"Wait, Why Is It Taking So Long?" — 4 Things Slowing Down The Pan Borneo Highway In Sabah Right Now

Pan Borneo Highway
If you’ve driven between Sandakan and Lahad Datu lately, you’ve probably spent more time looking at orange traffic cones than actual scenery.
The Pan Borneo Highway is the "dream" project we’ve been waiting for, but let’s be real, the progress bar feels like it’s stuck at 99% loading. Recently, Chief Minister Datuk Seri Hajiji Noor went down to the ground to inspect Work Package 25 (WP25), and he didn’t sugarcoat it.
The 14.96km stretch from Kampung Perpaduan Datuk Moh to Sukau is currently at 12.35% physical progress, slightly behind its 15.30% target. So, what’s the hold-up?
Here are the 4 major "speed bumps" keeping the machines from moving faster:
1. The "Invisible" Utility Maze
This is the big one. Hajiji identified utility relocation as the primary factor slowing down earthworks.
Think about it: before you can build a massive highway, you have to move miles of SESB electricity poles, water pipes, and fiber optic cables that have been there for decades. Moving these requires high-level coordination between agencies, and one wrong move could leave a whole village without water or TikTok.
2. The Logistical Tug-of-War
Moving heavy machinery through rural Sabah isn’t like driving a Myvi to the mall. The CM noted that logistical challenges are a major constraint. Getting raw materials, giant bridge beams, and specialized equipment into areas like Sukau requires precise timing and solid ground, both of which are hard to find in a construction zone.
3. "Temporary Access" Nightmares
We’ve all seen them, those narrow, bumpy diversions that keep you at a 20km/h crawl. These temporary access issues within the project area don't just annoy drivers; they actually slow down the workers too. Managing traffic while trying to build a multi-storey flyover on the same spot is basically a high-stakes game of Tetris.
4. Demolition & Land Dramas

Chief Minister of Sabah, Datuk Seri Hajiji Noor.
You can't build a road where a house is standing. Hajiji mentioned that land acquisition and the demolition of existing structures are still ongoing hurdles. Negotiating with land owners and ensuring everyone is compensated fairly takes time, and until the "site clear" signal is given, the bulldozers have to wait.
Is there light at the end of the tunnel?
Despite the delays, there is a "Save the Date" on the calendar. This RM269.9 million project is scheduled for completion by February 2028.
Once done, WP25 will feature:
- A multi-storey interchange (Flyover)
- Bus stops
- Pedestrian bridges
- Upgraded drainage to prevent those "flash flood" surprises
The government is pushing for closer coordination between agencies to stop the "blame game" and get the tarmac moving. For now, keep your snacks ready and your patience high, the road to a better Sabah is still under construction.
What do you think? Is 2028 a realistic goal or just another "Janji Manis"? Let us know in the comments!
Written By
Sofea Najmi
A Bachelor of English Language and Literature graduate with an obsession for the finer details. Sofea uses her background in translation to decode the technicalities of automotive innovation. She is dedicated to delivering impactful, meticulously researched articles that provide a narrative far beyond the spec sheet. LinkedIn: https://bit.ly/3C018vv
JPJ Running Numbers
KUALA LUMPUR
VRQ7812
SELANGOR
BST8542
JOHOR
JE5243J
PULAU PINANG
PSF6958
PERAK
APL5901
PAHANG
CFH7852
KEDAH
KGJ1946
NEGERI SEMBILAN
NEL9380
KOTA KINABALU
SJU2063
KUCHING
QAB5922P
Last updated 23 Sep, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Latest News
Perodua Ativa X Is Now RM53K - Would You Still Buy A Myvi?
The Perodua Ativa X is now RM53,000 after a RM9,500 rebate, just RM1,900 below the Myvi 1.5 H. Here's what you get with each.
17-09-2026
BUDI Diesel Can Now Be Transferred Beyond Family - Here's How It Works
BUDI Diesel eligibility can now be transferred beyond immediate family to the actual vehicle user. Here's who qualifies, how to apply and the Sept 27 deadline.
17-09-2026
Puspakom Has More Rivals Now. So Why Aren't Car Inspections Getting Cheaper?
Puspakom now has rivals for M.V.15 ownership transfer inspections, but fees won't get cheaper. Here's why JPJ is keeping rates standardised.
15-09-2026
If You're In Penang And Eyeing A Suzuki, There's A New Showroom To Check Out
Suzuki has opened a new RM1 million dealership in Juru, Penang, expanding its Malaysian network to 14 sales outlets and 13 service centres.
14-09-2026
Malaysia Has More Car Brands Than Ever. So Why Do We Still Choose Proton And Perodua?
Proton and Perodua account for nearly 63% of Malaysia's new car registrations in 2026. Here's why national brands still dominate despite growing competition.
14-09-2026
40,595 Summonses, RM12.18 Million Unpaid. JPJ's Patience Is Running Out
JPJ has given 945 transport companies 14 days to settle 40,595 outstanding summonses worth RM12.18 million or face tougher enforcement.
11-09-2026
Use The Kelana Jaya LRT? Here's Why Some Stations Won't Open Until 9.30AM
Kelana Jaya LRT track replacement works run from Sept 2026 to Sept 2027. Check the affected stations, Sunday dates and 9.30AM opening times.
10-09-2026
Your Car's Windscreen Isn't Just Glass, And This Crash Test Shows Why
Malaysia's first live windscreen crash test at MIROS shows why proper installation, adhesive and curing time matter for vehicle safety.
10-09-2026
Show More
trending_flat