ECRL Hits 82% Completion, Promises 1,800 Jobs - 80% For Locals

The East Coast Rail Link (ECRL) project is now 82.45% complete as of April 2025. The 665km railway is on track, with the Kota Bharu–Gombak stretch due by Dec 2026 and the Gombak–Port Klang section by Dec 2027.
Track installation from Maran to Kota Bharu, spanning 400 KM, finished ahead of schedule with work on the Maran–Bentong stretch beginning this month and is set to complete by June.
Electrification works started in May 2024, with over 9,000 OCS poles installed and around 2,700 left. Tunnel boring has reached 38 of 41 tunnels, with the 16.39km Genting Twin Tunnel expected to break through in Q3 this year.

Station construction is progressing well and is set for completion by mid-2026. Testing and commissioning of the system will begin in June 2026.
Transport Minister YB Anthony Loke Siew Fook shared these updates during the launch of the ECRL’s Operations & Maintenance (O&M) workforce training under the PLKI-ECRL programme.
Once operational in January 2027, the ECRL will require around 1,800 workers, with 80% being Malaysians. The aim is to build a skilled local workforce for modern rail operations.
The PLKI-ECRL programme is now focused on training for the O&M phase. A total of 3,200 trainees will benefit, starting with 210 Malaysians this year.

Of that, 102 trainees will begin one-year training in Liuzhou, China, from 15 May. They’ll learn technical and operational skills for various ECRL roles.
Trainees are guaranteed jobs upon completion and the programme is supported by a RM12 million sponsorship from China Communications Construction Company Ltd (CCCC).

ECRL will use 11 EMU train sets and 12 electric locomotives from CRRC Dalian. The first units are expected by year-end. These new trains will run up to 160 km/h, cutting travel time from Kota Bharu to Gombak to just four hours.
Loke also added that ECRL will help shift cargo from road to rail - an eco-friendly, cost-effective move in line with national transport goals.
He added that efforts are underway to ensure passenger fares remain affordable when operations begin.
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VQR7645
SELANGOR
BSN5897
JOHOR
JYT7125
PULAU PINANG
PSA8544
PERAK
APG2695
PAHANG
CFF9401
KEDAH
KGE9242
NEGERI SEMBILAN
NEJ8671
KOTA KINABALU
SJR614
KUCHING
QAB4655N
Last updated 31 Mar, 2026
Fuel Price
Petrol
RON 95
RM 2.59
+0.05
RON 97
RM 3.15
+0.05
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.04
+0.05
EURO 5 B7
RM 3.24
+0.05
Last updated 26 Feb, 2026
Related News
Kuantan Welcomes ECRL’s First Trains Ahead of 2027 Operations
The first ECRL electric passenger trains and freight locomotives have arrived in Kuantan as the project moves closer to operations in 2027.
11-02-2026
ECRL Fares To Be Announced Ahead of 2027 Launch
ECRL fares will be disclosed several months prior to the commencement of operations in January 2027, according to Transport Minister.
30-01-2026
ECRL Launch Hinges On System Integration, Jan 2027 Target Maintained
The ECRL remains on schedule, with system integration and testing now the key focus ahead of its planned Jan 2027 launch.
29-01-2026
ECRL First EMU Trains, E-Locos Head To Malaysia For Testing
Malaysia’s East Coast Rail Link gears up as its first EMUs and electric locomotives arrive for testing and future service.
17-12-2025
First ECRL Trains Depart China, Remaining Units Arriving Through 2026
First ECRL trains depart China, with remaining units scheduled to arrive through 2026.
28-11-2025
ECRL Nears Completion with 89% Progress, Operations Set for 2027
ECRL is on track to begin services from Kota Bharu to Gombak in Jan 2027, as construction progress hits 89%.
24-11-2025
ECRL Trains Fully Assembled, Ready for Malaysia
The first batch of trains for the East Coast Rail Link (ECRL) is now ready in Dalian, China.
21-11-2025
ECRL Hits 88% Milestone As Key C1B Stretch Completed
The ECRL project has hit 88% completion with the C1B Segment now successfully completed.
05-11-2025
Latest News
7 Years of Peace of Mind: Why the Saga MC3’s New Warranty is a "Must-Have" Add-On
Proton's new RM1,200 extended warranty for the Saga MC3 offers 7 years of cover. We decode the costs, the 1.5L i-GT engine risks, and the resale value hacks.
30-03-2026
Reality Check: Decoding the Massive Gaps in Maslan’s Cycling & Biodiesel Proposals
We decode the RM643m funding gap in Ahmad Maslan's B20 biodiesel plan and the reality of cycling in Malaysia. Is the 7-point fuel fix a dream or a disaster?
30-03-2026
Final 24 Hours: 3 Things You Must Do Before the BUDI95 Quota Drops to 200L Tomorrow
Midnight Deadline: The BUDI95 quota drops to 200L in less than 24 hours. See the 3 vital steps every driver must take today to avoid a massive price shock at the pump tomorrow.
30-03-2026
Proton Wants to Forgive Your “Service Sins” from RM120
Lapsed your Proton service for 12 months? Get a fresh start with PROTON’s 2026 campaign. Packages from RM120 for Persona/Saga and RM216 for X-series SUVs.
30-03-2026
Farewell to Budget High-Tech EV? MITI’s Terms Could Force BYD Out of Tanjung Malim
Why is the BYD Tanjung Malim plant stuck? We decode MITI’s 80% export rule and the RM200k price floor that’s keeping affordable EVs out of Malaysia.
30-03-2026
Motorcyclist Dies After Being Hit by Speeding Car in Klang
Tragic fatal crash in Klang: A motorcyclist was killed on the spot after a car allegedly speeding and overtaking on a double yellow line struck him on Jalan Bunga Raya Barat behind MBDK on 29 March 2026.
29-03-2026
The RM5,000 Raya Flex: Why Malaysians are Risking a Monthly Salary to Rent an Alphard
Is renting an Alphard for RM5,000 a waste or a genius move? We break down the 'Raya Flex' cost, from RM10k insurance premiums to the 'Executive Lounge' comfort that saves your back on an 18-hour East Coast jam.
27-03-2026
Safe Passage at Hormuz: Why Malaysia’s Special Deal with Iran Won't Lower Your Petrol Price
PM Anwar secured safe passage for Malaysian ships, so why is RON95 hitting RM3.87/L? We decode the 400% insurance surge and the new 200L BUDI95 quota.
27-03-2026
Show More
trending_flat