ECRL Hits 82% Completion, Promises 1,800 Jobs - 80% For Locals

The East Coast Rail Link (ECRL) project is now 82.45% complete as of April 2025. The 665km railway is on track, with the Kota Bharu–Gombak stretch due by Dec 2026 and the Gombak–Port Klang section by Dec 2027.
Track installation from Maran to Kota Bharu, spanning 400 KM, finished ahead of schedule with work on the Maran–Bentong stretch beginning this month and is set to complete by June.
Electrification works started in May 2024, with over 9,000 OCS poles installed and around 2,700 left. Tunnel boring has reached 38 of 41 tunnels, with the 16.39km Genting Twin Tunnel expected to break through in Q3 this year.

Station construction is progressing well and is set for completion by mid-2026. Testing and commissioning of the system will begin in June 2026.
Transport Minister YB Anthony Loke Siew Fook shared these updates during the launch of the ECRL’s Operations & Maintenance (O&M) workforce training under the PLKI-ECRL programme.
Once operational in January 2027, the ECRL will require around 1,800 workers, with 80% being Malaysians. The aim is to build a skilled local workforce for modern rail operations.
The PLKI-ECRL programme is now focused on training for the O&M phase. A total of 3,200 trainees will benefit, starting with 210 Malaysians this year.

Of that, 102 trainees will begin one-year training in Liuzhou, China, from 15 May. They’ll learn technical and operational skills for various ECRL roles.
Trainees are guaranteed jobs upon completion and the programme is supported by a RM12 million sponsorship from China Communications Construction Company Ltd (CCCC).

ECRL will use 11 EMU train sets and 12 electric locomotives from CRRC Dalian. The first units are expected by year-end. These new trains will run up to 160 km/h, cutting travel time from Kota Bharu to Gombak to just four hours.
Loke also added that ECRL will help shift cargo from road to rail - an eco-friendly, cost-effective move in line with national transport goals.
He added that efforts are underway to ensure passenger fares remain affordable when operations begin.
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VQX5725
SELANGOR
BSP9552
JOHOR
JYW5143
PULAU PINANG
PSC2260
PERAK
APH4067
PAHANG
CFG4807
KEDAH
KGF8452
NEGERI SEMBILAN
NEK3843
KOTA KINABALU
SJR8723
KUCHING
QAB7479N
Last updated 16 May, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
Kuantan Welcomes ECRL’s First Trains Ahead of 2027 Operations
The first ECRL electric passenger trains and freight locomotives have arrived in Kuantan as the project moves closer to operations in 2027.
11-02-2026
ECRL Fares To Be Announced Ahead of 2027 Launch
ECRL fares will be disclosed several months prior to the commencement of operations in January 2027, according to Transport Minister.
30-01-2026
ECRL Launch Hinges On System Integration, Jan 2027 Target Maintained
The ECRL remains on schedule, with system integration and testing now the key focus ahead of its planned Jan 2027 launch.
29-01-2026
ECRL First EMU Trains, E-Locos Head To Malaysia For Testing
Malaysia’s East Coast Rail Link gears up as its first EMUs and electric locomotives arrive for testing and future service.
17-12-2025
First ECRL Trains Depart China, Remaining Units Arriving Through 2026
First ECRL trains depart China, with remaining units scheduled to arrive through 2026.
28-11-2025
ECRL Nears Completion with 89% Progress, Operations Set for 2027
ECRL is on track to begin services from Kota Bharu to Gombak in Jan 2027, as construction progress hits 89%.
24-11-2025
ECRL Trains Fully Assembled, Ready for Malaysia
The first batch of trains for the East Coast Rail Link (ECRL) is now ready in Dalian, China.
21-11-2025
ECRL Hits 88% Milestone As Key C1B Stretch Completed
The ECRL project has hit 88% completion with the C1B Segment now successfully completed.
05-11-2025
Latest News
Phew! Anthony Loke Confirms T20s Won’t Be Cut From Fuel Subsidies... For Now
Transport Minister Anthony Loke confirms T20 group will not be cut from RON95 fuel subsidies for now. Learn why the government is sticking to the "simple" Budi95 MyKad system.
14-05-2026
First 300L, Now 200L... Is 150L Inevitable? A Look At The Future Of Budi Madani
Is the 150L petrol quota coming? We break down the "taken out of context" Budi95 news and why Malaysia's RM7 billion subsidy bill makes a future cut a real possibility.
13-05-2026
5 Shocking Numbers That Explain Why Proton Is Exiting Its Distribution Deal In South Africa
Proton's South African distributor, CMH Group, confirms the termination of its agreement. From selling only 7 cars in April to the rise of Geely, here are 5 numbers you need to see.
13-05-2026
It’s Not Just About Income'—Economy Ministry Responds To Concerns That T20 Are Being 'Unfairly' Cut Off
Is the T20 being unfairly cut off from RON95 subsidies? Economy Ministry clarifies how PADU will use household needs, not just income, for targeted fuel subsidies in Malaysia.
12-05-2026
Bankrupt Or Safe? Take This Quiz To See Your New Motor Insurance Fate
Will your driving habits save you money or break the bank? Take our quiz to see how Malaysia’s new 'risk-based' motor insurance rules from PIAM could affect your premiums.
12-05-2026
Cheap Petrol For T20? Its Days Are Numbered. PM Anwar Drops New Update
PM Anwar confirms the T20 fuel subsidy cut is in its final stages. Find out how the T20, B40 and M40 groups are affected by the new RON95 rationalisation.
11-05-2026
Why You Might Be Rejected (And Why You Won't): Decoding JPJ’s New License Conversion Categories
Returning to Malaysia? Starting June 1, 2026, you can convert your foreign driving license to a JPJ license without retaking the test. We decode the new SOPs, eligibility rules, and common reasons for rejection.
08-05-2026
"Wait, Why Is It Taking So Long?" — 4 Things Slowing Down The Pan Borneo Highway In Sabah Right Now
Why is the Pan Borneo Highway taking so long? Chief Minister Hajiji Noor reveals 4 main constraints slowing down Phase 1B from Sandakan to Lahad Datu.
07-05-2026
Show More
trending_flat