Kuching Urban Transportation System Anticipated To Commence In 2028

Anis

Share via

KUTS-487426150_1139772181496910_3284735880903202910_n-1024x768.jpg
The first phase of the Kuching Urban Transport System (KUTS) project is 29.89% complete as of April this year, slightly behind the projected 33.86% completion rate.

State Deputy Transport Minister Datuk Dr. Jerip Susil told the Sarawak Legislative Assembly that phase one will commence operations incrementally. The initial Blue Line segment, connecting Rembus to Riveria, is now anticipated to begin service in the fourth quarter of the following year.

"This is later than the initially targeted date due to construction delays," he told See Chee How (IND-Batu Lintang) ,adding that the full operation of the entire phase one is expected to commence in 2028.
Muhammad-Kifli-Ma-Hassan.---2025-05-21T153257.566.png

In response to a follow-up query from See, Jerip clarified that the first phase of KUTS will include the construction of two elevated autonomous rapid transit (ART) stations along Jalan Wan Alwi in Batu Lintang.

These two stations, according to him, will be located in front of Vivacity Megamall and near Kuching Lodge School, and the entire Jalan Wan Alwi stretch will be an elevated alignment or road.

"Meanwhile, there will be one station in front of the Public Works Department divisional office with an elevated design for Batu Lintang area," he added.

The initial phase of the Kuching Urban Transportation System (KUTS) project will establish three Autonomous Rail Transit (ART) lines, encompassing approximately 69.9 kilometers and featuring 31 stations. Muhammad-Kifli-Ma-Hassan.---2025-05-21T153345.782.png


These include the 12.3 km Red Line from Kuching Sentral to Pending, the 30 km Green Line connecting Pending and Damai Central, and the 27.6 km Blue Line which will run between Rembus (Kota Samarahan) and Hikmah Exchange in the city center.







Tagged:

Kuching Urban Transport System (KUTS)
KUTS
autonomous rapid transit (ART)
Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

Related News

Auto News
ART Trackless Trams Trial Run In Putrajaya Till 31 July - Free Rides Offered

ART Trackless Trams Trial Run In Putrajaya Till 31 July - Free Rides Offered

PPj and MOT begin ART Trackless Tram trail run till July 31, and free rides are offered to gauge public reception.

Auto News
Faizal: Johor ART Necessary To Minimise RTS Station Congestion

Faizal: Johor ART Necessary To Minimise RTS Station Congestion

The ART system in Johor Bahru can be an immediate solution to manage RTS Link congestion before completion of the LRT line.

Auto News
Johor State Govt Mulls ART System Alongside RTS Link

Johor State Govt Mulls ART System Alongside RTS Link

The Johor state government proposes the implementation of the ART system to combat congestion alongside the RTS Link.

Auto News
Sarawak Set To Become Asia's First Hydrogen-Powered Economy!

Sarawak Set To Become Asia's First Hydrogen-Powered Economy!

Sarawak to begin large-scale commercial production of green hydrogen by 2027 to promote renewable energy and minimise the region's carbon footprint.

Auto News
Sarawak State Govt. To Endorse Hydrogen-Powered ART Vehicles Including Buses

Sarawak State Govt. To Endorse Hydrogen-Powered ART Vehicles Including Buses

Sarawak state government has announced its plans to promote hydrogen-powered public vehicles among locals.

23-03-2023

Latest News

Auto News
Over 39,000 Road Issues Flagged On MyJalan App Since Launch

Over 39,000 Road Issues Flagged On MyJalan App Since Launch

MyJalan app logs over 39,000 complaints, but most fall outside federal jurisdiction, says Deputy Works Minister.

07-08-2025
Auto News
PLUS Eyes MLFF ANPR Toll Trials This Month - JustGo Digital App

PLUS Eyes MLFF ANPR Toll Trials This Month - JustGo Digital App

PLUS will begin trials for automatic number plate recognition (ALPR) toll system with its JustGo Digital App, part of proposed MLFF system, across nine toll plazas this month.

Auto News
Kelana Jaya Line Signalling Works Delayed, Phase 2 Work Starts Sept 6

Kelana Jaya Line Signalling Works Delayed, Phase 2 Work Starts Sept 6

Kelana Jaya Line Phase 2 and 3 signalling works will now begin on Sept 6, with select stations opening later on affected dates.

Auto News
UMW Toyota Jul y2025 Sales Total At 8,877 Units

UMW Toyota Jul y2025 Sales Total At 8,877 Units

UMW Toyota sees its sales for July 2025 total at 8,877 units, YTD total now up to 53,163 units.

07-08-2025
Auto News
RM25 Million Allocated to Light Up Dark Federal Roads – KKR

RM25 Million Allocated to Light Up Dark Federal Roads – KKR

The Works Ministry has allocated RM25 million to light up dark federal roads to prevent future accidents.

07-08-2025
Auto News
Ops Pengarah: 252 Fined, One With Road Tax Expired For 2 Years

Ops Pengarah: 252 Fined, One With Road Tax Expired For 2 Years

JPJ’s Ops Pengarah nabs dozens driving without licence, including one with road tax expired for two years.

07-08-2025
Auto News
Aerotrain Disruption A Minor Glitch, ETS3 Project On Track - Loke

Aerotrain Disruption A Minor Glitch, ETS3 Project On Track - Loke

KLIA’s Aerotrain glitch was a minor software bug, not a breakdown, while ETS3 to Johor Bahru is on track, says Transport Minister.

07-08-2025
Auto News
Updated Fuel Prices From 07 To 13 August

Updated Fuel Prices From 07 To 13 August

The Ministry of Finance (MoF) has announced the retail prices of all fuels in Malaysia, for the coming week of 07 to 13 August, 2025, the rates are as such.

06-08-2025