ECRL Hits 82% Completion, Promises 1,800 Jobs - 80% For Locals

The East Coast Rail Link (ECRL) project is now 82.45% complete as of April 2025. The 665km railway is on track, with the Kota Bharu–Gombak stretch due by Dec 2026 and the Gombak–Port Klang section by Dec 2027.
Track installation from Maran to Kota Bharu, spanning 400 KM, finished ahead of schedule with work on the Maran–Bentong stretch beginning this month and is set to complete by June.
Electrification works started in May 2024, with over 9,000 OCS poles installed and around 2,700 left. Tunnel boring has reached 38 of 41 tunnels, with the 16.39km Genting Twin Tunnel expected to break through in Q3 this year.

Station construction is progressing well and is set for completion by mid-2026. Testing and commissioning of the system will begin in June 2026.
Transport Minister YB Anthony Loke Siew Fook shared these updates during the launch of the ECRL’s Operations & Maintenance (O&M) workforce training under the PLKI-ECRL programme.
Once operational in January 2027, the ECRL will require around 1,800 workers, with 80% being Malaysians. The aim is to build a skilled local workforce for modern rail operations.
The PLKI-ECRL programme is now focused on training for the O&M phase. A total of 3,200 trainees will benefit, starting with 210 Malaysians this year.

Of that, 102 trainees will begin one-year training in Liuzhou, China, from 15 May. They’ll learn technical and operational skills for various ECRL roles.
Trainees are guaranteed jobs upon completion and the programme is supported by a RM12 million sponsorship from China Communications Construction Company Ltd (CCCC).

ECRL will use 11 EMU train sets and 12 electric locomotives from CRRC Dalian. The first units are expected by year-end. These new trains will run up to 160 km/h, cutting travel time from Kota Bharu to Gombak to just four hours.
Loke also added that ECRL will help shift cargo from road to rail - an eco-friendly, cost-effective move in line with national transport goals.
He added that efforts are underway to ensure passenger fares remain affordable when operations begin.
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VQK9343
SELANGOR
BSM3020
JOHOR
JYQ9681
PULAU PINANG
PRY4136
PERAK
APE9420
PAHANG
CFF1659
KEDAH
KGE2315
NEGERI SEMBILAN
NEJ4573
KOTA KINABALU
SJQ1732
KUCHING
QAB1960N
Last updated 03 Feb, 2026
Fuel Price
Petrol
RON 95
RM 2.54
+0.02
RON 97
RM 3.10
+0.02
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.88
+0.04
EURO 5 B7
RM 3.08
+0.04
Last updated 22 Jan, 2026
Related News
ECRL Fares To Be Announced Ahead of 2027 Launch
ECRL fares will be disclosed several months prior to the commencement of operations in January 2027, according to Transport Minister.
30-01-2026
ECRL Launch Hinges On System Integration, Jan 2027 Target Maintained
The ECRL remains on schedule, with system integration and testing now the key focus ahead of its planned Jan 2027 launch.
29-01-2026
ECRL First EMU Trains, E-Locos Head To Malaysia For Testing
Malaysia’s East Coast Rail Link gears up as its first EMUs and electric locomotives arrive for testing and future service.
17-12-2025
First ECRL Trains Depart China, Remaining Units Arriving Through 2026
First ECRL trains depart China, with remaining units scheduled to arrive through 2026.
28-11-2025
ECRL Nears Completion with 89% Progress, Operations Set for 2027
ECRL is on track to begin services from Kota Bharu to Gombak in Jan 2027, as construction progress hits 89%.
24-11-2025
ECRL Trains Fully Assembled, Ready for Malaysia
The first batch of trains for the East Coast Rail Link (ECRL) is now ready in Dalian, China.
21-11-2025
ECRL Hits 88% Milestone As Key C1B Stretch Completed
The ECRL project has hit 88% completion with the C1B Segment now successfully completed.
05-11-2025
ECRL Project On Track Despite RM2.9mil Theft Losses
MRL boosts security after 38 theft cases but says the ECRL project remains on schedule.
30-10-2025
Latest News
Martin Schulz Succeeds Amanda Zhang As Mercedes-Benz Malaysia CEO
Mercedes-Benz Cars Malaysia has named Martin Schulz as as its new CEO and president, effective February 1, 2026.
03-02-2026
JPJ Enforces Heavy Vehicle Road Ban Ahead of CNY To Ease Traffic
JPJ enforces heavy vehicle bans to ensure safer, smoother travel this Chinese New Year.
03-02-2026
MITI: Malaysia Poised as High-Value Auto Hub
Malaysia’s skilled workforce and 640+ vendors fuel its rise as a high-value auto export hub.
03-02-2026
Another Singapore Car Caught Pumping Subsidised RON95 In Johor
Another Singapore-registered vehicle has been caught pumping subsidised RON95 petrol in Johor.
03-02-2026
RTS Link to Deploy 100 E-Gates at Bukit Chagar ICQ
RTS Link to deploy 100 e-gates at Bukit Chagar ICQ as part of a high-capacity, congestion-reducing clearance system.
03-02-2026
BateriHub Reaches 200 Stores Nationwide, Sets New ASEAN Record
BateriHub’s ever-expanding local outlet network has now reached 200 locations nationwide.
03-02-2026
Isuzu Reels In ‘Strong’ 2025 Sales Figures Despite Downward Demands
Isuzu Malaysia says its 2025 sales remain strong despite downward demands for diesel vehicles in Malaysia.
02-02-2026
KLIA Aerotrain Performance Stabilising
Independent assessors say the KLIA Aurotrain system is operating as intended, with early service disruptions performance stabilising.
02-02-2026
Show More
trending_flat