Second RTS Link Train To Arrive At Wadi Hana Depot By End-September
Photo: Bernama. The second train set for the Johor Bahru–Singapore Rapid Transit System (RTS) Link is on its way and is expected to roll into the Wadi Hana Depot by the end of September.
The train has just wrapped up a round of tests at CRRC Batu Gajah in Perak.
RTS Operations Pte Ltd (RTSO) CEO Dr Ahmad Marzuki Ariffin said this will be the very first train to be brought into the depot for its next series of on-site tests.
“The first RTS train is still in Singapore undergoing the Offsite Systems Integration Test after its big reveal during the launch ceremony in late June. We expect to bring it over to the Wadi Hana Depot in the second half of November,” he told Harian Metro.
The Wadi Hana Depot will be the heart of operations and maintenance for the RTS Link.
It’s located just a kilometre north of Bukit Chagar Station, the main Malaysian gateway to the four-kilometre rail line linking Johor Bahru with Woodlands North in Singapore.
A total of eight train sets will make up the fleet, with trains two through eight currently in the final stages of production in Batu Gajah. They’ll be shipped to Johor Bahru in phases through the end of 2025.
As of August, rail system works have reached nearly 61 per cent completion. Most system tests are already done, and crews are now focused on installation and site testing.
“The challenge now is keeping everything running smoothly on-site, especially since system and infrastructure works are happening side by side,” Ahmad Marzuki added.
The RTS Link is still on track to be completed by December 2026 and is expected to start operations in early 2027, carrying up to 40,000 commuters daily.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VPS2477
SELANGOR
BSH7422
JOHOR
JYG6376
PULAU PINANG
PRT9940
PERAK
APB2061
PAHANG
CFD4692
KEDAH
KGC2715
NEGERI SEMBILAN
NEH1090
KOTA KINABALU
SJM5861
KUCHING
QAB1596M
Last updated 17 Sep, 2025
Fuel Price
Petrol
RON 95
RM 2.05
RON 97
RM 3.18
+0.02
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.90
+0.02
EURO 5 B7
RM 3.10
+0.02
Last updated 11 Sep, 2025
Related News
RTS & ETS Projects On Track For 2025-2026 Completion
Johor Regent Tunku Ismail Idris confirms Johor’s RTS and ETS projects are progressing smoothly.
11-09-2025
New Law In February To Ease RTS Link Border Checks - Home Minister
Malaysia will table a Bill next February to enable co-located border checks for the Johor Bahru–Singapore RTS Link.
27-08-2025
Malaysia’s Transport Push: RTS, Digital Upgrades and Rail Milestones
Transport Minister says Malaysia’s transport is hitting new milestones, bringing real changes for travellers.
26-08-2025
RTS Upgrades On Track, Cross-Border E-Hailing Needs Singapore’s Nod - Loke
Johor’s RTS Link is on track with major upgrades, but cross-border e-hailing can only happen with Singapore’s agreement.
19-08-2025
Johor Proposes RTS2 Link Between Iskandar Puteri and Tuas
With Bukit Chagar terminal nearing completion, Johor eyes new RTS2 link to Tuas to further ease cross-border travel.
01-08-2025
RTS Link Fare Study Underway to Ensure Affordable Cross-Border Travel
RTS Link operators are finalising fare strategies to encourage more commuters to switch from private vehicles to public transport.
01-07-2025
Johor On Track To Become Major Rail Hub In Malaysia
Johor is set to become a major rail hub in Malaysia underpinned by ongoing rail developments.
24-03-2025
QR Codes Coming for Drivers at Johor Checkpoints
Malaysia plans to expand QR code immigration clearance to car drivers, aiming to ease congestion at border checkpoints.
04-03-2025
Latest News
JSPT: Number Plates Flippers Online Are Illegal
Motorists caught with plate flippers risk jail, hefty fines, and having their vehicles seized under the Road Transport Act.
17-09-2025
Second RTS Link Train To Arrive At Wadi Hana Depot By End-September
The second RTS train set is heading to Johor Bahru for on-site testing, keeping the rail project on track for 2027 launch.
17-09-2025
Revised RON95 Subsidy Promises Flexible Distribution, Clearer Appeals
RON95 subsidy implementation to feature PADU checks, flexible distribution and an appeals process.
17-09-2025
Over 150 Companies Registered For Targeted RON95 Subsidy Scheme - KPDN
KPDN says 154 firms with 335 vehicles have applied for the SKPS RON95 subsidy and urges more to register early.
17-09-2025
6,684 Notices Issued During KL’s Ops PUU
Motorcyclists topped the list of 6,684 notices during Kuala Lumpur’s two-day Operation Patuh Undang-Undang.
17-09-2025
East-West Rail Link Across Titiwangsa Could Take 10-20 Years - Nanta
The east-west rail project crossing the Titiwangsa Range could take 10 to 20 years to complete.
16-09-2025
CAAM, MET Malaysia Inks Deal To Boost Flight Safety
CAAM and MET Malaysia have signed a new agreement to enhance aviation safety and operational efficiency.
16-09-2025
GM Number Plate Series Launched for Malaysia Day 2025
JPJ marks Malaysia Day 2025 with the launch of the GM number plate series, symbolising Gemilang Malaysia.
16-09-2025
Show More
trending_flat