Second RTS Link Train To Arrive At Wadi Hana Depot By End-September

Anis

Share via

Untitled-design---2025-09-17T101709.116.png Photo: Bernama. The second train set for the Johor Bahru–Singapore Rapid Transit System (RTS) Link is on its way and is expected to roll into the Wadi Hana Depot by the end of September. 

The train has just wrapped up a round of tests at CRRC Batu Gajah in Perak.

RTS Operations Pte Ltd (RTSO) CEO Dr Ahmad Marzuki Ariffin said this will be the very first train to be brought into the depot for its next series of on-site tests.

“The first RTS train is still in Singapore undergoing the Offsite Systems Integration Test after its big reveal during the launch ceremony in late June. We expect to bring it over to the Wadi Hana Depot in the second half of November,” he told Harian Metro.

514094738_18488693368065980_604961274850123543_n-(1).jpg514302176_18488693353065980_8568653864935399560_n-(1).jpg
The Wadi Hana Depot will be the heart of operations and maintenance for the RTS Link. 

It’s located just a kilometre north of Bukit Chagar Station, the main Malaysian gateway to the four-kilometre rail line linking Johor Bahru with Woodlands North in Singapore.

A total of eight train sets will make up the fleet, with trains two through eight currently in the final stages of production in Batu Gajah. They’ll be shipped to Johor Bahru in phases through the end of 2025.

As of August, rail system works have reached nearly 61 per cent completion. Most system tests are already done, and crews are now focused on installation and site testing.

Untitled-design---2025-09-11T112302.807.png
“The challenge now is keeping everything running smoothly on-site, especially since system and infrastructure works are happening side by side,” Ahmad Marzuki added.

The RTS Link is still on track to be completed by December 2026 and is expected to start operations in early 2027, carrying up to 40,000 commuters daily.

Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

JPJ Running Numbers

KUALA LUMPUR

VPS2477

SELANGOR

BSH7422

JOHOR

JYG6376

PULAU PINANG

PRT9940

PERAK

APB2061

PAHANG

CFD4692

KEDAH

KGC2715

NEGERI SEMBILAN

NEH1090

KOTA KINABALU

SJM5861

KUCHING

QAB1596M

Last updated 17 Sep, 2025

Fuel Price

Petrol

RON 95

RM 2.05

RON 97

RM 3.18

+0.02

RON 100

RM 5.00

VPR

RM 6.23

Diesel

EURO 5 B10

RM 2.90

+0.02

EURO 5 B7

RM 3.10

+0.02

Last updated 11 Sep, 2025

Related News

Auto News

01-08-2025
Auto News

30-06-2025
Auto News

13-12-2024

Latest News

Auto News
JSPT: Number Plates Flippers Online Are Illegal

JSPT: Number Plates Flippers Online Are Illegal

Motorists caught with plate flippers risk jail, hefty fines, and having their vehicles seized under the Road Transport Act.

Auto News
Second RTS Link Train To Arrive At Wadi Hana Depot By End-September

Second RTS Link Train To Arrive At Wadi Hana Depot By End-September

The second RTS train set is heading to Johor Bahru for on-site testing, keeping the rail project on track for 2027 launch.

17-09-2025
Auto News
Revised RON95 Subsidy Promises Flexible Distribution, Clearer Appeals

Revised RON95 Subsidy Promises Flexible Distribution, Clearer Appeals

RON95 subsidy implementation to feature PADU checks, flexible distribution and an appeals process.

Auto News
Over 150 Companies Registered For Targeted RON95 Subsidy Scheme - KPDN

Over 150 Companies Registered For Targeted RON95 Subsidy Scheme - KPDN

KPDN says 154 firms with 335 vehicles have applied for the SKPS RON95 subsidy and urges more to register early.

17-09-2025
Auto News
6,684 Notices Issued During KL’s Ops PUU

6,684 Notices Issued During KL’s Ops PUU

Motorcyclists topped the list of 6,684 notices during Kuala Lumpur’s two-day Operation Patuh Undang-Undang.

17-09-2025
Auto News
East-West Rail Link Across Titiwangsa Could Take 10-20 Years - Nanta

East-West Rail Link Across Titiwangsa Could Take 10-20 Years - Nanta

The east-west rail project crossing the Titiwangsa Range could take 10 to 20 years to complete.

16-09-2025
Auto News
CAAM, MET Malaysia Inks Deal To Boost Flight Safety

CAAM, MET Malaysia Inks Deal To Boost Flight Safety

CAAM and MET Malaysia have signed a new agreement to enhance aviation safety and operational efficiency.

16-09-2025
Auto News
GM Number Plate Series Launched for Malaysia Day 2025

GM Number Plate Series Launched for Malaysia Day 2025

JPJ marks Malaysia Day 2025 with the launch of the GM number plate series, symbolising Gemilang Malaysia.

Show More

trending_flat
Carz Automedia Malaysia Logo
About Us

CarzAutoMedia: Stay connected to the latest car news! Get instant updates on new releases, industry trends, and automotive innovations. Your go-to source for 24/7 coverage of everything automotive.

© 2025 CariCarz.com. All Rights Reserved.