Bukit Kayu Hitam ICQS-Sadao CIQ Project On Track For Completion This Year
Anis
1 hour ago
The RM141.6 million project to construct a six-lane road connecting Thailand's Sadao CIQ Complex and Malaysia's ICQS Complex is progressing well. Having commenced after site possession in June of the previous year, the project has reached 47% physical completion.
Works Minister Datuk Seri Alexander Nanta Linggi anticipates that the road will be finished by September.
“The site possession date for this project was June 21, 2024, and it is scheduled for completion in September this year… However, I’ve been informed by the contractor and those involved in the project that it may be completed slightly earlier.
“That’s good news. If we can complete it ahead of schedule, that would be great… As of April 29, the physical progress stands at 47%, which is slightly behind. However, I’ve been informed that it can still be completed as planned,” he says.
Upon the project's completion, the improved border entry will maintain efficient and uninterrupted traffic flow. Nanta emphasized that these road upgrades at this crucial border crossing will significantly enhance the mobility, accessibility, and safety of road users.
The road alignment project includes the construction of a 900-meter six-lane dual carriageway, a 300-meter service road providing access to the Bukit Kayu Hitam general operations force's tactical headquarters, the final control post building, and a covered entrance gate.
It will also involve the demolition of current structures and the erection of new buildings and facilities for the 5th Battalion Camp of the Border Regiment in Bukit Kayu Hitam.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VPC3129
SELANGOR
BSE4918
JOHOR
JXW6049
PULAU PINANG
PRQ3994
PERAK
ANV4065
PAHANG
CFB6809
KEDAH
KGA4473
NEGERI SEMBILAN
NEF7369
KOTA KINABALU
SJK7648
KUCHING
QAB3192L
Last updated 06 May, 2025
Fuel Price
Petrol
RON 95
RM 2.05
RON 97
RM 3.18
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.88
EURO 5 B7
RM 3.08
Last updated 01 May, 2025
Related News
Works Minister: Tapah Smoother Now, WISE to Offer Alternative to Menora
With the Tapah traffic project now complete, the Works Ministry eyes the upcoming WISE highway - a new alternative to the Menora Tunnel route. o
02-05-2025
Works Ministry Considering Motorcycle Lanes On Future Highways
The Works Ministry is considering adding motorcycle lanes to new highways to improve safety.
16-04-2025
Works Minister Demands Urgent Report On Kluang Pothole Crash
Works Minister demanded a swift report on the poor maintenance of Jalan Sengkang-Felda Inas-Bandar Tenggara road.
28-03-2025
Government Announces 50% Toll Discount for Hari Raya Aidilfitri Travel
50% toll discount announced for Hari Raya Aidilfitri travel on March 28 & 29.
26-03-2025
Potholes Must Be Fixed Within 24 Hours - Works Minister
The Works Minister urged the Federal road concessionaires to temporarily patch damaged roads within 24 hours.
24-03-2025
LTU Expressway Not Opening For Aidilfitri - Works Minister
The Works Minister denied claims that the LTU Expressway would be open for Aidilfitri.
24-03-2025
No Lane Closures for Roadworks - March 24 to April 7
Aidilfitri holiday - highway maintenance work involving lane closures will be paused from March 24 to April 7
21-03-2025
Maslan: Festive Toll Exemptions May Return; MIC Backs Chinese Community's Call
Maslan hints at revisiting festive toll exemptions as MIC also advocates for the Chinese community’s entitlement to free tolls.
24-01-2025
Latest News
Govt Urged To Delay Targeted RON95 Subsidy Due To US Tariffs
Lawmakers are urging the government to postpone its proposed RON95 subsidy rationalization due to US tariffs.
06-05-2025
Toyota GR86 Cup Car On Sale In Malaysia – 30 Units Only, RM208,315 Each
Toyota GR86 Cup Car now in sale locally through Haro Sports and Entertainment Sdn Bhd, just 30 units available at RM208,315 each.
06-05-2025
Ekovest Gets Green Light for LIKE and KBL Expressway Projects
Ekovest has received government approval to proceed with the LIKE and KBL expressway projects under its highway expansion plan.
06-05-2025
Bukit Kayu Hitam ICQS-Sadao CIQ Project On Track For Completion This Year
Bukit Kayu Hitam ICQS-Sadao CIQ project is 47% finished and expected to be completed by Sept.
06-05-2025
Myvi, Yamaha 135LC Most Involved In Accidents, Toyota Hilux Most Stolen
In 2024, the Perodua Myvi and Yamaha 135LC were most frequently involved in accidents, while the Toyota Hilux was the most stolen vehicle.
06-05-2025
Sisma Auto Opens New BYD Outlet At IPC
Sisma Auto opens a new BYD showroom outlet located in IPC Shopping Centre, Mutiara Damansara.
05-05-2025
Petronas Kimanis Station Trialling RON97 Supply For Bruneians
KPDN and PDB are trialing the sale of RON97 fuel to Bruneian motorists at the Kimanis Petronas Station.
05-05-2025
Massive Blaze Destroys 20 Cars, Three Motorcycles At Puchong Jaya Workshop
A Saturday morning fire at a Bukit Jalil Highway workshop in Bandar Puchong Jaya destroyed three motorcycles and 20 cars.
05-05-2025
Show More
trending_flat