Mutiara Line LRT: Penang’s RM8.3 Billion Connectivity Investment

Transport Minister Anthony Loke recently oversaw the signing of a contract between assigned project developers MRT Corporation and asset owner SRS Consortium. Together, both are set to build the first segment of Penang’s Mutiara Line, the state’s first light rail transit (LRT) project.
The contract for this phase is valued at RM8.31 Billion, excluding land acquisition costs which will be funded by the federal government, with efforts to minimise costs through ongoing negotiations.

The Mutiara Line will span 29.5 KM and feature 21 stations, starting from Penang South Reclamation Island-A (PSR-A) and ending at Penang Sentral and the Tun Abdul Razak Complex (Komtar). A provisional station will also be located on PSR-A.
The line includes three interchange stations: Komtar, Macallum (connecting Penang Sentral and Komtar) and Penang Sentral, which will link with KTM Komuter, ETS, and potential future metro lines.
-full_normal.jpg)
The project is divided into three tenders:
Tender 1: The first package, awarded to SRS Consortium, involves construction of 19 stations over 23.7 KM from PSR-A to Komtar. This segment’s total alignment length is 29.5 KM in a single direction.
Tender 2: Covering the extension from Macallum to Penang Sentral on Seberang Prai, this package includes a 6 KM alignment with a 3.2 KM sea-crossing bridge. The tender is expected to open in Q3 2025 and has attracted significant interest from both local and international bidders.
Tender 3: The Systems Turnkey Contract (STC) focuses on railway systems, encompassing design, procurement, construction, testing, commissioning, and maintenance. This tender opened on Dec 13, 2024, with submissions due by April 14, 2025. A second briefing is scheduled for Jan 14, 2025, in Kuala Lumpur.

The upcoming LRT system will feature Grade 3 Automation driverless electric trains with each train car designed to accommodate up to 405 passengers. Initial operations will see trains running at four-minute intervals to minimise waiting times.
Additionally, to enhance commuter convenience, all stations will include Park N Ride facilities with over 1,000 parking bays available for both cars and motorcycles.
Loke has reaffirmed the federal government’s commitment to managing costs effectively, even with potential land acquisition expenses. He emphasised that negotiations with Penang state government will focus on ensuring nominal land charges through a fair and collaborative approach.
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VRQ4558
SELANGOR
BST7656
JOHOR
JE4089J
PULAU PINANG
PSF6149
PERAK
APL5332
PAHANG
CFH7568
KEDAH
KGJ1493
NEGERI SEMBILAN
NEL8915
KOTA KINABALU
SJU1583
KUCHING
QAB5778P
Last updated 19 Sep, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
Public Review Opens for Revised Penang Mutiara LRT with Cross-Sea Link at Core
MRT Corp opens a three-month public review for the Penang Mutiara LRT, featuring a proposed six-kilometre cross-sea link to Penang Sentral.
23-02-2026
Penang Mutiara LRT Construction Kicks Off Jan 2026
Penang Mutiara Line LRT starts in Jan 2026, with traffic management measures ready to minimise disruptions.
19-11-2025
Penang Sentral Set to Become Mainland’s Integrated Transport Hub
The Butterworth KTM station, Mutiara Line LRT, and airport expansions will turn Penang Sentral into key transport and logistics hub.
11-11-2025
Penang Defends Mega Projects As Key To Tackling Traffic Woes
Penang’s transport councillor says flyovers, underpasses and the LRT are essential to ease congestion.
04-09-2025
MRT Corp Justifies RM16.8b Penang LRT Budget
MRT Corp says the RM16.8 billion ceiling for Penang LRT reflects market realities, but MCA wants clearer answers on taxpayers’ money.
21-08-2025
Langkawi LRT ‘Unrealistic’, Focus Stays on Penang LRT and ECRL - Loke
The government is pushing ahead with the Penang LRT and ECRL, but dismissed talk of a Langkawi LRT as unrealistic.
19-08-2025
Penang LRT Stays Within RM16 Billion Budget - MRT Corp
Penang LRT project capped at RM16 billion, with MRT Corp aiming to deliver a cost-efficient system despite rising expenses.
30-07-2025
Penang Still Waiting For Green Light From MOT For LRT project
Penang is set to begin Mutiara LRT construction but awaits final approval from MRT Corp and MOT.
02-07-2025
Latest News
Perodua Ativa X Is Now RM53K - Would You Still Buy A Myvi?
The Perodua Ativa X is now RM53,000 after a RM9,500 rebate, just RM1,900 below the Myvi 1.5 H. Here's what you get with each.
17-09-2026
BUDI Diesel Can Now Be Transferred Beyond Family - Here's How It Works
BUDI Diesel eligibility can now be transferred beyond immediate family to the actual vehicle user. Here's who qualifies, how to apply and the Sept 27 deadline.
17-09-2026
Puspakom Has More Rivals Now. So Why Aren't Car Inspections Getting Cheaper?
Puspakom now has rivals for M.V.15 ownership transfer inspections, but fees won't get cheaper. Here's why JPJ is keeping rates standardised.
15-09-2026
If You're In Penang And Eyeing A Suzuki, There's A New Showroom To Check Out
Suzuki has opened a new RM1 million dealership in Juru, Penang, expanding its Malaysian network to 14 sales outlets and 13 service centres.
14-09-2026
Malaysia Has More Car Brands Than Ever. So Why Do We Still Choose Proton And Perodua?
Proton and Perodua account for nearly 63% of Malaysia's new car registrations in 2026. Here's why national brands still dominate despite growing competition.
14-09-2026
40,595 Summonses, RM12.18 Million Unpaid. JPJ's Patience Is Running Out
JPJ has given 945 transport companies 14 days to settle 40,595 outstanding summonses worth RM12.18 million or face tougher enforcement.
11-09-2026
Use The Kelana Jaya LRT? Here's Why Some Stations Won't Open Until 9.30AM
Kelana Jaya LRT track replacement works run from Sept 2026 to Sept 2027. Check the affected stations, Sunday dates and 9.30AM opening times.
10-09-2026
Your Car's Windscreen Isn't Just Glass, And This Crash Test Shows Why
Malaysia's first live windscreen crash test at MIROS shows why proper installation, adhesive and curing time matter for vehicle safety.
10-09-2026
Show More
trending_flat