New Juru-Sungai Dua Highway Project - Q4 2025 Start, 2030 Completion

Kumeran Sagathevan

Share via

481900270_1045347884281966_8962089833125402567_n.jpg


The Juru-Sungai Dua Elevated Highway construction is set to begin in the final quarter (Q4) of this year (2025), and is expected to be fully completed by 2030.

Once complete this highway aims to address the heavy traffic congestion issue between the Juru and Sungai Dua toll plazas - key areas targeted are Penang Bridge, Prai, Permatang Pauh and Sungai Dua.

The highways which would span 17.4 KM long, with 9 KM of elevated roadway will be developed in eight phases. To improve traffic flow, it will feature intersections without traffic lights and two elevated U-turns.


481340131_1184486906380130_6110609291251030492_n.jpg


Several major interchanges, including the Juru Utara (Autocity) interchange, the Penang Bridge interchange and a new flyover at Jalan Tun Hussein Onn, will also be upgraded as part of the project.

State Infrastructure Committee chairman Zairil Khir Johari confirmed that the project has been carefully planned together with the Works Ministry, the Malaysian Highway Authority and PLUS.

Construction is scheduled to officially start in late 2025 and will take approximately three years to complete. While the final cost is still being determined, it is expected to be lower than the RM3 billion originally estimated.

481903738_1045347817615306_7259334006769051306_n.jpg

The project was initially estimated to cost only RM1.8 billion when first announced by Deputy Works Minister, Datuk Seri Ahmad Maslan.

The new highway will implement a system similar to the one in Ipoh, where local traffic is separated from through traffic to reduce congestion. A Traffic Management Plan will also be put in place to minimize disruptions during construction.

This project is a part of broader infrastructure upgrades for Penang, which also include the Penang Light Rail Transit (LRT), the expansion of Penang International Airport and the development of Batu Kawan Industrial Park 3. 


Source: NSTP

Tagged:

Juru–Sungai Dua Elevated Highway
Penang State Infrastructure Committee chairman Zairil Khir Johari
Deputy Works Minister, Datuk Seri Ahmad Maslan
Penang Light Rail Transit (LRT)
Share This Article

Written By

Kumeran Sagathevan

More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!

Share via

Related News

Auto News
Penang On Track And Well-Prepared For Large Scale Projects

Penang On Track And Well-Prepared For Large Scale Projects

Penang will implement extensive traffic management measures to mitigate disruptions from upcoming large-scale projects.

04-06-2025
Auto News
Maslan: 15 KM Juru-Sungai Dua Elevated Highway To Cost RM1.8B

Maslan: 15 KM Juru-Sungai Dua Elevated Highway To Cost RM1.8B

The Juru-Sungai Dua Elevated Highway is set to cost RM1.8B, project will be undertaken by PLUS on a Public-Private Partnership basis.

Auto News
Penang Defends Mega Projects As Key To Tackling Traffic Woes

Penang Defends Mega Projects As Key To Tackling Traffic Woes

Penang’s transport councillor says flyovers, underpasses and the LRT are essential to ease congestion.

04-09-2025
Auto News
PLUS Eyes MLFF ANPR Toll Trials Using JustGo Digital App

PLUS Eyes MLFF ANPR Toll Trials Using JustGo Digital App

PLUS will begin trials for automatic number plate recognition (ALPR) toll system with its JustGo Digital App, part of proposed MLFF system, across nine toll plazas this month.

Latest News

Auto News
PLUS To Close Two Bangi Ramps Nightly Until Nov 28

PLUS To Close Two Bangi Ramps Nightly Until Nov 28

PLUS will close two ramps near Bangi nightly from 10PM to 5AM starting today until Nov 28.

10-11-2025
Auto News
KLIA Aerotrain Halts Daily Midnight To 5am For Maintenance

KLIA Aerotrain Halts Daily Midnight To 5am For Maintenance

KLIA Aerotrain will stop running every night from midnight to 5am for routine checks and maintenance.

10-11-2025
Auto News
4.4 Mil Old Vehicles Threaten Road Safety, Incentive Alone Insufficient

4.4 Mil Old Vehicles Threaten Road Safety, Incentive Alone Insufficient

JPJ data shows over 4.4 million old vehicles are still on the road making up about 17% of the country’s 25.7m active vehicles.

10-11-2025
Auto News
Proton Shifts 15,575 Units In Oct 2025, Outgoing Saga Still Leads

Proton Shifts 15,575 Units In Oct 2025, Outgoing Saga Still Leads

Proton closes Oct 2025 by shifting 15,575 units, outgoing Saga sales spikes to 12-year high ahead of successor’s debut.

10-11-2025
Auto News
JPJ Warns Public Against Fake “Free Driving Licence” TikTok Scams

JPJ Warns Public Against Fake “Free Driving Licence” TikTok Scams

JPJ has warned the public about fake TikTok posts claiming people can get free driving licences without any tests.

10-11-2025
Auto News
RM3b Juru–Sungai Dua Link Cuts Travel Time To Just  20 Minutes

RM3b Juru–Sungai Dua Link Cuts Travel Time To Just 20 Minutes

RM3 billion traffic dispersal project aims to slash travel time between Juru and Sungai Dua from an hour to just 20 minutes.

Auto News
Nanta: Barrier-Free ANPR Toll System Still at RFP Stage

Nanta: Barrier-Free ANPR Toll System Still at RFP Stage

The Works Ministry is inviting proposals for an ANPR-based barrier-free MLFF toll system.

Auto News
New Leapmotor 3S Showroom Opens In Ipoh, Perak

New Leapmotor 3S Showroom Opens In Ipoh, Perak

Perak state capital of Ipoh gains new Leapmotor brand 3S showroom and service outlet operated by dealers CST Auto.

07-11-2025