ECRL Kelantan LIne 87.8% Complete, On Track for 2026 Completion

Malaysia Rail Link (MRL) CEO Datuk Seri Darwis Abdul Razak announced that the 400 KM East Coast Rail Link (ECRL) track installation from Maran, Pahang, to Kota Bharu, Kelantan, has been completed ahead of schedule by two and a half months.
For the first time in Malaysia, the CCPG-500A track-laying machine was used to lay 206 KM of tracks from Dungun, Terengganu, to Kota Bharu, Kelantan. The machine successfully completed its work at Kota Bharu Station, which will also serve as the starting point of the ECRL line.

As of Dec 2024, the ECRL project in Kelantan is 87.8% complete. This progress will help speed up the installation of electrification, signaling, and telecommunications for the remaining 43.86KM stretch in the state.
The Kelantan section includes two stations: Kota Bharu Station (for passengers) and Pasir Puteh Station (for both passengers and cargo). Both stations are expected to be completed by the second quarter of 2026.

The full 665KM ECRL line will connect Kelantan, Terengganu, and Pahang on the East Coast to Selangor on the West Coast. The project is expected to be finished by Dec 2026, with operations starting in Jan 2027. Once complete, this line is expected to boost regional economic growth and transform Malaysia’s rail network.
On ticket prices, Darwis assured that fares will be affordable, with more details to be announced by the Transport Ministry.
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VQD6353
SELANGOR
BSK8493
JOHOR
JYM7917
PULAU PINANG
PRW5654
PERAK
APD3748
PAHANG
CFE4593
KEDAH
KGD4350
NEGERI SEMBILAN
NEH8965
KOTA KINABALU
SJP2853
KUCHING
QAB7426M
Last updated 16 Dec, 2025
Fuel Price
Petrol
RON 95
RM 2.64
-0.02
RON 97
RM 3.27
-0.02
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.06
-0.02
EURO 5 B7
RM 3.26
-0.02
Last updated 11 Dec, 2025
Related News
First ECRL Trains Depart China, Remaining Units Arriving Through 2026
First ECRL trains depart China, with remaining units scheduled to arrive through 2026.
28-11-2025
ECRL Nears Completion with 89% Progress, Operations Set for 2027
ECRL is on track to begin services from Kota Bharu to Gombak in Jan 2027, as construction progress hits 89%.
24-11-2025
ECRL Trains Fully Assembled, Ready for Malaysia
The first batch of trains for the East Coast Rail Link (ECRL) is now ready in Dalian, China.
21-11-2025
ECRL Hits 88% Milestone As Key C1B Stretch Completed
The ECRL project has hit 88% completion with the C1B Segment now successfully completed.
05-11-2025
ECRL Project On Track Despite RM2.9mil Theft Losses
MRL boosts security after 38 theft cases but says the ECRL project remains on schedule.
30-10-2025
MOT Eyes Rail Expansion, Road Safety and Airport Improvements
Transport Minister YB Loke Siew Fook outlines major transport projects and safety reforms under the 2026 Budget.
30-10-2025
ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses
The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.
14-10-2025
Budget 2026: Prasarana Seeks Continued Support for Travel Passes and LRT3
Prasarana moots continued support for travel passes, LRT 3 line completion, cites them as key to easing living costs and improving urban mobility.
09-10-2025
Latest News
Gemas-JB ETS Needs Better Access To Curb City Traffic - Expert
Experts urge improved first-mile access, feeder buses, and park-and-ride options for the Gemas- JB ETS.
16-12-2025
SCS Adopts Advanced European Testing Systems
SCS raises the bar for vehicle inspections with advanced European testing technology.
16-12-2025
Shah Alam LRT Launch Delayed To Avoid Another 2021 Kelana Jaya Crash
Prasarana delays the Shah Alam LRT opening, prioritising passenger safety and thorough testing after past LRT mishaps.
15-12-2025
Federal Highway Won’t Be Upgraded, Costs Deemed Too High
Despite worsening traffic conditions, the Federal Highway will not be upgraded, with the government citing high costs.
15-12-2025
Bollards Are There for Your Safety, Not Decoration - DBKL
DBKL is reminding the public that bollards play a crucial role in keeping pedestrians safe.
15-12-2025
Experts Call For Stricter Rules, Defensive Driving As Road Deaths Rise
Negligent driving caused over 1,200 fatalities this year, prompting calls for tougher enforcement and smarter driver education.
15-12-2025
New KTM Komuter Timetable Starts Jan 1 Amid Track Works
KTMB will roll out a revised KTM Komuter schedule from Jan 1 due to ongoing KVDT2 works.
15-12-2025
Govt Rules Out Tiered RON95 Pricing After 300 litres
Government rules out tiered RON95 prices under BUDI95, keeps RM1.99 for first 300 litres
12-12-2025
Show More
trending_flat