Section 11 Of the West Coast Expressway Will Complete By Year End

Anis

Share via

caricarz-19.jpg

Number of vehicles passing through the WCE has increased by 30%, to 50,000 to 60,000 vehicles per day.

West Coast Expressway Sdn Bhd (WCESB) plans to open four more sections of the West Coast Expressway by the end of the year, including the SKVE, Banting, Assam Jawa, and South Taiping sections.

WCE Highway operations manager Syed Muhd Naguib Syed Mohd told Bernama that the 35-kilometer (km) Section 11, Beruas-South Taiping section is 88% complete and will be operational by the end of the year. According to Naguib, the construction involves elements of engineering, toll, slope, and mechanical work at the moment. He also stated that WCE will construct an animal box culvert as an environmental conservation measure because the route will pass through Bubu Forest Reserve.


“WCE also intended to build two electric vehicle charging stations at Lekir and Teluk Intan, as well as four Rest and Service Areas (R&R) — Teluk Intan R&R (north and south), Sungai Wangi R&R (south), Ayer Tawar R&R (north), and Sg Nyior R&R (north and south)”, he added.
He also stated that the number of vehicles passing through the WCE has increased by 30%, to 50,000 to 60,000 vehicles per day.
“During the recent Aidilfitri celebrations, traffic volume reached 100,000 vehicles a day and 85,000 for Raya Aidiladha,” he said.

caricarz-20.jpg




Tagged:

West Coast Expressway (WCE)
West Coast Expressway Sdn Bhd (WCESB)
Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

Related News

Auto News
WCE: Six New Toll Plazas Planned Along Melaka’s 69 KM Stretch

WCE: Six New Toll Plazas Planned Along Melaka’s 69 KM Stretch

WCE set to add six new tolls along Melaka’s 69 KM stretch to ease congestion and spread out traffic flow.

Auto News
WCE Reports 48% Jump In Toll Revenue, Eyes Full Completion By 2027

WCE Reports 48% Jump In Toll Revenue, Eyes Full Completion By 2027

Toll collections on the WCE surged 48% in Q2 to RM44.1 million, with the firm aiming for full completion by March 2027.

27-11-2025
Auto News
Court Upholds Land Takeover For WCE Despite Residents’ Complaint

Court Upholds Land Takeover For WCE Despite Residents’ Complaint

Judge rules the acquisition for WCE valid even without direct notice, as Kampung Jawa landowners gear up for a crucial valuation hearing.

26-11-2025
Auto News
WCE Road Closure on Nov 9 For Klang Royal City Marathon 2025

WCE Road Closure on Nov 9 For Klang Royal City Marathon 2025

Parts of West Coast Expressway (WCE) will temporarily close for Klang Royal City Marathon on Sunday, Nov 9 2025.

Auto News
Selangor Govt Will Decide Fate Of 19 WCE-Affected Residents

Selangor Govt Will Decide Fate Of 19 WCE-Affected Residents

The Selangor govt is set to decide soon on the fate of 19 Kampung Jawa residents affected by the West Coast Expressway project.

Auto News
Hauliers Warn WCE Delays Hurting Logistics and Economy

Hauliers Warn WCE Delays Hurting Logistics and Economy

The Association of Malaysian Hauliers says delays in completing Section 3 of the WCE are disrupting cargo flow and driving up costs.

29-09-2025
Auto News
West Coast Expressway On Track For 2027 Completion

West Coast Expressway On Track For 2027 Completion

The West Coast Expressway is on track for full completion by 2027, with eight of its 11 sections already open.

27-08-2025
Auto News
Hauliers Demand Swift WCE Land Fix

Hauliers Demand Swift WCE Land Fix

Association of Malaysian Hauliers urges swift resolution of land disputes delaying completion of the WCE Section 3.

11-08-2025

Latest News

Auto News
Federal Highway Won’t Be Upgraded, Costs Deemed Too High

Federal Highway Won’t Be Upgraded, Costs Deemed Too High

Despite worsening traffic conditions, the Federal Highway will not be upgraded, with the government citing high costs.

Auto News
Bollards Are There for Your Safety, Not Decoration - DBKL

Bollards Are There for Your Safety, Not Decoration - DBKL

DBKL is reminding the public that bollards play a crucial role in keeping pedestrians safe.

15-12-2025
Auto News
Experts Call For Stricter Rules, Defensive Driving As Road Deaths Rise

Experts Call For Stricter Rules, Defensive Driving As Road Deaths Rise

Negligent driving caused over 1,200 fatalities this year, prompting calls for tougher enforcement and smarter driver education.

15-12-2025
Auto News
New KTM Komuter Timetable Starts Jan 1 Amid Track Works

New KTM Komuter Timetable Starts Jan 1 Amid Track Works

KTMB will roll out a revised KTM Komuter schedule from Jan 1 due to ongoing KVDT2 works.

15-12-2025
Auto News
Govt Rules Out Tiered RON95 Pricing After 300 litres

Govt Rules Out Tiered RON95 Pricing After 300 litres

Government rules out tiered RON95 prices under BUDI95, keeps RM1.99 for first 300 litres

12-12-2025
Auto News
Hyundai Partners EON, Expands Local Network

Hyundai Partners EON, Expands Local Network

Hyundai and EON have signed a LOI to open two new dealerships in Klang Valley and Penang.

Auto News
Perodua Traz/Nexis D66B Set to Debut on December 17

Perodua Traz/Nexis D66B Set to Debut on December 17

The long-awaited Perodua Traz/Nexis D66B SUV is set to make its official debut later on December 17, 2025.

12-12-2025
Auto News
Gemas-JB Electrified Train Cuts KL-Johor Travel To 4 Hours

Gemas-JB Electrified Train Cuts KL-Johor Travel To 4 Hours

The new electrified Gemas-Johor Bahru train line slashes travel time from KL to Johor to just 4 hours 20 minutes.

12-12-2025