Penang Mutiara Line LRT Project Set to Complete in 2030
The Malaysian Transport Minister Anthony Loke said that the cabinet has approved the Penang Mutiara Line LRT project which will begin construction this year, with completion expected by 2030.
Mass Rapid Transit Corporation Sdn Bhd (MRT Corp), a subsidiary of the Ministry of Finance Incorporated (MOF), has been chosen as project owner and developer.
Meanwhile, SRS Consortium Sdn Bhd (SRS) was awarded the civil construction contract for Segment 1 (Silicon Island to Komtar) following a single-sourcing request for proposal from the Penang state government. Notably, SRS was the project partner for the Penang Transport Master Plan, which was won in an open tender in August 2015.
MRT Corp and SRS are now in negotiations, with a six-month timeframe before making the decision. Meanwhile, building contracts for Segment 2 (Komtar to Penang Sentral) will be given via an open tender process.
Furthermore, Loke stated that all contracts awarded would be for the purpose of building, maintaining and at last transfer basis. He, however, declined to provide the project's cost, citing continuing talks.
-full.jpg)
Furthermore, a rolling stock operations depot will be built beside the integrated transit-oriented development at Tapak Pesta, Sungai Nibong. Once fully operational, both of these projects will provide additional non-fare income, which can be critical for the Penang LRT's ongoing maintenance.
The Mutiara Line LRT will run from Silicon Island to Komtar and then on to Penang Sentral in Seberang Perai, connecting to the existing KTM Komuter and ETS railway lines.
This route spans 29 km long and contains 20 stops, including crucial interchange points at Komtar and Penang Sentral stations.
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VPM5539
SELANGOR
BSG7726
JOHOR
JYE4987
PULAU PINANG
PRT1064
PERAK
ANY7209
PAHANG
CFD677
KEDAH
KGB6433
NEGERI SEMBILAN
NEG6396
KOTA KINABALU
SJL9999*
KUCHING
QAB8457L
Last updated 04 Aug, 2025
Fuel Price
Petrol
RON 95
RM 2.05
RON 97
RM 3.17
-0.04
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.91
EURO 5 B7
RM 3.11
Last updated 31 Jul, 2025
Related News
Anwar: 13MP Pushes for Improved Connectivity – Better Buses, Trains and Roads
The 13th Malaysia Plan focuses on better connectivity through buses, trains, roads, and smarter planning.
31-07-2025
Penang On Track And Well-Prepared For Large Scale Projects
Penang will implement extensive traffic management measures to mitigate disruptions from upcoming large-scale projects.
04-06-2025
Mutiara Line LRT: Penang’s RM8.3 Billion Connectivity Investment
Penang’s RM8.31 billion Mutiara Line LRT project begins with the first phase contract signing.
14-01-2025
Penang Mutiara Line LRT Won’t Be Like Kelana Jaya LRT
Penang’s Mutiara Line LRT would run only 2-car train when it begins and would scale up if required.
31-05-2024
Penang LRT Stays Within RM16 Billion Budget - MRT Corp
Penang LRT project capped at RM16 billion, with MRT Corp aiming to deliver a cost-efficient system despite rising expenses.
30-07-2025
Penang Still Waiting For Green Light From MOT For LRT project
Penang is set to begin Mutiara LRT construction but awaits final approval from MRT Corp and MOT.
02-07-2025
Mutiara LRT Issues Resolved , Earthworks Commencing Soon
Transport Minister announced that all outstanding issues regarding the Mutiara LRT project have been resolved.
11-06-2025
Penang LRT Project Progressing Steadily - MRT Corp
Construction of the Mutiara Line Penang LRT project is on track, according to MRT Corp.
21-04-2025
Latest News
KPDN Probes SG Driver Sighted Pumping RON95 in Johor
KPDN is probing a viral incident where a Singapore-registered car was seen pumping subsidised RON95 fuel.
04-08-2025
Traffic Diversion On Bukit Gambir-Tangkak From Aug 5
Traffic along the NSE near Tangkak will be diverted in both directions from Aug 5 for bridge construction.
04-08-2025
1,489 Summonses Issued in VEP Enforcement Operation – JPJ
JPJ has issued a total of 1,489 summonses during an enforcement operation on VEP at the JB-Singapore land border.
04-08-2025
No Green Light Yet For Cross-Border Ride-Hailing Between SG, JB.
Singapore holds off on cross-border ride-hailing plans, opting instead to improve its existing taxi scheme with Malaysia.
04-08-2025
RM110 Million Collected from Special Plate Sales Since 2023 – MoT
A total of RM110 million has been collected from sales of special number plates since 2023, the Transport Ministry says.
04-08-2025
Nanta: 80% of Accidents Driver-Linked, Road Budget 70% Short
With 80% of accidents linked to drivers, the Works Ministry still grapples with limited funds to fix and rebuild roads.
04-08-2025
LRT3 Shah Alam Line Opening Could Be Delayed to Oct 31 – Report
The LRT3 Shah Alam line opening could be delayed until Oct 31 instead of the planned launch date of Sept 30.
04-08-2025
ETS to JB Sentral ‘On Track’, But Not Quite There Yet
KTMB says electrification works between Kluang to JB Sentral are ongoing and the extension will proceed once conditions are met.
04-08-2025
Show More
trending_flat