Mutiara Line LRT: Penang’s RM8.3 Billion Connectivity Investment

Transport Minister Anthony Loke recently oversaw the signing of a contract between assigned project developers MRT Corporation and asset owner SRS Consortium. Together, both are set to build the first segment of Penang’s Mutiara Line, the state’s first light rail transit (LRT) project.
The contract for this phase is valued at RM8.31 Billion, excluding land acquisition costs which will be funded by the federal government, with efforts to minimise costs through ongoing negotiations.

The Mutiara Line will span 29.5 KM and feature 21 stations, starting from Penang South Reclamation Island-A (PSR-A) and ending at Penang Sentral and the Tun Abdul Razak Complex (Komtar). A provisional station will also be located on PSR-A.
The line includes three interchange stations: Komtar, Macallum (connecting Penang Sentral and Komtar) and Penang Sentral, which will link with KTM Komuter, ETS, and potential future metro lines.
-full_normal.jpg)
The project is divided into three tenders:
Tender 1: The first package, awarded to SRS Consortium, involves construction of 19 stations over 23.7 KM from PSR-A to Komtar. This segment’s total alignment length is 29.5 KM in a single direction.
Tender 2: Covering the extension from Macallum to Penang Sentral on Seberang Prai, this package includes a 6 KM alignment with a 3.2 KM sea-crossing bridge. The tender is expected to open in Q3 2025 and has attracted significant interest from both local and international bidders.
Tender 3: The Systems Turnkey Contract (STC) focuses on railway systems, encompassing design, procurement, construction, testing, commissioning, and maintenance. This tender opened on Dec 13, 2024, with submissions due by April 14, 2025. A second briefing is scheduled for Jan 14, 2025, in Kuala Lumpur.

The upcoming LRT system will feature Grade 3 Automation driverless electric trains with each train car designed to accommodate up to 405 passengers. Initial operations will see trains running at four-minute intervals to minimise waiting times.
Additionally, to enhance commuter convenience, all stations will include Park N Ride facilities with over 1,000 parking bays available for both cars and motorcycles.
Loke has reaffirmed the federal government’s commitment to managing costs effectively, even with potential land acquisition expenses. He emphasised that negotiations with Penang state government will focus on ensuring nominal land charges through a fair and collaborative approach.
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VQU2966
SELANGOR
BSP3086
JOHOR
JYU9778
PULAU PINANG
PSB4700
PERAK
APG7153
PAHANG
CFG2477
KEDAH
KGF3778
NEGERI SEMBILAN
NEK1565
KOTA KINABALU
SJR4237
KUCHING
QAB5648N
Last updated 22 Apr, 2026
Fuel Price
Petrol
RON 95
RM 2.59
+0.05
RON 97
RM 3.15
+0.05
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.04
+0.05
EURO 5 B7
RM 3.24
+0.05
Last updated 26 Feb, 2026
Related News
Public Review Opens for Revised Penang Mutiara LRT with Cross-Sea Link at Core
MRT Corp opens a three-month public review for the Penang Mutiara LRT, featuring a proposed six-kilometre cross-sea link to Penang Sentral.
23-02-2026
Penang Mutiara LRT Construction Kicks Off Jan 2026
Penang Mutiara Line LRT starts in Jan 2026, with traffic management measures ready to minimise disruptions.
19-11-2025
Penang Sentral Set to Become Mainland’s Integrated Transport Hub
The Butterworth KTM station, Mutiara Line LRT, and airport expansions will turn Penang Sentral into key transport and logistics hub.
11-11-2025
Penang Defends Mega Projects As Key To Tackling Traffic Woes
Penang’s transport councillor says flyovers, underpasses and the LRT are essential to ease congestion.
04-09-2025
MRT Corp Justifies RM16.8b Penang LRT Budget
MRT Corp says the RM16.8 billion ceiling for Penang LRT reflects market realities, but MCA wants clearer answers on taxpayers’ money.
21-08-2025
Langkawi LRT ‘Unrealistic’, Focus Stays on Penang LRT and ECRL - Loke
The government is pushing ahead with the Penang LRT and ECRL, but dismissed talk of a Langkawi LRT as unrealistic.
19-08-2025
Penang LRT Stays Within RM16 Billion Budget - MRT Corp
Penang LRT project capped at RM16 billion, with MRT Corp aiming to deliver a cost-efficient system despite rising expenses.
30-07-2025
Penang Still Waiting For Green Light From MOT For LRT project
Penang is set to begin Mutiara LRT construction but awaits final approval from MRT Corp and MOT.
02-07-2025
Latest News
FREE Oil Changes & 5,000 New Helmets?! JPJ Is Giving Away Some Major Goodies In Penang This Weekend!
Heading to Penang this weekend? JPJ is giving away 5,000 free helmets and 1,500 oil changes at the Batu Kawan Stadium! Check out the full list of freebies and rules here.
21-04-2026
You Can Score 'Cantik' Number Plates For As Low As RM250 In Penang This Weekend
Skip the JPJ eBid drama! Score 'cantik' number plates for as low as RM250 at the JPJ 80th Anniversary Carnival in Penang this weekend. 50,000 numbers available!
21-04-2026
Why "Oil-Rich" Malaysia Still Imports 50% of Its Fuel, And Why That’s a Problem Right Now
Why does oil-rich Malaysia still import 50% of its fuel? We break down the 700k vs 350k barrel deficit and how the West Asia crisis is affecting your petrol price.
21-04-2026
Mitsubishi Just Opened A Massive 21,000 Sq Ft 4S Centre in Miri For All Your Car Needs
Mitsubishi Motors Malaysia opens a massive 21,000 sq ft 4S Centre in Miri with Auto Pacifica! Featuring 13 service bays and Body & Paint services, it's the new home for the Mitsubishi Xforce in Sarawak.
20-04-2026
17x Higher?! MOF Revealed The Real Reason Petrol Prices Are Climbing (And It’s Not Just Crude Oil)
Think petrol is just about crude oil? Think again. MOF revealed that shipping insurance has surged by 17x due to the West Asia conflict.
20-04-2026
Journalists Say New 200L Petrol Cap Is 'Not Enough' To Do Their Jobs. Should They Get More?
Is 200L enough? 14 media clubs are pleading with the Gov to restore the 300L BUDI95 quota.
17-04-2026
From 300 to 8,000 Customers: The 15-Year Evolution of Auto Bavaria Kuala Lumpur
Auto Bavaria Kuala Lumpur celebrates 15 years! Discover how they grew from 300 to 8,000 customers and become Malaysia’s first EV-certified BMW dealer.
16-04-2026
Siti Nurhaliza Injured in 4-Vehicle Collision on MEX Highway
Datuk Seri Siti Nurhaliza involved in a multi-car accident at KM14.2 of the MEX Highway. Management confirms minor injuries and stable condition.
16-04-2026
Show More
trending_flat
