Auto News
New Leapmotor 3S Showroom Opens In Ipoh, Perak

New Leapmotor 3S Showroom Opens In Ipoh, Perak

Perak state capital of Ipoh gains new Leapmotor brand 3S showroom and service outlet operated by dealers CST Auto.

07-11-2025
Auto News
KLIMS 2026 – ‘Beyond Mobility’ Theme Retained, Key Brands Announced

KLIMS 2026 – ‘Beyond Mobility’ Theme Retained, Key Brands Announced

KLIMS 2026 set to retain ‘Beyond Mobility’ theme, over 20 key participating brands confirmed too.

07-11-2025
Auto News
Govt Moves To Tighten FRU Vehicle Safety After Teluk Intan Crash

Govt Moves To Tighten FRU Vehicle Safety After Teluk Intan Crash

The Cabinet is reviewing new safety measures for FRU vehicles following the tragic Teluk Intan crash.

07-11-2025
Auto News
JPJ Targets Firms Hiring Unlicensed Foreign Drivers

JPJ Targets Firms Hiring Unlicensed Foreign Drivers

JPJ will launch operations nationwide to take action against companies employing foreigners without valid driving licences.

07-11-2025
Auto News
MOT Steps Up Public Transport, Road Safety Upgrades

MOT Steps Up Public Transport, Road Safety Upgrades

MOT rolls out new buses, terminals, and safety rules to improve travel and reduce road risks.

07-11-2025
Auto News
CKD Excise Duty Revision: Govt Studying Measures to Ease Impact

CKD Excise Duty Revision: Govt Studying Measures to Ease Impact

Govt exploring ways to cushion a potential 10-30% car price hike once CKD excise duty exemption expires.

Auto News
Loke Urges Malaysians To Clear 5.5 Million Unpaid JPJ Summonses By Year-End

Loke Urges Malaysians To Clear 5.5 Million Unpaid JPJ Summonses By Year-End

Transport Minister Anthony Loke says over 5.5 million JPJ summonses remain unpaid, urges motorists to settle them before year-end too.

Auto News
GWM Malaysia 3rd Anniversary Sees RM150,000 In Rewards Up For Grabs

GWM Malaysia 3rd Anniversary Sees RM150,000 In Rewards Up For Grabs

RM150,000 in rewards, comprised of premium gadgets and more, are up for grabs from GWM Malaysia as it celebrates its third year anniversary.

07-11-2025