ECRL Kelantan LIne 87.8% Complete, On Track for 2026 Completion

Kumeran Sagathevan

Share via

473570617_915900833935803_4309343137374085889_n.jpg


Malaysia Rail Link (MRL) CEO Datuk Seri Darwis Abdul Razak announced that the 400 KM East Coast Rail Link (ECRL) track installation from Maran, Pahang, to Kota Bharu, Kelantan, has been completed ahead of schedule by two and a half months.

For the first time in Malaysia, the CCPG-500A track-laying machine was used to lay 206 KM of tracks from Dungun, Terengganu, to Kota Bharu, Kelantan. The machine successfully completed its work at Kota Bharu Station, which will also serve as the starting point of the ECRL line.


473573793_915900880602465_3304683280230114542_n.jpg


As of Dec 2024, the ECRL project in Kelantan is 87.8% complete. This progress will help speed up the installation of electrification, signaling, and telecommunications for the remaining 43.86KM stretch in the state.

The Kelantan section includes two stations: Kota Bharu Station (for passengers) and Pasir Puteh Station (for both passengers and cargo). Both stations are expected to be completed by the second quarter of 2026.


473758948_915900903935796_2411794522342733421_n.jpg


The full 665KM ECRL line will connect Kelantan, Terengganu, and Pahang on the East Coast to Selangor on the West Coast. The project is expected to be finished by Dec 2026, with operations starting in Jan 2027. Once complete, this line is expected to boost regional economic growth and transform Malaysia’s rail network.

On ticket prices, Darwis assured that fares will be affordable, with more details to be announced by the Transport Ministry.


Share This Article

More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!

Share via

JPJ Running Numbers

KUALA LUMPUR

VRQ2733

SELANGOR

BST7217

JOHOR

JE3179J

PULAU PINANG

PSF5744

PERAK

APL4862

PAHANG

CFH7429

KEDAH

KGJ1321

NEGERI SEMBILAN

NEL8542

KOTA KINABALU

SJU1383

KUCHING

QAB5687P

Last updated 18 Sep, 2026

Fuel Price

Petrol

RON 95

RM 3.97

+1.38

RON 97

RM 4.90

+1.75

RON 100

RM 7.20

+2.20

VPR

RM 8.23

+2.00

Diesel

EURO 5 B10

RM 5.12

+2.08

EURO 5 B7

RM 5.32

+2.08

Last updated 30 Apr, 2026

Related News

Auto News
Kuantan Welcomes ECRL’s First Trains Ahead of 2027 Operations

Kuantan Welcomes ECRL’s First Trains Ahead of 2027 Operations

The first ECRL electric passenger trains and freight locomotives have arrived in Kuantan as the project moves closer to operations in 2027.

11-02-2026
Auto News
ECRL Fares To Be Announced Ahead of 2027 Launch

ECRL Fares To Be Announced Ahead of 2027 Launch

ECRL fares will be disclosed several months prior to the commencement of operations in January 2027, according to Transport Minister.

30-01-2026
Auto News
ECRL Launch Hinges On System Integration, Jan 2027 Target Maintained

ECRL Launch Hinges On System Integration, Jan 2027 Target Maintained

The ECRL remains on schedule, with system integration and testing now the key focus ahead of its planned Jan 2027 launch.

29-01-2026
Auto News
ECRL First EMU Trains, E-Locos Head To Malaysia For Testing

ECRL First EMU Trains, E-Locos Head To Malaysia For Testing

Malaysia’s East Coast Rail Link gears up as its first EMUs and electric locomotives arrive for testing and future service.

17-12-2025
Auto News
First ECRL Trains Depart China, Remaining Units Arriving Through 2026

First ECRL Trains Depart China, Remaining Units Arriving Through 2026

First ECRL trains depart China, with remaining units scheduled to arrive through 2026.

28-11-2025
Auto News
ECRL Nears Completion with 89% Progress, Operations Set for 2027

ECRL Nears Completion with 89% Progress, Operations Set for 2027

ECRL is on track to begin services from Kota Bharu to Gombak in Jan 2027, as construction progress hits 89%.

Auto News
ECRL Trains Fully Assembled, Ready for Malaysia

ECRL Trains Fully Assembled, Ready for Malaysia

The first batch of trains for the East Coast Rail Link (ECRL) is now ready in Dalian, China.

21-11-2025
Auto News
ECRL Hits 88% Milestone As Key C1B Stretch Completed

ECRL Hits 88% Milestone As Key C1B Stretch Completed

The ECRL project has hit 88% completion with the C1B Segment now successfully completed.

05-11-2025

Latest News

Auto News
Perodua Ativa X Is Now RM53K - Would You Still Buy A Myvi?

Perodua Ativa X Is Now RM53K - Would You Still Buy A Myvi?

The Perodua Ativa X is now RM53,000 after a RM9,500 rebate, just RM1,900 below the Myvi 1.5 H. Here's what you get with each.

17-09-2026
Auto News
BUDI Diesel Can Now Be Transferred Beyond Family - Here's How It Works

BUDI Diesel Can Now Be Transferred Beyond Family - Here's How It Works

BUDI Diesel eligibility can now be transferred beyond immediate family to the actual vehicle user. Here's who qualifies, how to apply and the Sept 27 deadline.

17-09-2026
Auto News
Puspakom Has More Rivals Now. So Why Aren't Car Inspections Getting Cheaper?

Puspakom Has More Rivals Now. So Why Aren't Car Inspections Getting Cheaper?

Puspakom now has rivals for M.V.15 ownership transfer inspections, but fees won't get cheaper. Here's why JPJ is keeping rates standardised.

15-09-2026
Auto News
If You're In Penang And Eyeing A Suzuki, There's A New Showroom To Check Out

If You're In Penang And Eyeing A Suzuki, There's A New Showroom To Check Out

Suzuki has opened a new RM1 million dealership in Juru, Penang, expanding its Malaysian network to 14 sales outlets and 13 service centres.

14-09-2026
Auto News
Malaysia Has More Car Brands Than Ever. So Why Do We Still Choose Proton And Perodua?

Malaysia Has More Car Brands Than Ever. So Why Do We Still Choose Proton And Perodua?

Proton and Perodua account for nearly 63% of Malaysia's new car registrations in 2026. Here's why national brands still dominate despite growing competition.

14-09-2026
Auto News
40,595 Summonses, RM12.18 Million Unpaid. JPJ's Patience Is Running Out

40,595 Summonses, RM12.18 Million Unpaid. JPJ's Patience Is Running Out

JPJ has given 945 transport companies 14 days to settle 40,595 outstanding summonses worth RM12.18 million or face tougher enforcement.

11-09-2026
Auto News
Use The Kelana Jaya LRT? Here's Why Some Stations Won't Open Until 9.30AM

Use The Kelana Jaya LRT? Here's Why Some Stations Won't Open Until 9.30AM

Kelana Jaya LRT track replacement works run from Sept 2026 to Sept 2027. Check the affected stations, Sunday dates and 9.30AM opening times.

10-09-2026
Auto News
Your Car's Windscreen Isn't Just Glass, And This Crash Test Shows Why

Your Car's Windscreen Isn't Just Glass, And This Crash Test Shows Why

Malaysia's first live windscreen crash test at MIROS shows why proper installation, adhesive and curing time matter for vehicle safety.

10-09-2026

Show More

trending_flat
Carz Automedia Malaysia Logo
About Us

CarzAutoMedia: Stay connected to the latest car news! Get instant updates on new releases, industry trends, and automotive innovations. Your go-to source for 24/7 coverage of everything automotive.

© 2026 CariCarz.com. All Rights Reserved.