Penang Mutiara Line LRT Project Set to Complete in 2030
-full_normal.jpg)
The Malaysian Transport Minister Anthony Loke said that the cabinet has approved the Penang Mutiara Line LRT project which will begin construction this year, with completion expected by 2030.
Mass Rapid Transit Corporation Sdn Bhd (MRT Corp), a subsidiary of the Ministry of Finance Incorporated (MOF), has been chosen as project owner and developer.
-full_normal.jpg)
Meanwhile, SRS Consortium Sdn Bhd (SRS) was awarded the civil construction contract for Segment 1 (Silicon Island to Komtar) following a single-sourcing request for proposal from the Penang state government. Notably, SRS was the project partner for the Penang Transport Master Plan, which was won in an open tender in August 2015.
MRT Corp and SRS are now in negotiations, with a six-month timeframe before making the decision. Meanwhile, building contracts for Segment 2 (Komtar to Penang Sentral) will be given via an open tender process.
Furthermore, Loke stated that all contracts awarded would be for the purpose of building, maintaining and at last transfer basis. He, however, declined to provide the project's cost, citing continuing talks.
-full.jpg)
Furthermore, a rolling stock operations depot will be built beside the integrated transit-oriented development at Tapak Pesta, Sungai Nibong. Once fully operational, both of these projects will provide additional non-fare income, which can be critical for the Penang LRT's ongoing maintenance.
The Mutiara Line LRT will run from Silicon Island to Komtar and then on to Penang Sentral in Seberang Perai, connecting to the existing KTM Komuter and ETS railway lines.
This route spans 29 km long and contains 20 stops, including crucial interchange points at Komtar and Penang Sentral stations.
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VPY1046
SELANGOR
BSJ9038
JOHOR
JYK5801
PULAU PINANG
PRV4463
PERAK
APC3184
PAHANG
CFD9713
KEDAH
KGC8517
NEGERI SEMBILAN
NEH5267
KOTA KINABALU
SJN5357
KUCHING
QAB4754M
Last updated 04 Nov, 2025
Fuel Price
Petrol
RON 95
RM 2.60
RON 97
RM 3.20
+0.06
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.95
+0.06
EURO 5 B7
RM 3.15
+0.06
Last updated 30 Oct, 2025
Related News
Penang LRT: Major Road Diversions in Bayan Lepas from Jan 2026
Traffic along Jalan Sultan Azlan Shah will be cut from three lanes to two for Penang LRT construction, with works stretching until 2028.
03-10-2025
Anwar: 13MP Pushes for Improved Connectivity – Better Buses, Trains and Roads
The 13th Malaysia Plan focuses on better connectivity through buses, trains, roads, and smarter planning.
31-07-2025
Penang On Track And Well-Prepared For Large Scale Projects
Penang will implement extensive traffic management measures to mitigate disruptions from upcoming large-scale projects.
04-06-2025
Mutiara Line LRT: Penang’s RM8.3 Billion Connectivity Investment
Penang’s RM8.31 billion Mutiara Line LRT project begins with the first phase contract signing.
14-01-2025
Penang Mutiara Line LRT Won’t Be Like Kelana Jaya LRT
Penang’s Mutiara Line LRT would run only 2-car train when it begins and would scale up if required.
31-05-2024
Penang Defends Mega Projects As Key To Tackling Traffic Woes
Penang’s transport councillor says flyovers, underpasses and the LRT are essential to ease congestion.
04-09-2025
MRT Corp Justifies RM16.8b Penang LRT Budget
MRT Corp says the RM16.8 billion ceiling for Penang LRT reflects market realities, but MCA wants clearer answers on taxpayers’ money.
21-08-2025
Langkawi LRT ‘Unrealistic’, Focus Stays on Penang LRT and ECRL - Loke
The government is pushing ahead with the Penang LRT and ECRL, but dismissed talk of a Langkawi LRT as unrealistic.
19-08-2025
Latest News
New Audit Move To Keep Highway Concessionaires In Check
Works Ministry will introduce independent audits for highway concessionaires in early 2026.
04-11-2025
BAS.MY Pass Now At RM30 Monthly for Unlimited Bus Rides
BAS.MY services now cost just RM1 a day as the government reduces the 30-day Unlimited Travel Pass from RM50 to RM30.
04-11-2025
RTS Link 65% Complete, First Train Arriving This Month
RTS Link connecting JB and SG is officially 65% complete, with the first train set expected to arrive this month.
03-11-2025
Toyota Skill Contest 2025 Winners Announced
Winners for the Toyota Skill Contest 2025 organised by UMW Toyota Motor have been announced.
03-11-2025
Budi95: Only 0.6% Max Out Quota, Govt Flags Unusual Purchase Near Border
Only 0.6% hit the 300L limit under BUDI95 programme with most recipients using only about 98 litres in Oct.
03-11-2025
RM600 Million Super Magnet Plant Set to Power Malaysia’s EV Ambitions
RM600 million JS Link–Lynas investment drives Malaysia’s push in downstream REE processing for EV and clean energy sectors.
03-11-2025
Datuk Abdul Rashid Musa Returns To Proton As Deputy CEO
Datuk Abdul Rashid Musa returns to Proton as Deputy CEO, succeeding Roslan Abdullah.
03-11-2025
ETS3 To Johor Bahru Set To Roll Out by Mid-December
The ETS3 line is set to launch by mid-Dec, extending the Electric Train Service from Gemas to JB.
03-11-2025
Show More
trending_flat