Penang LRT: Major Road Diversions in Bayan Lepas from Jan 2026
-full_normal.jpg)
Major traffic diversions will take place in Bayan Lepas from mid-Jan 2026 as construction of the Penang LRT Mutiara Line gets underway.
According to SRS Consortium project director Adil Putra Ahmad, the first phase will affect Jalan Sultan Azlan Shah between Kampung Jawa and Mayang Pasir. Traffic will be cut from three to two lanes in both directions to allow work on the elevated tracks.
The stretch, over 1KM long, will take about 38 months to complete, with the target set for Dec 2028.
-full_normal.jpg)
-full_normal.jpg)
Traffic control will focus on three main areas: Komtar, Sunny Point and the Free Industrial Zone (FIZ). Adil warned that congestion is unavoidable, while state infrastructure and transport committee chairman Zairil Khir Johari said the state would keep the public updated so drivers can better plan their routes.
He also assured that contractors will follow strict safety measures, especially during the monsoon.
-full_normal.jpg)
The new line will serve key points across the island. Stations are planned at the FIZ, Penang International Airport, Universiti Sains Malaysia, SPICE, and the upcoming Penang Waterfront Convention Centre, with stops through Jelutong, Sungai Pinang and Macallum Street.
A channel crossing will link the island to Penang Sentral, connecting directly to the national rail network.
-full_normal.jpg)
-full_normal.jpg)
“This means someone from Sungai Petani or Padang Besar can take a commuter train to Penang Sentral, transfer to the LRT and continue straight to the airport, USM, Bayan Lepas or Komtar,” Zairil explained.
He described the Mutiara Line as a game-changer, with daily ridership expected to start at 70,000 and grow past 100,000 over time. The system is also expected to cut traffic along the Tun Dr Lim Chong Eu Expressway and surrounding routes.
Source: MalayMail
Gallery
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VQA4730
SELANGOR
BSK2601
JOHOR
JYL3046
PULAU PINANG
PRV7834
PERAK
APC5908
PAHANG
CFE1877
KEDAH
KGD859
NEGERI SEMBILAN
NEH6275
KOTA KINABALU
SJN7132
KUCHING
QAB5351M
Last updated 18 Nov, 2025
Fuel Price
Petrol
RON 95
RM 2.65
+0.05
RON 97
RM 3.25
+0.05
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.07
+0.05
EURO 5 B7
RM 3.27
+0.05
Last updated 13 Nov, 2025
Related News
Penang Police Strengthen Security For Mutiara LRT Project
Penang police are coordinating with agencies to ensure the Mutiara LRT project proceeds safely without compromising public security.
18-11-2025
Mutiara Line LRT: Penang’s RM8.3 Billion Connectivity Investment
Penang’s RM8.31 billion Mutiara Line LRT project begins with the first phase contract signing.
14-01-2025
Penang Mutiara Line LRT Project Set to Complete in 2030
The cabinet has approved the construction of the Penang Mutiara Line LRT Project, with completion expected by 2023.
30-03-2024
Anwar: 13MP Pushes for Improved Connectivity – Better Buses, Trains and Roads
The 13th Malaysia Plan focuses on better connectivity through buses, trains, roads, and smarter planning.
31-07-2025
Penang On Track And Well-Prepared For Large Scale Projects
Penang will implement extensive traffic management measures to mitigate disruptions from upcoming large-scale projects.
04-06-2025
Mutiara Line LRT: Penang’s RM8.3 Billion Connectivity Investment
Penang’s RM8.31 billion Mutiara Line LRT project begins with the first phase contract signing.
14-01-2025
Penang Mutiara Line LRT Won’t Be Like Kelana Jaya LRT
Penang’s Mutiara Line LRT would run only 2-car train when it begins and would scale up if required.
31-05-2024
Penang Mutiara Line LRT Project Set to Complete in 2030
The cabinet has approved the construction of the Penang Mutiara Line LRT Project, with completion expected by 2023.
30-03-2024
Latest News
2026 Proton Saga Garners Over 10,000 Bookings In Just Five Days!
All-new 2026 Proton Saga charts just over 10,000 bookings in just 5 days - one booking placed every 43 seconds!
18-11-2025
Lamborghini Among 92 Luxury Cars Seized In KL JPJ Crackdown
JPJ’s Ops Luxury has targeted high-end offenders since July, issuing over 400 notices and seizing 92 of luxury vehicles.
18-11-2025
Lady Driver Cheats Death Following ECRL Construction Beam Collapse in Batu Caves
Lady driver narrowly escaped death as massive steel structure from the ECRL project collapsed onto her car along the MRR2.
18-11-2025
Penang Police Strengthen Security For Mutiara LRT Project
Penang police are coordinating with agencies to ensure the Mutiara LRT project proceeds safely without compromising public security.
18-11-2025
Works Ministry Reviewing ANPR Toll Payments With JustGo App
Govt is reviewing the ANPR system paired with the JustGo app to streamline toll payments and reduce congestion.
18-11-2025
Activate Your X50 RFID and Win Up to RM500 in Toll Credits
Activate your Proton X50’s built-in Touch ’n Go RFID and stand a chance to earn up to RM500 in toll rebates.
18-11-2025
Trans Borneo Railway Feasibility Study To Conclude By Mid-2026
Govt has begun a feasibility study for the Trans Borneo Railway, which could link Sabah, Sarawak, Brunei and Kalimantan.
18-11-2025
LRT3 Enters Final Testing Phase, Govt Targets Dec 31 Opening
LRT3 line is now in its final round of safety and reliability tests, with its launch date hinging on Dec results.
18-11-2025
Show More
trending_flat