ECRL: Port Klang Stretch Will Be Upgraded to Double-Track System
Mukhlis Azman
18-2-2025
The 25-KM stretch of the ECRL at Port Klang will be upgraded to a double-track system with no extra cost, Transport Minister YB Anthony Loke said.
The 25-KM stretch of the East Coast Rail Link (ECRL) project in Port Klang will be upgraded to a double-track system, NST reports. According to transport minister YB Anthony Loke, the construction of the double track, known as Section D, spanning from the Jalan Kastam station to both Northport and Westport, will not increase the overall cost for the whole project.
“To enhance rail freight capacity and improve transport efficiency to Northport and Westport, the Cabinet has agreed to construct a double track, which will include a new standard-gauge track for ECRL services, while maintaining the existing metre-gauge track for KTM services.
“The estimated cost of the ECRL project, after incorporating the new scope in Section D, remains lower than the cost agreed upon in 2017 when the ECRL alignment only extended to Jalan Kastam station without a connection to Northport and Westport,” Loke told the reporters at yesterday’s press conference.
Loke also added that the detailed tender information for this double-track upgrade project will be released by both the Malaysia Rail Link Berhad (MRL) and the China Communications Construction Company Ltd. (CCCC) by the end of the month.
“For the construction of this track, Malaysia Rail Link Bhd, as the ECRL project owner, and China Communications Construction Company Ltd, as the main contractor, will release detailed tender information by the end of the month. Priority will be given to qualified and experienced Bumiputera contractors in the rail industry,” he added.
This double-track upgrade for the ECRL Port Klang stretch means that both the KTM and ECRL will have separate tracks, with the originally planned single-track system allowing trains of different gauges to use the same line. However, the original plan would seem like a poor solution when you consider the eventual heavy rail traffic these two lines will garner in the future.
As for the whole ECRL project, completion progress is recorded at 78.5% as of Jan this year, with the testing and certification of Phase 1 from Kota Bharu to Gombak slated to begin later in June 2026, ahead of its expected operation commencement in Jan 2027. Meanwhile, Phase 2 from Gombak to Port Klang is set to be completed by Dec 2027 and begin operations in Jan 2028.
Source: NST
Gallery
Written By
Mukhlis Azman
An avid two-wheeler that writes and talks about four-wheelers for a living, while dreaming of an urban transit-laden Malaysia. @mukhlisazman
JPJ Running Numbers
KUALA LUMPUR
VPD7465
SELANGOR
BSE8596
JOHOR
JXX8149
PULAU PINANG
PRQ7610
PERAK
ANV8719
PAHANG
CFB7960
KEDAH
KGA6250
NEGERI SEMBILAN
NEF9352
KOTA KINABALU
SJK9999*
KUCHING
QAB3843L
Last updated 22 May, 2025
Fuel Price
Petrol
RON 95
RM 2.05
RON 97
RM 3.10
+0.03
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.80
+0.03
EURO 5 B7
RM 3.00
+0.03
Last updated 22 May, 2025
Related News
Task Force Given 30 Days To Submit Preliminary Report On FRU Crash - Loke
Task force investigating the Teluk Intan crash that killed nine FRU personnel must submit a preliminary report to the MOT within 30 days.
21-05-2025
Maxim Malaysia Responds to APAD’s Shutdown Orders, Operations Ongoing
Maxim Malaysia has published an official response to the recent shutdown orders made by the Land Public Transport Agency.
15-05-2025
Task Force To Probe Fatal FRU Crash In Teluk Intan
MOT will form a Special Task Force to investigate a fatal crash in Teluk Intan, Perak, that killed nine FRU personnel.
14-05-2025
MOT Lowers School Zone Speed Limit To 30 KM/H
The government will soon gazette new 30 KM/H speed limit in school zones.
30-04-2025
A_A Number Plate Series Nets Over RM24 Million
A_A number plate series drew over 24,000 bidders and raised more than RM24 million through JPJeBid.
24-04-2025
BYD Charges Up MOT Staff EV Adoption Effort
“Jom Pandu BYD Bersama MOT” effort sees ministry team up with BYD to drive EV transition from the inside out.
22-04-2025
MOT Announced Achievements Carried Out In 2025
Anthony Loke highlighted MOT’s significant achievements during the ministry’s April 2025 monthly meeting.
22-04-2025
Malaysia, China Signed MoU On Railway Development
Malaysia, China signed a MoU to cooperate on railway development, including joint projects and knowledge sharing.
18-04-2025
Latest News
PLUS Announces Several Road Closures For ASEAN Summit
PLUS announces several road closures on May 23-26 and May 28 for the ASEAN Summit 2025.
22-05-2025
Report: Penang State Govt Considering Third Bridge Option
Penang state govt reportedly eyeing up third bridge option as alternative towards proposed undersea tunnel.
22-05-2025
Penang Bus Ridership Now Exceeds 46,000 Daily
Penang bus average daily ridership has reached 46,333 after the introduction of on-demand van service and free bus travel.
22-05-2025
Proton and Continental Launch Tyre Replacement at Service Centres
Proton and Continental teams up, offers tyre sales, installation, and support at selected Proton service centres.
22-05-2025
Targeted RON95 Subsidy Should Proceed Despite Tariffs - Economist
Despite US tariffs, economist Ahmed Razman Abdul Latiff advises the government to continue with targeted RON95 fuel subsidies.
22-05-2025
Penang Govt Acquires 15 New Toyota Camry 2.5V
Penang govt fleets 15 Toyota Camry 2.5V, but why no HEV or EV to reflect its green commitments?
22-05-2025
JPJ Unveils New Driving Licence with Enhanced Security
JPJ introduces a redesigned LMM driving licence card with stronger security, limited to Malaysian citizens travelling overseas.
22-05-2025
Increased Fuel Prices From 22 To 28 May
The Ministry of Finance (MoF) has announced the retail prices of all fuels in Malaysia, for the coming week of 22 to 28 May, 2025, the rates are as such.
21-05-2025
Show More
trending_flat