"Wait, Why Is It Taking So Long?" — 4 Things Slowing Down The Pan Borneo Highway In Sabah Right Now

Pan Borneo Highway
If you’ve driven between Sandakan and Lahad Datu lately, you’ve probably spent more time looking at orange traffic cones than actual scenery.
The Pan Borneo Highway is the "dream" project we’ve been waiting for, but let’s be real, the progress bar feels like it’s stuck at 99% loading. Recently, Chief Minister Datuk Seri Hajiji Noor went down to the ground to inspect Work Package 25 (WP25), and he didn’t sugarcoat it.
The 14.96km stretch from Kampung Perpaduan Datuk Moh to Sukau is currently at 12.35% physical progress, slightly behind its 15.30% target. So, what’s the hold-up?
Here are the 4 major "speed bumps" keeping the machines from moving faster:
1. The "Invisible" Utility Maze
This is the big one. Hajiji identified utility relocation as the primary factor slowing down earthworks.
Think about it: before you can build a massive highway, you have to move miles of SESB electricity poles, water pipes, and fiber optic cables that have been there for decades. Moving these requires high-level coordination between agencies, and one wrong move could leave a whole village without water or TikTok.
2. The Logistical Tug-of-War
Moving heavy machinery through rural Sabah isn’t like driving a Myvi to the mall. The CM noted that logistical challenges are a major constraint. Getting raw materials, giant bridge beams, and specialized equipment into areas like Sukau requires precise timing and solid ground, both of which are hard to find in a construction zone.
3. "Temporary Access" Nightmares
We’ve all seen them, those narrow, bumpy diversions that keep you at a 20km/h crawl. These temporary access issues within the project area don't just annoy drivers; they actually slow down the workers too. Managing traffic while trying to build a multi-storey flyover on the same spot is basically a high-stakes game of Tetris.
4. Demolition & Land Dramas

Chief Minister of Sabah, Datuk Seri Hajiji Noor.
You can't build a road where a house is standing. Hajiji mentioned that land acquisition and the demolition of existing structures are still ongoing hurdles. Negotiating with land owners and ensuring everyone is compensated fairly takes time, and until the "site clear" signal is given, the bulldozers have to wait.
Is there light at the end of the tunnel?
Despite the delays, there is a "Save the Date" on the calendar. This RM269.9 million project is scheduled for completion by February 2028.
Once done, WP25 will feature:
- A multi-storey interchange (Flyover)
- Bus stops
- Pedestrian bridges
- Upgraded drainage to prevent those "flash flood" surprises
The government is pushing for closer coordination between agencies to stop the "blame game" and get the tarmac moving. For now, keep your snacks ready and your patience high, the road to a better Sabah is still under construction.
What do you think? Is 2028 a realistic goal or just another "Janji Manis"? Let us know in the comments!
Written By
Sofea Najmi
A Bachelor of English Language and Literature graduate with an obsession for the finer details. Sofea uses her background in translation to decode the technicalities of automotive innovation. She is dedicated to delivering impactful, meticulously researched articles that provide a narrative far beyond the spec sheet. LinkedIn: https://bit.ly/3C018vv
JPJ Running Numbers
KUALA LUMPUR
VRX7360
SELANGOR
BSU9305
JOHOR
JH1733J
PULAU PINANG
PSH2985
PERAK
APM7928
PAHANG
CFJ3684
KEDAH
KGJ7458
NEGERI SEMBILAN
NEM5428
KOTA KINABALU
SJV1074
KUCHING
QAB9647P
Last updated 07 Nov, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Latest News
Caricarz Automall Challenges Trade-In Prices, Records 300 Consignment Car Sales in 2026
Caricarz Automall reports 300 vehicle sales in 2026 as its consignment model challenges traditional used-car trade-in and dealer bidding prices.
06-11-2026
Port Klang High Tide Warning: 7-11 November 2026 Forecast And Driver Advice
Port Klang high tides are forecast from 7-11 November 2026, peaking at 5.2m. Check the tide schedule and driving precautions.
06-11-2026
Chery-Sapura RM307 Million Axle Assembly Deal: Models And Malaysia Plans
Chery's RM307 million Sapura axle assembly deal includes Jaecoo J5 and Lepas programmes. Here's what's being assembled in Malaysia.
06-11-2026
Own A Recond Toyota? New Campaign Highlights Official Servicing And Genuine Parts
Own a recond Toyota in Malaysia? Toyota's new service campaign starts from RM469, with genuine parts, certified technicians and warranty benefits.
05-11-2026
Deepavali 2026 Toll Discount: 50% Off Highway Tolls On Nov 6-7
Deepavali 2026 brings a 50% highway toll discount on Nov 6-7. Check the exact timing, eligible vehicles, excluded plazas and travel tips.
05-11-2026
Bukit Jalil Concert Traffic: New Management Plan Expected By February 2027
Fed up with Bukit Jalil concert traffic? Here's what the government is planning, from a February 2027 traffic plan to smart-city solutions.
03-11-2026
BYD Malaysia OneGo App: How To Book A Service And Get RM50 Off
Learn how to book BYD servicing using the OneGo App and get RM50 off. Choose your service centre, advisor and appointment before 31 December 2026.
03-11-2026
Always Wanted A MINI? Its Certified Pre-Owned Programme Is Back In Malaysia
MINI NEXT returns to Malaysia with certified pre-owned MINIs, 360-degree inspections, verified vehicle histories, trade-in options and used electric MINIs.
02-11-2026
Show More
trending_flat
Malaysia First Used Car and EV Consignment Platform
This is the best place to sell your car at true market value. Instead of accepting low dealer trade-ins, we handle everything and connect your car directly to genuine buyers for the highest price.

Understanding CariCarzAutomall Consignment Plan


Approved 200-Check Points Inspection

7 Day Money Back Guarantee

One Year Extended Warranty

No Hidden Charge