WCE: 29.5 KM Tanjong Karang-Assam Jawa Section is 71% Complete.

Kumeran Sagathevan

Share via

WCE-Sec-7-(3).jpg


According to Works Minister Datuk Seri Alexander Nanta Linggi, the Tanjong Karang-Assam Java section of the West Coast Expressway (WCE) has reached 71% completion and is scheduled to be completed by March 2026.

This stretch runs 29.5 KM and is separated into two sections: Section 7A and Section 7B.


WCE-Sec-7-(6).jpg


"Section 7A covers the stretch from Assam Java Interchange to Sungai Terap Farm, totaling 19.5 KM, while Section 7B extends from Sungai Terap Farm to Tanjong Karang Interchange, covering 10 KM," said Nanta. "As of April, Section 7A is 91% complete, and Section 7B is at 44%."

Speaking to reporters after inspecting the project's progress, Nanta stated that the new route will reduce traffic congestion, especially on weekends and during the holiday season.


WCE-Sec-7-(5).jpgWCE-Sec-7-(2).jpg


Once completed, this segment is expected to save up to an hour of travel time compared to the present federal road. It’s also tipped to reduce traffic density on the North-South Highway by offering an alternate route.

Nanta also acknowledged the difficulties in constructing these sections due to the soft soil structure, which necessitated tiered reclamation operations. However, he expressed optimism that the project will be finished on time.



Source: BERNAMA



Tagged:

West Coast Expressway (WCE)
Tanjong Karang and Assam Jawa WCE
Public Works Minister Datuk Seri Alexander Nanta Linggi
Share This Article

Written By

Kumeran Sagathevan

More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!

Share via

Related News

Auto News

Hauliers Demand Swift WCE Land Fix

Association of Malaysian Hauliers urges swift resolution of land disputes delaying completion of the WCE Section 3.

11-08-2025
Auto News

230km Southern WCE Feasibility Study To Conclude By Dec

Study underway on 230km WCE from Banting to Gelang Patah to ease North-South Expressway jams.

08-08-2025
Auto News

WCE Sec 2 Toll Enabled; Responds to Klang Eviction Claims

WCE starts toll operations in Seksyen 2 and clarifies illegal evictions claims.

Auto News

Hari Raya 2025: Over 140K Vehicles Expected Daily on WCE

Over 140,000 vehicles are expected to use the WCE daily during this upcoming Hari Raya Aidilfitri festive season.

24-03-2025
EV

WCE Section 2 Opens with 240 kW DC Handal Charging Station

WCE Section 2 opens today toll free till 22 Feb, features 240 kW DCFC station by DC Handal.

Auto News

ECRL Kelantan LIne 87.8% Complete, On Track for 2026 Completion

ECRL project makes swift progress to reach 87.8% completion, and it appears on track for planned 2027 launch.

Auto News

WCE Sees 83% Increment In Traffic & 128% Increment In Toll Collection

WCE sees increased average daily traffic volume by 83% supported by a boost in toll income by 128%.

Auto News

WCE Extension Banting-Gelang Patah Set To Provide NSE Alternative

WCE, which will connect Banting to Gelang Patah, is set to reduce the traffic congestion on the NSE.

04-11-2024

Latest News

Auto News

Updated Fuel Prices From 14 To 20 August

The Ministry of Finance (MoF) has announced the retail prices of all fuels in Malaysia, for the coming week of 14 to 20 August, 2025, the rates are as such.

13-08-2025
Auto News

iCaur Malaysia Established New Components Hub

iCaur Malaysia, ahead of the iCaur 03 launch, has opened an 88,000 square feet Components Hub in Shah Alam.

Auto News

Abandoned Cars In Cyberjaya Stir Safety Fears

Viral TikTok shows abandoned, damaged cars in Cyberjaya sparking public frustration and safety concerns.

13-08-2025
Auto News

R&M, Govt in Final Talks to Revive Stalled MEX II Highway

The government and sukuk holders are finalising a rescue plan for the stalled MEX II Highway.

Auto News

Malaysian Transport Safety Board Proposal Back on Table – MOT

The Ministry of Transport is drafting a policy to establish the Malaysian Transport Safety Board (MTSB).

13-08-2025
Auto News

Johor Demands Stiffer Penalties For Foreign RON95 Buyers

Johor Wants Heavier Punishment for Foreign-Registered Vehicle Owners Buying Subsidised RON95.

13-08-2025
Auto News

RM68 SMART Tunnel Pass Offers Unlimited Travel This Merdeka

Unlimited SMART Tunnel travel from Aug 16 to Sept 16 for just RM68 with the MUTP.

Auto News

Diesel Smuggling Bust at Bukit Kayu Hitam Nets RM380k in Seizures

AKPS foiled a diesel smuggling attempt, seizing RM380k worth of fuel and vehicles.

13-08-2025