ECRL Hits 82% Completion, Promises 1,800 Jobs - 80% For Locals
The East Coast Rail Link (ECRL) project is now 82.45% complete as of April 2025. The 665km railway is on track, with the Kota Bharu–Gombak stretch due by Dec 2026 and the Gombak–Port Klang section by Dec 2027.
Track installation from Maran to Kota Bharu, spanning 400 KM, finished ahead of schedule with work on the Maran–Bentong stretch beginning this month and is set to complete by June.
Electrification works started in May 2024, with over 9,000 OCS poles installed and around 2,700 left. Tunnel boring has reached 38 of 41 tunnels, with the 16.39km Genting Twin Tunnel expected to break through in Q3 this year.
Station construction is progressing well and is set for completion by mid-2026. Testing and commissioning of the system will begin in June 2026.
Transport Minister YB Anthony Loke Siew Fook shared these updates during the launch of the ECRL’s Operations & Maintenance (O&M) workforce training under the PLKI-ECRL programme.
Once operational in January 2027, the ECRL will require around 1,800 workers, with 80% being Malaysians. The aim is to build a skilled local workforce for modern rail operations.
The PLKI-ECRL programme is now focused on training for the O&M phase. A total of 3,200 trainees will benefit, starting with 210 Malaysians this year.
Of that, 102 trainees will begin one-year training in Liuzhou, China, from 15 May. They’ll learn technical and operational skills for various ECRL roles.
Trainees are guaranteed jobs upon completion and the programme is supported by a RM12 million sponsorship from China Communications Construction Company Ltd (CCCC).
ECRL will use 11 EMU train sets and 12 electric locomotives from CRRC Dalian. The first units are expected by year-end. These new trains will run up to 160 km/h, cutting travel time from Kota Bharu to Gombak to just four hours.
Loke also added that ECRL will help shift cargo from road to rail - an eco-friendly, cost-effective move in line with national transport goals.
He added that efforts are underway to ensure passenger fares remain affordable when operations begin.
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VPS2415
SELANGOR
BSH7411
JOHOR
JYG6315
PULAU PINANG
PRT9853
PERAK
APB2049
PAHANG
CFD4677
KEDAH
KGC2695
NEGERI SEMBILAN
NEH1085
KOTA KINABALU
SJM5851
KUCHING
QAB1588M
Last updated 15 Sep, 2025
Fuel Price
Petrol
RON 95
RM 2.05
RON 97
RM 3.18
+0.02
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.90
+0.02
EURO 5 B7
RM 3.10
+0.02
Last updated 11 Sep, 2025
Related News
ECRL Cites Potential Delay From Escalated Cable and Wire Theft
ECRL says thefts of cable and wires could derail construction progress on the 665 km railway project.
11-09-2025
Govt Studying ECRL Extension to Thai Border Town Rantau Panjang
Anwar says the ECRL extension to Rantau Panjang could open new growth at the Malaysia–Thailand border.
03-09-2025
Zafrul: ECRL Will Spur Jobs, Investments Along the East Coast
Tengku Zafrul says the ECRL will not only improve connectivity but also drive growth across the East Coast.
03-09-2025
ECRL Extension To Thailand Faces Track, Flood Challenges – Loke
Transport Minister says extending the ECRL to Thailand faces challenges like track differences and flood risks.
20-08-2025
Langkawi LRT ‘Unrealistic’, Focus Stays on Penang LRT and ECRL - Loke
The government is pushing ahead with the Penang LRT and ECRL, but dismissed talk of a Langkawi LRT as unrealistic.
19-08-2025
Anwar: 13MP Pushes for Improved Connectivity – Better Buses, Trains and Roads
The 13th Malaysia Plan focuses on better connectivity through buses, trains, roads, and smarter planning.
31-07-2025
ECRL Extension from Kota Bharu to Pasir Mas Under Review
Kelantan is pushing for the ECRL to extend to Rantau Panjang, eyeing cross-border rail links with Thailand.
23-07-2025
ECRL Set To Receive First Two EMU Trains, E-Locos By Year-End
ECRL is expected to receive its first two EMU trains and two E-Loco by the end of this year.
16-07-2025
Latest News
GWM Wey 80 Teased Again, Now Renamed ‘Wey G9’ Instead
Upcoming GWM Wey 80 teased on social media, now bearing new ‘Wey G9’ nameplate too.
15-09-2025
Proton Iriz Production Ends – No Successor Planned, But Should There Be One?
Proton Iriz hatch production ends without a successor, leaving automaker without a new hatch model since 1994.
12-09-2025
West Ipoh Span Expressway Construction Will Begin After 2026
Construction of the West Ipoh Span Expressway is set to start after 2026, providing an alternative to the busy Menora Tunnel route.
12-09-2025
SSLR2 Highway Launched: RM7.6b Project Will Link Sarawak and Sabah
The 335km Sarawak–Sabah Link Road Phase 2 will connect key towns across northern Sarawak into Sabah.
12-09-2025
Proton: We Are Prepared To Serve New X50 After Sales In East Malaysia
Proton reassures it is more than capable of handling after sales coverage for face-lifted new X50 model in East Malaysia.
12-09-2025
PLUS: Up to 2.2 Million Vehicles Daily This Malaysia Day Weekend
PLUS expects traffic to hit 2.2 million vehicles per day on Sept 12, 13, 19 and 20,motorists urged to plan journeys with the MyPLUS-TTA app.
12-09-2025
Prasarana Rail Reliability Hits Record High, Disruptions Halved
Prasarana reports its best rail performance yet, with service reliability more than doubling since 2024.
12-09-2025
Caricarz Automall Sunday Car Market Returns Sept 21 After Strong Debut
Caricarz Automall Sunday Car Market returns Sept 21 to help owners beat lowball trade-ins with direct sales.
12-09-2025
Show More
trending_flat