The RM141.6 million project to construct a six-lane road connecting Thailand's Sadao CIQ Complex and Malaysia's ICQS Complex is progressing well. Having commenced after site possession in June of the previous year, the project has reached 47% physical completion.

Works Minister Datuk Seri Alexander Nanta Linggi anticipates that the road will be finished by September.

“The site possession date for this project was June 21, 2024, and it is scheduled for completion in September this year… However, I’ve been informed by the contractor and those involved in the project that it may be completed slightly earlier.

“That’s good news. If we can complete it ahead of schedule, that would be great… As of April 29, the physical progress stands at 47%, which is slightly behind. However, I’ve been informed that it can still be completed as planned,” he says.

photo_2025-05-03_12-09-51_1746245653.jpg


Upon the project's completion, the improved border entry will maintain efficient and uninterrupted traffic flow. Nanta emphasized that these road upgrades at this crucial border crossing will significantly enhance the mobility, accessibility, and safety of road users.

The road alignment project includes the construction of a 900-meter six-lane dual carriageway, a 300-meter service road providing access to the Bukit Kayu Hitam general operations force's tactical headquarters, the final control post building, and a covered entrance gate.
2019-Subaru-Forester-review-Penang-to-Bangkok-official-17.jpg

It will also involve the demolition of current structures and the erection of new buildings and facilities for the 5th Battalion Camp of the Border Regiment in Bukit Kayu Hitam.

Tagged:

BUKIT KAYU HITAM ICQS-SADAO CIQ PROJECT
Public Works Minister Datuk Seri Alexander Nanta Linggi
Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

Related News

Auto News
Govt Yet to Decide on Toll-Free Travel for Next Year’s Festive Season

Govt Yet to Decide on Toll-Free Travel for Next Year’s Festive Season

Govt has yet to decide on bringing back toll-free travel for next year’s festive season, says the Works Minister.

25-07-2025
Auto News
East-West Highway Safe, More Upgrades Coming - Works Minister

East-West Highway Safe, More Upgrades Coming - Works Minister

The Works Ministry told Bernama the JRTB is safe for users, but more upgrades are on the way under the 13th Malaysia Plan.

22-07-2025
Auto News
New Marang Bridge 55% Done, Set to Finish By Jan 2027

New Marang Bridge 55% Done, Set to Finish By Jan 2027

The RM338mil Marang Bridge project is over halfway complete and on track for January 2027.

15-07-2025
Auto News
KKR Only Gets Half of RM4B Needed for Road Repairs – Ahmad Maslan

KKR Only Gets Half of RM4B Needed for Road Repairs – Ahmad Maslan

The Public Works Ministry only received half of the RM 4 billion required to repair the damaged roads in Malaysia.

30-06-2025
Auto News
RM4b Needed, Critical Road Repairs Come First

RM4b Needed, Critical Road Repairs Come First

Road repairs will be done in stages due to budget limits, with priority on the most severe sections.

19-06-2025
Auto News
Works Minister: Tapah Smoother Now, WISE to Offer Alternative to Menora

Works Minister: Tapah Smoother Now, WISE to Offer Alternative to Menora

With the Tapah traffic project now complete, the Works Ministry eyes the upcoming WISE highway - a new alternative to the Menora Tunnel route. o

Auto News
Works Ministry Considering Motorcycle Lanes On Future Highways

Works Ministry Considering Motorcycle Lanes On Future Highways

The Works Ministry is considering adding motorcycle lanes to new highways to improve safety.

16-04-2025
Auto News
Works Minister Demands Urgent Report On Kluang Pothole Crash

Works Minister Demands Urgent Report On Kluang Pothole Crash

Works Minister demanded a swift report on the poor maintenance of Jalan Sengkang-Felda Inas-Bandar Tenggara road.

28-03-2025

Latest News

Auto News
Own Damage Knock for Knock Brings Faster Repair Settlements

Own Damage Knock for Knock Brings Faster Repair Settlements

Drivers not at fault in accidents can now claim Own Damage Knock for Knock repair from insurers, with NCDs left untouched.

Auto News
Delayed EKVE Phase One Finally Opened With  30-Day Toll-Free Span

Delayed EKVE Phase One Finally Opened With 30-Day Toll-Free Span

Phase one of EKVE finally opens six years behind schedule, concessionaires offer 30-day toll-free run.

Auto News
New Isuzu 3S Outlet Opens in Kuantan, Pahang

New Isuzu 3S Outlet Opens in Kuantan, Pahang

Isuzu Malaysia sees local network strengthened with newly opened 3S centre in Kuantan, Pahang.

29-08-2025
Auto News
Road Closures In Seremban Ahead Of Merdeka

Road Closures In Seremban Ahead Of Merdeka

Several major roads in Seremban will close this week for National Day rehearsals and celebrations.

29-08-2025
Auto News
Malaysians Told To Ignore False Claims Of RON95 Rationing

Malaysians Told To Ignore False Claims Of RON95 Rationing

The Finance Ministry has denied viral claims of RON95 rationing and urged Malaysians to beware of suspicious messages and links.

29-08-2025
Auto News
Johor Speeds Up Road Repairs with Pothole Pro JCB

Johor Speeds Up Road Repairs with Pothole Pro JCB

Johor lead Asia-Pacific region by adopting Pothole Pro JCB for faster, longer-lasting road repairs.

Auto News
Loke: KLIA Taxi Touting Betrays Nation’s Image

Loke: KLIA Taxi Touting Betrays Nation’s Image

KLIA taxi touts overcharging tourists by up to RM400 are tarnishing Malaysia’s reputation.

Auto News
PLUS Expects 2.2 Million Vehicles This Merdeka Weekend

PLUS Expects 2.2 Million Vehicles This Merdeka Weekend

PLUS is bracing for 2.2 million vehicles daily over the Merdeka weekend and is urging drivers to plan ahead using its updated app.

29-08-2025