ECRL Hits 82% Completion, Promises 1,800 Jobs - 80% For Locals

The East Coast Rail Link (ECRL) project is now 82.45% complete as of April 2025. The 665km railway is on track, with the Kota Bharu–Gombak stretch due by Dec 2026 and the Gombak–Port Klang section by Dec 2027.
Track installation from Maran to Kota Bharu, spanning 400 KM, finished ahead of schedule with work on the Maran–Bentong stretch beginning this month and is set to complete by June.
Electrification works started in May 2024, with over 9,000 OCS poles installed and around 2,700 left. Tunnel boring has reached 38 of 41 tunnels, with the 16.39km Genting Twin Tunnel expected to break through in Q3 this year.

Station construction is progressing well and is set for completion by mid-2026. Testing and commissioning of the system will begin in June 2026.
Transport Minister YB Anthony Loke Siew Fook shared these updates during the launch of the ECRL’s Operations & Maintenance (O&M) workforce training under the PLKI-ECRL programme.
Once operational in January 2027, the ECRL will require around 1,800 workers, with 80% being Malaysians. The aim is to build a skilled local workforce for modern rail operations.
The PLKI-ECRL programme is now focused on training for the O&M phase. A total of 3,200 trainees will benefit, starting with 210 Malaysians this year.

Of that, 102 trainees will begin one-year training in Liuzhou, China, from 15 May. They’ll learn technical and operational skills for various ECRL roles.
Trainees are guaranteed jobs upon completion and the programme is supported by a RM12 million sponsorship from China Communications Construction Company Ltd (CCCC).

ECRL will use 11 EMU train sets and 12 electric locomotives from CRRC Dalian. The first units are expected by year-end. These new trains will run up to 160 km/h, cutting travel time from Kota Bharu to Gombak to just four hours.
Loke also added that ECRL will help shift cargo from road to rail - an eco-friendly, cost-effective move in line with national transport goals.
He added that efforts are underway to ensure passenger fares remain affordable when operations begin.
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VRE5834
SELANGOR
BSR3247
JOHOR
JYB7162
PULAU PINANG
PSD4735
PERAK
APJ5421
PAHANG
CFG9541
KEDAH
KGG7895
NEGERI SEMBILAN
NEK7927
KOTA KINABALU
SJS7792
KUCHING
QAB1307P
Last updated 01 Jul, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
Kuantan Welcomes ECRL’s First Trains Ahead of 2027 Operations
The first ECRL electric passenger trains and freight locomotives have arrived in Kuantan as the project moves closer to operations in 2027.
11-02-2026
ECRL Fares To Be Announced Ahead of 2027 Launch
ECRL fares will be disclosed several months prior to the commencement of operations in January 2027, according to Transport Minister.
30-01-2026
ECRL Launch Hinges On System Integration, Jan 2027 Target Maintained
The ECRL remains on schedule, with system integration and testing now the key focus ahead of its planned Jan 2027 launch.
29-01-2026
ECRL First EMU Trains, E-Locos Head To Malaysia For Testing
Malaysia’s East Coast Rail Link gears up as its first EMUs and electric locomotives arrive for testing and future service.
17-12-2025
First ECRL Trains Depart China, Remaining Units Arriving Through 2026
First ECRL trains depart China, with remaining units scheduled to arrive through 2026.
28-11-2025
ECRL Nears Completion with 89% Progress, Operations Set for 2027
ECRL is on track to begin services from Kota Bharu to Gombak in Jan 2027, as construction progress hits 89%.
24-11-2025
ECRL Trains Fully Assembled, Ready for Malaysia
The first batch of trains for the East Coast Rail Link (ECRL) is now ready in Dalian, China.
21-11-2025
ECRL Hits 88% Milestone As Key C1B Stretch Completed
The ECRL project has hit 88% completion with the C1B Segment now successfully completed.
05-11-2025
Latest News
The Era Of Reckless Lorries Is Finally Ending: Why This New Telematics Move Is The Game Changer We’ve Been Waiting For
Reckless lorries have been a terror on Malaysian roads for years. But is a new "smart" telematics system the game changer we've been waiting for? Here's the scoop.
30-06-2026
Another 6 Months Of No Price Hikes! Here’s The Latest On The CKD Tax Revision
Good news for car buyers! The government has deferred the OMV excise duty revision for another 6 months. Get the latest update on CKD car prices and what this means for you.
30-06-2026
Forget Luxury Condos! PM Anwar Wants Affordable Homes Next To Train Stations – Here’s The Plan
PM Anwar wants affordable homes, not luxury condos, next to LRT3 stations! See the 4 locations identified for new Transit-Oriented Developments in the Klang Valley.
30-06-2026
Save RM6,000 A Year? We Calculated Your Real Savings By Switching To The New LRT3
LRT3 Shah Alam Line is now open with free rides until July 31. See how switching to public transport can save you RM6,000 annually in fuel, tolls, and parking.
29-06-2026
Ferrari’s 16-Year Marketing Chief Stepped Down—But Was It Really His Choice?
Ferrari’s 16-year marketing lead has stepped down following the controversial Luce EV launch. Was this a planned exit or a high-profile design disaster casualty?
26-06-2026
Foreigners Are Using Local MyKads to Buy Vehicles—And Leaving Locals With a Legal Nightmare
Think renting your car to a foreigner is easy money? Think again. JPJ's Ops PeWA is seizing vehicles and hauling local owners to court. Learn the risks.
26-06-2026
From 80 Sen To RM4.30: A Simple Breakdown Of The New LRT3 Fares
Planning to ride the new LRT3? Get a simple breakdown of the Shah Alam Line fares.
25-06-2026
BUDI Diesel Explained: 200L Quota, No Deadlines, And The New 'Approved Person' Rule You Need To Know
Confused by the new RM2.10 diesel subsidy? Our ultimate guide covers quotas, how to claim your extra 100L, and the latest 'Approved Person' rules.
25-06-2026
Show More
trending_flat