ECRL Nears Completion with 89% Progress, Operations Set for 2027
-full_normal.jpg)
The East Coast Rail Link (ECRL) project has reached 89% completion as of Oct 2025, according to Malaysia Rail Link Sdn Bhd (MRL) CEO Datuk Seri Darwis Abdul Razak. He noted that the project is on track to hit 90% progress by year-end, thanks to the coordinated efforts of the MRL team and its implementation partners.
Preparations are now moving towards the testing and commissioning phase, expected to start by mid-2026. Once complete, the ECRL is set to begin operations from Kota Bharu to the Gombak Integrated Terminal in Jan 2027.
-full_normal.jpg)
Phase Two, covering the stretch between Gombak and Port Klang, is scheduled to open in Jan 2028, marking a major milestone in Malaysia’s transportation network.
The ECRL, a high-profile national infrastructure initiative launched by the federal government in 2017, spans 665km across Kelantan, Pahang, Terengganu, and Selangor. It symbolizes strong bilateral cooperation between Malaysia and China and demonstrates the government’s commitment to enhancing the country’s strategic transport links.
-full_normal.jpg)
Construction in Terengganu, which covers 242 KM and includes six stations, has achieved the highest progress among the four states at 94.82% as of Oct 2025. Darwis highlighted this as a clear sign of efficiency and dedication by the teams working in the state.
The milestone was marked during the signing of a Memorandum of Understanding (MoU) between MRL and the Terengganu state government, aimed at supporting transit-oriented development (TOD) around ECRL stations.
-full_normal.jpg)
-full_normal.jpg)
The MoU was signed by Terengganu State Secretary Datuk Zulkifli Ali on behalf of the state, and Darwis representing MRL. The ceremony was witnessed by Terengganu Menteri Besar Datuk Seri Ahmad Samsuri Mokhtar and Chief Secretary to the Government Tan Sri Shamsul Azri Abu Bakar, who also chairs MRL.
The partnership will focus on integrated planning to boost public transport usage, optimise land use around stations, and attract commercial and private investment. Ahmad Samsuri added that with TOD governance in each district, development can proceed responsibly and with people’s interests in mind, making it an ideal moment to draw investors to the state.
Source: The STAR
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VQB1471
SELANGOR
BSK3680
JOHOR
JYL5420
PULAU PINANG
PRV9781
PERAK
APC7294
PAHANG
CFE2496
KEDAH
KGD1664
NEGERI SEMBILAN
NEH6739
KOTA KINABALU
SJN8172
KUCHING
QAB5653M
Last updated 24 Nov, 2025
Fuel Price
Petrol
RON 95
RM 2.65
RON 97
RM 3.28
+0.03
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.10
+0.03
EURO 5 B7
RM 3.30
+0.03
Last updated 20 Nov, 2025
Related News
ECRL Trains Fully Assembled, Ready for Malaysia
The first batch of trains for the East Coast Rail Link (ECRL) is now ready in Dalian, China.
21-11-2025
ECRL Hits 88% Milestone As Key C1B Stretch Completed
The ECRL project has hit 88% completion with the C1B Segment now successfully completed.
05-11-2025
MOT Eyes Rail Expansion, Road Safety and Airport Improvements
Transport Minister YB Loke Siew Fook outlines major transport projects and safety reforms under the 2026 Budget.
30-10-2025
ECRL Project On Track Despite RM2.9mil Theft Losses
MRL boosts security after 38 theft cases but says the ECRL project remains on schedule.
30-10-2025
ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses
The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.
14-10-2025
Budget 2026: Prasarana Seeks Continued Support for Travel Passes and LRT3
Prasarana moots continued support for travel passes, LRT 3 line completion, cites them as key to easing living costs and improving urban mobility.
09-10-2025
ECRL Project Hits 87% Completion by August 2025 – MoT
The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.
23-09-2025
ECRL Work Halted - Petronas Gas Pipeline Leak, Safety Zone Declared
Petronas Gas pipeline leak at the ECRL project has halted works, emergency crews racing to purge butane gas.
22-09-2025
Latest News
ECRL Nears Completion with 89% Progress, Operations Set for 2027
ECRL is on track to begin services from Kota Bharu to Gombak in Jan 2027, as construction progress hits 89%.
24-11-2025
Johor’s Elevated ART Moving Forward, RFP Under Review - Loke
Johor’s Autonomous Rapid Transit project is progressing, with proposals being refined before final approval.
24-11-2025
Isuzu Malaysia Opens New 4S Centre in Balakong
Isuzu Malaysia has opened its new 4S centre in Balakong, operated by SV Prestige Auto.
24-11-2025
Over RM1.3 Million In Fines Issued To 4,634 Singapore Drivers For VEP Violations
Since July, JPJ has issued RM1.39 million in fines to 4,634 Singapore-registered vehicles for failing to comply with VEP requirements.
24-11-2025
Pasir Gudang Highway Off Worst Roads List But Streetlight Issues Linger
Pasir Gudang Highway has finally dropped from the worst roads list after years of repairs, but faulty streetlights continue to cause issues.
24-11-2025
ETS JB to KL Service Starts Dec 12, Royal Launch Set For Dec 11
ETS JB-KL service finally set to begin operations on Dec 12, official launch graced by the Sultan Ibrahim set for Dec 11.
24-11-2025
Over 1,300 hours Of Train Delays This Year Due To Cable Theft - Loke
Cable theft has caused major disruptions to KTM Komuter and ETS services this year, resulting in over 1,300 hours of delays.
21-11-2025
Gemas-JB Rail Project Set To Start Full Service This Month
The Gemas-Johor Baru rail line nears completion with full train services expected this month.
21-11-2025
Show More
trending_flat